Schedule change
68Lead relevance · High

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

What this score is built from

  • Project scale (0-25 pts): total registered MW of the grouped units, on a diminishing-returns scale.
  • Event type (0-20 pts): a new planned asset, capacity change, operator change or schedule change each carry a fixed weight.
  • Lifecycle stage (0-10 pts): planning-stage assets score higher than already-commissioned ones.
  • Recency (0-8 pts): how recent the registry snapshot is.
  • Operator identified (0-10 pts): whether the registered operator name is known.
  • Multi-unit evidence (0-10 pts): number of units, discounted when grouping evidence is weaker.
  • Several changes together (0-8 pts) and size of change (0-7 pts, magnitude of a date or capacity change on a capped, logarithmic scale).

Commissioning delayed for 2 registered wind units in Kruft, Rheinland-Pfalz

Kruft, Rheinland-Pfalz · Operator: ABO Energy Windpark 18 GmbH & Co. KG

2 units · 12.4 MW

Asset typeHorizontalläufer
Energy carrierWind
Registered operatorABO Energy Windpark 18 GmbH & Co. KG

A later registered planned commissioning date may indicate asset delay or rescheduling.

A later registered planned commissioning date may indicate asset delay or rescheduling.
Registered units
2
Asset type
Horizontalläufer
Energy carrier
Wind
Location
Kruft, Rheinland-Pfalz
Registered operator
ABO Energy Windpark 18 GmbH & Co. KG
Operating status
In Planung
Planned commissioning
Aug 2026 → Dec 2029
Change
+1241 days

GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.

Grouping basisConservative municipality/operator/category grouping
These registrations are grouped for presentation because they share location/operator/category characteristics. GridGraph does not assert that this grouping represents one canonical development project.

1 Jul 2026 → 11 Sept 2026

← Back to the brief · 2026-09-13