Multiple changes
60Lead relevance · High

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance60

  • Project scale (MW)9
  • Event type14
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Several changes together5
  • Size of change6

Signal materiality55

  • Event type18
  • Size of change24
  • MW affected7
  • Several changes together6

Multiple registry changes (capacity + schedule) — 6.9 MW

Lünne, Niedersachsen · Operator: Raiffeisen Lünne Projektentwicklung GmbH

1 unit · 6.9 MW

Asset typeHorizontalläufer
Energy carrierWind
Registered operatorRaiffeisen Lünne Projektentwicklung GmbH

Registered capacity changed from 6 MW to 6.9 MW (+0.9 MW, +15%). The registered planned commissioning date moved by +548 days (Dec 2026 → Jun 2028).

Why this ranks high. Capacity and schedule changes recorded together on the same units and the registered operator is known. It affects only one 6.9 MW unit.

Several registry changes were recorded together on the same units. That may indicate a substantive update to the project rather than a routine correction, and is worth investigating.
Developer servicesGrid & electricalEngineeringMarket intelligence

Investigation hypotheses only. They are not evidence that any of these needs currently exist.

Registered capacity
6 MW → 6.9 MW (+0.9 MW / +15%)
Planned commissioning
Dec 2026 → Jun 2028 (+548 days)

GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.

Grouping basisSingle unit
A single MaStR registration.
Asset type (MaStR)
Horizontalläufer
Energy carrier (MaStR)
Wind
Operating status (MaStR)
In Planung

MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.

Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.

15 Oct 2026 → 17 Oct 2026