64Lead relevance · High
Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Lead relevance64
- Project scale (MW)18
- Event type20
- Lifecycle stage10
- Recency8
- Operator identified4
- Multi-unit evidence4
Signal materiality44
- Event type20
- MW affected13
- Units affected11
New planned wind units — 5 units / 34.6 MW
Pattensen, Niedersachsen · Operator: Operator ID ABR965870485671 (name not resolved)
5 planned units · 34.6 MW · First observed 25 Sept 2026
- MaStR evidence: HIGH
- Registry only · external search not performed
What changed
5 new planned wind units totalling 34.6 MW were first observed in this MaStR snapshot.
Why this ranks high. Mid-sized 34.6 MW signal and freshly registered planned asset. Operator identity is unresolved, which reduces immediate actionability; the grouping evidence is limited.
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Project development or development-management services
- Grid-connection / interconnection and electrical infrastructure services
- Engineering and environmental services
- Civil works and balance-of-plant
- Turbine-related services (supply, transport, installation, service)
Verify next
- Identify the developer or project company
- Check planning and permitting status
- Search municipal planning documents
- Search recent company announcements
- Search tenders and procurement notices
- Verify whether construction or supplier selection has started
Change summary
- Planned units first observed
- 5
- Total registered capacity
- 34.6 MW
- Capacity per unit
- 6.8–7 MW per unit
- First observed in MaStR snapshot
- 25 Sept 2026
- Planned commissioning
- 01 Jul 2029
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (5)
SEE994700489817View official MaStR record ↗SEE962478628363View official MaStR record ↗SEE966245963381View official MaStR record ↗SEE925107125411View official MaStR record ↗SEE931298100526View official MaStR record ↗
Grouping basis
Supporting registry evidence: Same planned/commissioning date on every unit
These registrations are grouped for presentation because they share location/operator/category characteristics. GridGraph does not assert that this grouping represents one canonical development project.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Planung
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.
Snapshot transition
First tracked snapshot → 25 Sept 2026