Composite changeCritical priority93
This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.
What this score is built from
- Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
- Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
- Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.
Major asset update in Neukieritzsch, Sachsen
Gasturbinen mit Abhitzekessel
Facts
- Registered capacity
- 875 MW → 391.17 MW (-483.83 MW / -55%)
- Registered operator
- Lausitz Energie Kraftwerke AG → Gaskraftwerk Lippendorf GmbH
Commercial interpretation
Multiple material registration changes occurred in the same source transition and may warrant investigation.
Source lineage
Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE973821807274
Composite changeCritical priority93
This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.
What this score is built from
- Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
- Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
- Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.
Major asset update in Spreetal, Sachsen
Gasturbinen mit Abhitzekessel
Facts
- Commissioning
- Sept 2029 → Oct 2031 (+761 days)
- Registered capacity
- 870 MW → 391.17 MW (-478.83 MW / -55%)
- Registered operator
- Lausitz Energie Kraftwerke AG → Gaskraftwerk Schwarze Pumpe GmbH
Commercial interpretation
Multiple material registration changes occurred in the same source transition and may warrant investigation.
Source lineage
Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE960894923635
Capacity changeLow priority41
This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.
What this score is built from
- Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
- Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
- Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.
Registered capacity changed for Horizontalläufer in Steinreich, Brandenburg
Horizontalläufer
Facts
- Asset type
- Horizontalläufer
- Energy carrier
- Wind
- Location
- Steinreich, Brandenburg
- Registered operator
- Alterric Deutschland GmbH
- Operating status
- In Planung
- Registered capacity
- 4.2 MW → 7.2 MW
- Change
- +3 MW
Commercial interpretation
A material capacity increase indicates a larger registered asset capacity than in the previous snapshot.
Source lineage
Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE994076161874
Composite changeLow priority41
This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.
What this score is built from
- Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
- Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
- Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.
Major asset update in Großenwiehe, Schleswig-Holstein
Horizontalläufer
Facts
- Commissioning
- Sept 2027 → Dec 2028 (+484 days)
- Registered capacity
- 4.8 MW → 7 MW (+2.2 MW / 46%)
Commercial interpretation
Multiple material registration changes occurred in the same source transition and may warrant investigation.
Source lineage
Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE998320722927
Timing changeHigh priority76
This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.
What this score is built from
- Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
- Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
- Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.
Commissioning delay for 60 MW Gasturbinen mit Abhitzekessel in Frankfurt am Main, Hessen
Gasturbinen mit Abhitzekessel
Facts
- Combined registered capacity across grouped units
- 124.04 MW
- Registered units
- 3
- Asset type
- Gasturbinen mit Abhitzekessel
- Energy carrier
- Erdgas
- Location
- Frankfurt am Main, Hessen
- Registered operator
- Mainova AG
- Operating status
- In Planung
- Planned commissioning
- Sept 2026 → Nov 2026
- Change
- +64 days
Commercial interpretation
A later registered planned commissioning date may indicate asset delay or rescheduling.
Source lineage
Presentation group: 3 registered MaStR units
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE918810715130, SEE900931819460, SEE975123428881
Timing changeHigh priority75
This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.
What this score is built from
- Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
- Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
- Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.
Commissioning delay for 15 MW Horizontalläufer in Ausschließliche Wirtschaftszone
Horizontalläufer
Facts
- Combined registered capacity across grouped units
- 180 MW
- Registered units
- 12
- Asset type
- Horizontalläufer
- Energy carrier
- Wind
- Location
- Ausschließliche Wirtschaftszone
- Registered operator
- EnBW He Dreiht GmbH & Co. KG
- Operating status
- In Planung
- Planned commissioning
- Jun 2026 → Oct 2026
- Change
- +93 days
Commercial interpretation
A later registered planned commissioning date may indicate asset delay or rescheduling.
Source lineage
Presentation group: 12 registered MaStR units
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE959171440316, SEE983599520046, SEE923954894696, SEE998812552131, SEE980282368237, SEE926317316675, SEE918479491512, SEE980292520984, SEE951024907250, SEE977091784846, SEE956282536914, SEE908981182558
Timing changeHigh priority68
This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.
What this score is built from
- Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
- Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
- Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.
Commissioning delay for 6.8 MW Horizontalläufer in Namborn, Saarland
Horizontalläufer
Facts
- Asset type
- Horizontalläufer
- Energy carrier
- Wind
- Location
- Namborn, Saarland
- Registered operator
- KS Energiesysteme GmbH & Co. KG
- Operating status
- In Planung
- Planned commissioning
- Jan 2026 → Sept 2029
- Change
- +1368 days
Commercial interpretation
A later registered planned commissioning date may indicate asset delay or rescheduling.
Source lineage
Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE961749418528
Operator changeLow priority35
This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.
What this score is built from
- Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
- Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
- Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.
Registered operator changed for Horizontalläufer in Alsheim, Rheinland-Pfalz
Horizontalläufer
Facts
- Asset type
- Horizontalläufer
- Energy carrier
- Wind
- Location
- Alsheim, Rheinland-Pfalz
- Operating status
- In Planung
- Registered operator
- ABO Energy Windpark 23 GmbH & Co. KG → Vattenfall Wind Mettenheim GmbH
Commercial interpretation
A registered operator change may warrant investigation of the registered asset's current commercial context.
Source lineage
Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE969716045593
Operator changeLow priority35
This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.
What this score is built from
- Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
- Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
- Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.
Registered operator changed for Horizontalläufer in Balve, Nordrhein-Westfalen
Horizontalläufer
Facts
- Asset type
- Horizontalläufer
- Energy carrier
- Wind
- Location
- Balve, Nordrhein-Westfalen
- Operating status
- In Planung
- Registered operator
- PNE AG → Windpark Balver Wald Betriebs GmbH & Co. KG
Commercial interpretation
A registered operator change may warrant investigation of the registered asset's current commercial context.
Source lineage
Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE986579804563
New planned assetCritical priority100
This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.
What this score is built from
- Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
- Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
- Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.
New planned 880.4 MW Gasturbinen mit nachgeschalteter Dampfturbine in Voerde (Niederrhein), Nordrhein-Westfalen
Gasturbinen mit nachgeschalteter Dampfturbine
Facts
- First observed
- 2026-09-11
- Registered capacity
- 880.4 MW
- Asset type
- Gasturbinen mit nachgeschalteter Dampfturbine
- Energy carrier
- Erdgas
- Location
- Voerde (Niederrhein), Nordrhein-Westfalen
- Registered operator
- RWE Generation SE
- Operating status
- In Planung
Commercial interpretation
A newly registered planned asset of this size may warrant early investigation for equipment, construction, grid or professional-services opportunities.
Source lineage
Presentation group: 1 registered MaStR unit
Snapshot transition: First tracked snapshot → 11 Sept 2026
MaStR unit IDs: SEE952338852908
New planned assetCritical priority100
This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.
What this score is built from
- Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
- Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
- Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.
New planned 878.1 MW Gasturbinen mit nachgeschalteter Dampfturbine in Bergkamen, Nordrhein-Westfalen
Gasturbinen mit nachgeschalteter Dampfturbine
Facts
- First observed
- 2026-09-11
- Registered capacity
- 878.1 MW
- Asset type
- Gasturbinen mit nachgeschalteter Dampfturbine
- Energy carrier
- Erdgas
- Location
- Bergkamen, Nordrhein-Westfalen
- Registered operator
- Gaskraftwerk Bergkamen GmbH
- Operating status
- In Planung
Commercial interpretation
A newly registered planned asset of this size may warrant early investigation for equipment, construction, grid or professional-services opportunities.
Source lineage
Presentation group: 1 registered MaStR unit
Snapshot transition: First tracked snapshot → 11 Sept 2026
MaStR unit IDs: SEE977698856878
New planned assetCritical priority100
This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.
What this score is built from
- Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
- Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
- Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.
New planned 850.8 MW Gasturbinen mit nachgeschalteter Dampfturbine in Gundremmingen, Bayern
Gasturbinen mit nachgeschalteter Dampfturbine
Facts
- Combined registered capacity across grouped units
- 979.85 MW
- Registered units
- 29
- First observed
- 2026-09-11
- Registered capacity
- 850.8 MW
- Asset type
- Gasturbinen mit nachgeschalteter Dampfturbine
- Energy carrier
- Erdgas
- Location
- Gundremmingen, Bayern
- Registered operator
- RWE Generation SE
- Operating status
- In Planung
Commercial interpretation
A newly registered planned asset of this size may warrant early investigation for equipment, construction, grid or professional-services opportunities.
Source lineage
Presentation group: 29 registered MaStR units
Snapshot transition: First tracked snapshot → 11 Sept 2026
MaStR unit IDs: SEE968155469649, SEE965756082444, SEE977404654545, SEE922380340166, SEE971276194697, SEE900894444778, SEE921177994858, SEE914458821424, SEE983175903898, SEE965451885647, SEE966337374071, SEE976725563086, SEE916444687670, SEE945248948847, SEE996676429378, SEE947943737238, SEE929785881829, SEE906781049569, SEE939324670579, SEE926409412711, SEE983030959862, SEE905999571060, SEE996406323853, SEE979170976159, SEE988691126752, SEE935934259715, SEE907381622664, SEE905951934490, SEE966786659767