Intelligence brief

German Energy Asset Change Intelligence — 2026-10-18

A curated, source-traceable view of registered MaStR asset updates.

Coverage: 06–18 Oct 2026Latest MaStR snapshot: 18 Oct 2026Snapshots compared: 4
Source coverageLatest MaStR snapshot: 18 Oct 2026Changes compared with: 17 Oct 2026Brief generated: 18 Oct 2026
8Top opportunities shown
The diversified selection shown in the Top section. 76 grouped events score above the investigation threshold in total. A registry signal only: it does not establish procurement activity or buyer intent.
14New development signals
48Major schedule shifts
16Operator changes
36Commissioning events
290.98 MWNewly planned capacity

119 grouped events (units merged into likely site groups; not confirmed projects). Unit-level records: 301 registry changes across 285 registrations, 1.78 GW registered capacity.

Start here

  1. 77New planned wind development signal — 12 units / 81.6 MW · Warburg, Nordrhein-Westfalen
  2. 76Multiple registry changes (capacity + schedule) — 5 units / 34.5 MW · Emsbüren, Niedersachsen
  3. 70New planned wind units — 7 units / 47.8 MW · Willebadessen, Nordrhein-Westfalen
  4. 69Multiple registry changes (schedule + operator) — 3 units / 18 MW · Emsbüren, Niedersachsen
  5. 69Multiple registry changes (schedule + operator) — 3 units / 18 MW · Lünne, Niedersachsen

Receive a filtered weekly brief for your market

Tell us which Bundesländer and technologies you care about and we'll follow up with a weekly brief scoped to that — not the full report.

Relevant Bundesländer (optional)
Relevant technologies (optional)

We'll only use this to follow up with a filtered weekly brief for your market. Read how your data is stored and how to withdraw at any time in our Privacy Policy.

Top opportunities to investigate (8)

Selected from the highest-scoring investigation signals, with category diversification to avoid repetitive results. Cards are ordered by opportunity score; a higher-scoring signal of an already well-represented type may appear in a section below. Scores are deterministic and are not probabilities. Everything here is a starting point for verification, not evidence of demand.

New planned asset
77Lead relevance · Very high

Why this ranks high. Large 81.6 MW multi-unit signal, 12 registrations moving together and the registered operator is known. A targeted external search found no reliable corroborating source yet, which is not proof that the project does not exist.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance77

  • Project scale (MW)22
  • Event type20
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence9

Signal materiality52

  • Event type20
  • MW affected17
  • Units affected15

New planned wind development signal — 12 units / 81.6 MW

Warburg, Nordrhein-Westfalen · Operator: NaturStromProjekte GmbH

12 planned units · 81.6 MW · First observed 15 Oct 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 31 Dec 2028

12 new planned wind units totalling 81.6 MW were first observed in this MaStR snapshot.

A multi-unit planned development of this scale may represent an early commercial signal worth investigating.

  • MaStR evidence: HIGH
  • Registry only · external search performed; no project corroboration
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
12
Total registered capacity
81.6 MW
Capacity per unit
6.8 MW each
First observed in MaStR snapshot
15 Oct 2026
Planned commissioning
31 Dec 2028
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
External evidence details

External verification: Searched, no reliable evidence found

A targeted search (5 queries) found no sufficiently reliable external source for this wind development in Warburg. This does not show that the project does not exist. No public procurement evidence was found in this verification run.

Project company
NaturStromProjekte GmbH (registered in MaStR; not confirmed externally)
Developer
Not identified
Project evidence
None
Commercial evidence
None found

We searched and found no reliable external evidence yet. This is not proof that the project does not exist.

No public procurement evidence was found in this verification run.

No independent external sources.

Registry lead relevance: 77 (unchanged by external verification) Searched, but no reliable external evidence was found; registry score unchanged.

Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Searched, no reliable evidence found — a targeted search found no sufficiently reliable external source, which is not proof that the project does not exist. External evidence is additional context and never replaces or downgrades the MaStR record; project corroboration is not evidence of procurement or buyer intent.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 12 registered MaStR units
Snapshot transition: First tracked snapshot → 15 Oct 2026
MaStR unit IDs: SEE919586904452, SEE919801592235, SEE920782690513, SEE930524322244, SEE936206732707, SEE940067877514, SEE954652017452, SEE959177927255, SEE970706500909, SEE975470373346, SEE980016486398, SEE995508289869
Commercial signals (12): cmvb9v0kr1392wtdw5vu1t0gk, cmvb9v0kr1393wtdwxosepu90, cmvb9v0ks1397wtdwri9bb359, cmvb9v0ks139owtdw92s8rbqg, cmvb9v0kt13a0wtdwr2z1mp9j, cmvb9v0kt13a7wtdws5354y56, cmvb9v0ku13auwtdwsr7tiqsh, cmvb9v0ku13b4wtdwvyw33qhp, cmvb9v0kw13bxwtdwbrvdmeht, cmvb9v0kw13cawtdw0ohe4ad3, cmvb9v0kx13ckwtdwol0s9w1d, cmvb9v0ky13d3wtdwdvo8sr14

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Multiple changes
76Lead relevance · Very high

Why this ranks high. Mid-sized 34.5 MW signal, 5 registrations moving together, capacity and schedule changes recorded together on the same units and the registered operator is known.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance76

  • Project scale (MW)18
  • Event type14
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Multi-unit evidence6
  • Several changes together5
  • Size of change6

Signal materiality72

  • Event type18
  • Size of change24
  • MW affected13
  • Units affected11
  • Several changes together6

Multiple registry changes (capacity + schedule) — 5 units / 34.5 MW

Emsbüren, Niedersachsen · Operator: Raiffeisen Lünne Projektentwicklung GmbH

5 units · 34.5 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Dec 2026 → Jun 2028 (+548 days)

5 wind units registered a capacity change; combined registered capacity moved from 30 MW to 34.5 MW (+4.5 MW). 5 wind units registered a later planned commissioning date (+548 days).

Several registry changes were recorded together on the same units. That may indicate a substantive update to the project rather than a routine correction, and is worth investigating.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Design / technologyGrid connectionEngineeringEquipment sizingProject schedulingConstruction timing
Design change?Permit & grid documentsDeveloper updatesRegistry correction?
Facts, hypotheses and how to verify
Per-unit change
5 units changed from 6 MW to 6.9 MW each
Combined registered capacity now
34.5 MW
Combined change
+4.5 MW (+15%)
Units with a new planned date
5
Planned commissioning (same for every unit)
Dec 2026 → Jun 2028 (+548 days)
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Check whether the change reflects a design or turbine-model change
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Compare with permit and grid-connection documents
  • Check permitting and construction status
  • Look for recent developer announcements
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 5 registered MaStR units
Snapshot transition: 15 Oct 2026 → 17 Oct 2026
MaStR unit IDs: SEE953230730707, SEE906786016610, SEE972769190394, SEE910509593159, SEE913475025464
Commercial signals (10): cmvbwy1122uhowts4xgl4ns33, cmvbwy1132uhxwts488d8v00s, cmvbwy1162ujkwts4n0cb4162, cmvbwy1132ui3wts42qvwem5y, cmvbwy1132ui7wts4vwd8gghy, cmvbwy1132uhpwts4e4rzz9ta, cmvbwy1132uhywts4tyyekzns, cmvbwy1132ui4wts47agu5cvs, cmvbwy1132ui8wts4x4cw9avd, cmvbwy1162ujjwts4y8vb5bd8

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
New planned asset
70Lead relevance · High

Why this ranks high. Large 47.8 MW multi-unit signal and the registered operator is known. The grouping evidence is limited; a targeted external search found no reliable corroborating source yet, which is not proof that the project does not exist.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance70

  • Project scale (MW)20
  • Event type20
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence4

Signal materiality47

  • Event type20
  • MW affected15
  • Units affected12

New planned wind units — 7 units / 47.8 MW

Willebadessen, Nordrhein-Westfalen · Operator: Energiekontor AG

7 planned units · 47.8 MW · First observed 15 Oct 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 31 Jan 2030

7 new planned wind units totalling 47.8 MW were first observed in this MaStR snapshot.

A multi-unit planned development of this scale may represent an early commercial signal worth investigating.

  • MaStR evidence: HIGH
  • Registry only · external search performed; no project corroboration
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
7
Total registered capacity
47.8 MW
Capacity per unit
6.8–7 MW per unit
First observed in MaStR snapshot
15 Oct 2026
Planned commissioning
31 Jan 2030
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
External evidence details

External verification: Searched, no reliable evidence found

A targeted search (5 queries) found no sufficiently reliable external source for this wind development in Willebadessen. This does not show that the project does not exist. No public procurement evidence was found in this verification run.

Project company
Energiekontor AG (registered in MaStR; not confirmed externally)
Developer
Not identified
Project evidence
None
Commercial evidence
None found

We searched and found no reliable external evidence yet. This is not proof that the project does not exist.

  • Bekanntmachungen, Kreis HöxterPermit document · kreis-hoexter.de · Published 16 Oct 2026 · low confidenceSupports: locationVerified from page text
  • Aufstellung Teilflächennutzungsplan Windkraft zur ( ...Municipal planning document · willebadessen.de · Published 13 Jun 2023 · low confidenceSupports: locationVerified from PDF text · page 12“… ie bisher in der Region verwendeten üblichen Abmessungen hinaus geht. Die Stadt Willebadessen hat mit Unterstützung der KÖTTER Consulting Engineers GmbH & Co. KG, Rheine eine zukünftig zu erwartende Größe und Konfiguration entwickelt: Als Muster wird eine Windkraftanlage mit 8 MW Leistung, 200 m Rotordurchmesser, Nabenhöhe 220 m, Gesamthö …”Older source: weighed lower unless it clearly describes the same ongoing project.
  • Stadt Willebadessen Kreis Höxter Stadtteil ...Municipal planning document · willebadessen.de · Published 10 Jun 2022 · low confidenceSupports: locationVerified from PDF text · page 6“… gründung zur Aufstellung des vorhabenbezogenen Bebauungsplanes Nr. 17 der Stadt Willebadessen: „Sonderbaufläche Windenergie Willebadessen“ im Stadtteil Willebadessen Sonderbaufläche Windenergie Willebadessen Seite 3 Im wirksamen Flächennutzungsplan (FNP) stellt die Stadt Willebadessen zwei Konzentrationszonen für Windkraftanlagen dar. Es …”Older source: weighed lower unless it clearly describes the same ongoing project.

No public procurement evidence was found in this verification run.

No independent external sources.

Registry lead relevance: 70 (unchanged by external verification) Searched, but no reliable external evidence was found; registry score unchanged.

Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Searched, no reliable evidence found — a targeted search found no sufficiently reliable external source, which is not proof that the project does not exist. External evidence is additional context and never replaces or downgrades the MaStR record; project corroboration is not evidence of procurement or buyer intent.
Grouping: Conservative group — Same planned/commissioning date on every unit
Presentation group: 7 registered MaStR units
Snapshot transition: First tracked snapshot → 15 Oct 2026
MaStR unit IDs: SEE917465876258, SEE924173212155, SEE943974060307, SEE956252580534, SEE985095304540, SEE992581547756, SEE992694628809
Commercial signals (7): cmvb9v0kr138wwtdwonxncegk, cmvb9v0ks139ewtdwol2xmtig, cmvb9v0kt13abwtdw15xk1qco, cmvb9v0ku13aywtdwj49tllgt, cmvb9v0kx13crwtdweqytq5xn, cmvb9v0kx13cvwtdwp32moufi, cmvb9v0kx13cwwtdwjbxq84a4

Grouping basisConservative group
Supporting registry evidence: Same planned/commissioning date on every unit
These registrations are grouped for presentation because they share location/operator/category characteristics. GridGraph does not assert that this grouping represents one canonical development project.
Multiple changes
69Lead relevance · High

Why this ranks high. Mid-sized 18 MW signal, 3 registrations moving together, schedule and operator changes recorded together on the same units, unusually large schedule shift (244 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance69

  • Project scale (MW)14
  • Event type13
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Multi-unit evidence5
  • Several changes together5
  • Size of change5

Signal materiality61

  • Event type16
  • Size of change20
  • MW affected11
  • Units affected8
  • Several changes together6

Multiple registry changes (schedule + operator) — 3 units / 18 MW

Emsbüren, Niedersachsen · Operator: Bürgerenergiegesellschaft Listrup-Süd GmbH & Co. KG

3 units · 18 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Dec 2026 → Aug 2027 (+244 days)

3 wind units registered a later planned commissioning date (+244 days). The registered operator changed on 3 wind units.

Several registry changes were recorded together on the same units. That may indicate a substantive update to the project rather than a routine correction, and is worth investigating.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timingAsset transactionsFinancing
Registry correction?Permit & construction statusDeveloper updatesCompany register
Facts, hypotheses and how to verify
Units with a new planned date
3
Planned commissioning (same for every unit)
Dec 2026 → Aug 2027 (+244 days)
Units with an operator change
3
Previous registered operator
Raiffeisen Lünne Projektentwicklung GmbH
New registered operator
Bürgerenergiegesellschaft Listrup-Süd GmbH & Co. KG
  • Project development or development-management services
  • Engineering and environmental services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check permitting and construction status
  • Check whether the previous and new operators are related entities
  • Look for recent developer updates
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 3 registered MaStR units
Snapshot transition: 15 Oct 2026 → 17 Oct 2026
MaStR unit IDs: SEE901359604447, SEE956501745875, SEE947818168112
Commercial signals (6): cmvbwy1132uhswts45hfa4lih, cmvbwy1132uhqwts4xtpy04uy, cmvbwy1122uhjwts4e9qdwsmr, cmvbwy1132uhtwts4cw6xhsap, cmvbwy1122uhkwts48jdvok4n, cmvbwy1122uh5wts4uk6s3jrh

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
  • SEE901359604447WEA06 · 6 MW · 2027-08-31 · Dec 2026 → Aug 2027 (+244 days); operator → Bürgerenergiegesellschaft Listrup-Süd GmbH & Co. KGView official MaStR record ↗
  • SEE956501745875WEA05 · 6 MW · 2027-08-31 · Dec 2026 → Aug 2027 (+244 days); operator → Bürgerenergiegesellschaft Listrup-Süd GmbH & Co. KGView official MaStR record ↗
  • SEE947818168112WEA04 · 6 MW · 2027-08-31 · Dec 2026 → Aug 2027 (+244 days); operator → Bürgerenergiegesellschaft Listrup-Süd GmbH & Co. KGView official MaStR record ↗
Multiple changes
69Lead relevance · High

Why this ranks high. Mid-sized 18 MW signal, 3 registrations moving together, schedule and operator changes recorded together on the same units, unusually large schedule shift (244 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance69

  • Project scale (MW)14
  • Event type13
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Multi-unit evidence5
  • Several changes together5
  • Size of change5

Signal materiality61

  • Event type16
  • Size of change20
  • MW affected11
  • Units affected8
  • Several changes together6

Multiple registry changes (schedule + operator) — 3 units / 18 MW

Lünne, Niedersachsen · Operator: Bürgerenergiegesellschaft Heitel-Ost GmbH & Co. KG

3 units · 18 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Dec 2026 → Aug 2027 (+244 days)

3 wind units registered a later planned commissioning date (+244 days). The registered operator changed on 3 wind units.

Several registry changes were recorded together on the same units. That may indicate a substantive update to the project rather than a routine correction, and is worth investigating.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timingAsset transactionsFinancing
Registry correction?Permit & construction statusDeveloper updatesCompany register
Facts, hypotheses and how to verify
Units with a new planned date
3
Planned commissioning (same for every unit)
Dec 2026 → Aug 2027 (+244 days)
Units with an operator change
3
Previous registered operator
Raiffeisen Lünne Projektentwicklung GmbH
New registered operator
Bürgerenergiegesellschaft Heitel-Ost GmbH & Co. KG
  • Project development or development-management services
  • Engineering and environmental services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check permitting and construction status
  • Check whether the previous and new operators are related entities
  • Look for recent developer updates
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 3 registered MaStR units
Snapshot transition: 15 Oct 2026 → 17 Oct 2026
MaStR unit IDs: SEE991124828581, SEE926633307043, SEE908465709035
Commercial signals (6): cmvbwy1152uivwts44wcg497b, cmvbwy1142uikwts49m4odmi6, cmvbwy1132uhzwts4d5yecnpw, cmvbwy1142uiuwts4xyzut9rv, cmvbwy1172uk5wts4c7wxrj68, cmvbwy1132ui0wts4nulkttbd

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
  • SEE991124828581WEA06 · 6 MW · 2027-08-31 · Dec 2026 → Aug 2027 (+244 days); operator → Bürgerenergiegesellschaft Heitel-Ost GmbH & Co. KGView official MaStR record ↗
  • SEE926633307043WEA05 · 6 MW · 2027-08-31 · Dec 2026 → Aug 2027 (+244 days); operator → Bürgerenergiegesellschaft Heitel-Ost GmbH & Co. KGView official MaStR record ↗
  • SEE908465709035WEA04 · 6 MW · 2027-08-31 · Dec 2026 → Aug 2027 (+244 days); operator → Bürgerenergiegesellschaft Heitel-Ost GmbH & Co. KGView official MaStR record ↗
Operator change
69Lead relevance · High

Why this ranks high. Large 72 MW multi-unit signal, 10 registrations moving together and the registered operator is known.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance69

  • Project scale (MW)22
  • Event type13
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence8

Signal materiality45

  • Event type14
  • MW affected17
  • Units affected14

Registered operator changed on 10 wind units — 10 units / 72 MW

Berkenbrück, Brandenburg · Operator: reVenton Windpark BB1 GmbH & Co. KG

10 units · 72 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 10 wind units.

A registered operator change can be a useful trigger for investigating ownership, project restructuring, or a change in the commercial entity responsible for the asset. It does not by itself establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Units with an operator change
10
Previous registered operator
reVenton Asset Partners GmbH
New registered operator
reVenton Windpark BB1 GmbH & Co. KG
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“wind berkenbrück dehmsee…”); Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 10 registered MaStR units
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE912795734759, SEE905896498231, SEE939926948540, SEE937665053846, SEE933002789454, SEE917642721807, SEE965103179407, SEE976068024596, SEE907851232980, SEE961819067533
Commercial signals (10): cmvb9v0kr138qwtdwkfglkpiv, cmvb9v0kq138awtdwvw6pqdpe, cmvb9v0kt13a6wtdwbihdobb4, cmvb9v0kt13a3wtdwwbf63cgf, cmvb9v0kt139twtdwvezo05f3, cmvb9v0kr138ywtdw90pmu32m, cmvb9v0kv13biwtdwfx82lvpx, cmvb9v0kw13cbwtdwrx57vue5, cmvb9v0kq138gwtdwocsmmlis, cmvb9v0kv13bcwtdwi3hxj4s7

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“wind berkenbrück dehmsee…”); Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
  • SEE912795734759Wind Berkenbrück-Dehmsee - WEA 4 · 7.2 MW · 2028-07-31 · operator → reVenton Windpark BB1 GmbH & Co. KGView official MaStR record ↗
  • SEE905896498231Wind Berkenbrück-Dehmsee - WEA 3 · 7.2 MW · 2028-07-31 · operator → reVenton Windpark BB1 GmbH & Co. KGView official MaStR record ↗
  • SEE939926948540Wind Berkenbrück-Dehmsee - WEA 9 · 7.2 MW · 2028-07-31 · operator → reVenton Windpark BB1 GmbH & Co. KGView official MaStR record ↗
  • SEE937665053846Wind Berkenbrück-Dehmsee - WEA 2 · 7.2 MW · 2028-07-31 · operator → reVenton Windpark BB1 GmbH & Co. KGView official MaStR record ↗
  • SEE933002789454Wind Berkenbrück-Dehmsee - WEA 8 · 7.2 MW · 2028-07-31 · operator → reVenton Windpark BB1 GmbH & Co. KGView official MaStR record ↗
  • SEE917642721807Wind Berkenbrück-Dehmsee - WEA 6 · 7.2 MW · 2028-07-31 · operator → reVenton Windpark BB1 GmbH & Co. KGView official MaStR record ↗
  • SEE965103179407Wind Berkenbrück-Dehmsee - WEA 11 · 7.2 MW · 2028-07-31 · operator → reVenton Windpark BB1 GmbH & Co. KGView official MaStR record ↗
  • SEE976068024596Wind Berkenbrück-Dehmsee - WEA 1 · 7.2 MW · 2028-07-31 · operator → reVenton Windpark BB1 GmbH & Co. KGView official MaStR record ↗
  • SEE907851232980Wind Berkenbrück-Dehmsee - WEA 10 · 7.2 MW · 2028-07-31 · operator → reVenton Windpark BB1 GmbH & Co. KGView official MaStR record ↗
  • SEE961819067533Wind Berkenbrück-Dehmsee - WEA 7 · 7.2 MW · 2028-07-31 · operator → reVenton Windpark BB1 GmbH & Co. KGView official MaStR record ↗
New planned asset
68Lead relevance · High

Why this ranks high. Mid-sized 16.68 MW signal, 3 registrations moving together and the registered operator is known. External corroboration is only partial.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance68

  • Project scale (MW)14
  • Event type20
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence5
  • External verification3

Signal materiality38

  • Event type20
  • MW affected10
  • Units affected8

New planned wind development signal — 3 units / 16.68 MW

Sontra, Hessen · Operator: Trianel Wind und Solar GmbH & Co. KG

3 planned units · 16.68 MW · First observed 15 Oct 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 01 Jun 2028

3 new planned wind units totalling 16.68 MW were first observed in this MaStR snapshot.

A multi-unit planned development of this scale may represent an early commercial signal worth investigating.

  • MaStR evidence: HIGH
  • Partially corroborated externally · 6 independent sources

Project corroboration does not establish procurement activity.

External evidence predates registry detection; newly observed does not necessarily mean a new project.

Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
3
Total registered capacity
16.68 MW
Capacity per unit
5.56 MW each
First observed in MaStR snapshot
15 Oct 2026
Planned commissioning
01 Jun 2028
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
External evidence details

External verification: Partially corroborated

Some external sources mention a wind development in Sontra associated with PNE WIND AG, but the match to the registered project is incomplete. Public project evidence found as early as 30 Sept 2023; GridGraph first observed the MaStR registration on 15 Oct 2026. Related commercial activity (for example a supplier order or tender) was found for this company or place, but it cannot yet be tied to this exact registered project.

Project company
Trianel Wind und Solar GmbH & Co. KG (registered in MaStR; not confirmed externally)
Developer
PNE WIND AG
Project evidence
Partial
Commercial evidence
Related activity, not pinned to this project
  • Bekanntmachungen - Stadt SontraDeveloper project page · sontra.de · Publication date unknown · medium confidenceSupports: project exists, location, project stageVerified from page text
  • Sontra wird Anteilseigner bei EAM Energiewendepartner GmbHNews / press report · hna.de · Published 30 Sept 2023 · medium confidenceSupports: project exists, location, unit count, project stageVerified from page textOlder source: weighed lower unless it clearly describes the same ongoing project.
  • PNE WIND AG hat den Windpark Sontra fertiggestellt und an den Käufer übergeben - Windbranche.deNews / press report · windbranche.de · Publication date unknown · medium confidenceSupports: project exists, location, procurement activityVerified from page text
  • Vorranggebiete Windenergie in NentershausenWeb page · nefino.de · Publication date unknown · medium confidenceSupports: project exists, location, project stageJudged from search excerpt only
  • Windenergie-WanderwegWeb page · grenzenlos-nordhessen.de · Publication date unknown · medium confidenceSupports: project exists, locationVerified from page text
  • Sontra (Germany) - Wind farms - Online access - The Wind PowerWeb page · thewindpower.net · Publication date unknown · medium confidenceSupports: project exists, locationVerified from page text
  • AMTSBLATTPermit document · hochsauerlandkreis.de · Published 5 Sept 2024 · low confidenceSupports: company identityVerified from PDF text · page 2“… G ZUR DURCHFÜHRUNG DES BUNDES- IMMISSIONSSCHUTZGESETZES (9. BIMSCHV) Antrag der Trianel Wind und Solar GmbH & Co. KG, v. d. Trianel Wind und Solar Verwaltungs GmbH, v. d. GF Dr. Markus Hakes auf Erteilung einer Genehmigung gem. § 4 BImSchG für die Errichtung und den Betrieb von insgesamt 12 Windenergieanlagen vom Typ ENERCON E-160 EP5 E3 …”
  • Trianel Wind und Solar (TWS)Developer project page · trianel-erneuerbare.de · Publication date unknown · low confidenceSupports: company identityVerified from page text
  • Reports, participating interests and key figures – TrianelDeveloper project page · trianel.com · Publication date unknown · low confidenceSupports: company identityVerified from page text

Related commercial activity (for example a supplier order or tender) was found for this company or place, but it cannot yet be tied to this exact registered project.

6 independent external sources.

Registry lead relevance: 65 → After external verification: 68 (+3) +3: identity or project only partially corroborated; +1 related commercial activity that cannot yet be pinned to this exact group.

Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Partially corroborated — 6 independent external sources at medium confidence or better. External evidence is additional context and never replaces or downgrades the MaStR record; project corroboration is not evidence of procurement or buyer intent.
Grouping: Likely site group — Shared unit-name pattern (“sontra…”); Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 3 registered MaStR units
Snapshot transition: First tracked snapshot → 15 Oct 2026
MaStR unit IDs: SEE905938530998, SEE979828247075, SEE980334294651
Commercial signals (3): cmvb9v0kq138bwtdw3kc2g1hp, cmvb9v0kx13cjwtdwpoen8a1x, cmvb9v0kx13cmwtdwm8octvgy

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“sontra…”); Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Operator change
64Lead relevance · High

Why this ranks high. Large 77 MW multi-unit signal and 11 registrations moving together. Operator identity is unresolved, which reduces immediate actionability.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance64

  • Project scale (MW)22
  • Event type13
  • Lifecycle stage10
  • Recency6
  • Operator identified4
  • Multi-unit evidence9

Signal materiality46

  • Event type14
  • MW affected17
  • Units affected15

Registered operator changed on 11 wind units — 11 units / 77 MW

Lingen (Ems), Niedersachsen · Operator: Registered operator name not resolved

11 units · 77 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 11 wind units.

A registered operator change can be a useful trigger for investigating ownership, project restructuring, or a change in the commercial entity responsible for the asset. It does not by itself establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Units with an operator change
11
Previous registered operator
2 different operators: AKWP Nr. 2 GmbH & Co. KG; Windpark Lingen Ochsenbruch Betriebsführungsgesellschaft mbH
New registered operator
Operator ID ABR943728656329 (name not resolved)
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 11 registered MaStR units
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE912501533287, SEE939731705499, SEE917476110709, SEE934913987533, SEE969129669836, SEE959456996392, SEE910760806289, SEE905296840401, SEE911008083189, SEE923790111322, SEE919066186781
Commercial signals (11): cmvb9v0kr138pwtdw0j5kymnc, cmvb9v0kt13a5wtdwle9xafz3, cmvb9v0kr138xwtdw97c0oj9q, cmvb9v0kt139vwtdw0ckprw0u, cmvb9v0kw13bvwtdwg4dajqh3, cmvb9v0ku13b5wtdwv81eqr9x, cmvb9v0kr138lwtdwuiaiwixg, cmvb9v0kq1388wtdwf8zlp19m, cmvb9v0kr138mwtdw6am20cox, cmvb9v0ks139bwtdwa0avzk6a, cmvb9v0kr1391wtdwfbt1jb2e

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
↑ Back to top

Receive a filtered weekly brief for your market

Tell us which Bundesländer and technologies you care about and we'll follow up with a weekly brief scoped to that — not the full report.

Relevant Bundesländer (optional)
Relevant technologies (optional)

We'll only use this to follow up with a filtered weekly brief for your market. Read how your data is stored and how to withdraw at any time in our Privacy Policy.

New developments (11)

New planned asset
64Lead relevance · High

Why this ranks high. Mid-sized 36 MW signal and 5 registrations moving together. Operator identity is unresolved, which reduces immediate actionability; a targeted external search found no reliable corroborating source yet, which is not proof that the project does not exist.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance64

  • Project scale (MW)18
  • Event type20
  • Lifecycle stage10
  • Recency6
  • Operator identified4
  • Multi-unit evidence6

Signal materiality45

  • Event type20
  • MW affected14
  • Units affected11

New planned wind development signal — 5 units / 36 MW

Forst (Lausitz), Brandenburg · Operator: Registered operator name not resolved

5 planned units · 36 MW · First observed 15 Oct 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 29 Sept 2029

5 new planned wind units totalling 36 MW were first observed in this MaStR snapshot.

A multi-unit planned development of this scale may represent an early commercial signal worth investigating.

  • MaStR evidence: HIGH
  • Registry only · external search performed; no project corroboration
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
5
Total registered capacity
36 MW
Capacity per unit
7.2 MW each
First observed in MaStR snapshot
15 Oct 2026
Planned commissioning
29 Sept 2029
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
External evidence details

External verification: Searched, no reliable evidence found

A targeted search (5 queries) found no sufficiently reliable external source for this wind development in Forst (Lausitz). This does not show that the project does not exist. No public procurement evidence was found in this verification run.

Project company
Not resolved
Developer
Not identified
Project evidence
None
Commercial evidence
None found

We searched and found no reliable external evidence yet. This is not proof that the project does not exist.

No public procurement evidence was found in this verification run.

No independent external sources.

Registry lead relevance: 64 (unchanged by external verification) Searched, but no reliable external evidence was found; registry score unchanged.

Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Searched, no reliable evidence found — a targeted search found no sufficiently reliable external source, which is not proof that the project does not exist. External evidence is additional context and never replaces or downgrades the MaStR record; project corroboration is not evidence of procurement or buyer intent.
Grouping: Likely site group — Shared unit-name pattern (“wp forst briesnig…”); Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 5 registered MaStR units
Snapshot transition: First tracked snapshot → 15 Oct 2026
MaStR unit IDs: SEE946358278367, SEE948336517277, SEE957510772852, SEE957640100518, SEE974437881887
Commercial signals (5): cmvb9v0kt13afwtdw6zvch08o, cmvb9v0ku13ahwtdw1c9f6fc5, cmvb9v0ku13b1wtdwhtboip07, cmvb9v0ku13b2wtdwfa6cr5pq, cmvb9v0kw13c6wtdwfvmto4uu

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“wp forst briesnig…”); Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
New planned asset
64Lead relevance · High

Why this ranks high. Mid-sized 36 MW signal and 5 registrations moving together. Operator identity is unresolved, which reduces immediate actionability; a targeted external search found no reliable corroborating source yet, which is not proof that the project does not exist.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance64

  • Project scale (MW)18
  • Event type20
  • Lifecycle stage10
  • Recency6
  • Operator identified4
  • Multi-unit evidence6

Signal materiality45

  • Event type20
  • MW affected14
  • Units affected11

New planned wind development signal — 5 units / 36 MW

Heinersbrück, Brandenburg · Operator: Registered operator name not resolved

5 planned units · 36 MW · First observed 15 Oct 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 29 Sept 2029

5 new planned wind units totalling 36 MW were first observed in this MaStR snapshot.

A multi-unit planned development of this scale may represent an early commercial signal worth investigating.

  • MaStR evidence: HIGH
  • Registry only · external search performed; no project corroboration
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
5
Total registered capacity
36 MW
Capacity per unit
7.2 MW each
First observed in MaStR snapshot
15 Oct 2026
Planned commissioning
29 Sept 2029
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
External evidence details

External verification: Searched, no reliable evidence found

A targeted search (5 queries) found no sufficiently reliable external source for this wind development in Heinersbrück. This does not show that the project does not exist. No public procurement evidence was found in this verification run.

Project company
Not resolved
Developer
Not identified
Project evidence
None
Commercial evidence
None found

We searched and found no reliable external evidence yet. This is not proof that the project does not exist.

No public procurement evidence was found in this verification run.

No independent external sources.

Registry lead relevance: 64 (unchanged by external verification) Searched, but no reliable external evidence was found; registry score unchanged.

Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Searched, no reliable evidence found — a targeted search found no sufficiently reliable external source, which is not proof that the project does not exist. External evidence is additional context and never replaces or downgrades the MaStR record; project corroboration is not evidence of procurement or buyer intent.
Grouping: Likely site group — Shared unit-name pattern (“wp forst briesnig…”); Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 5 registered MaStR units
Snapshot transition: First tracked snapshot → 15 Oct 2026
MaStR unit IDs: SEE916868555586, SEE929647300673, SEE936580733444, SEE947994732251, SEE999505363195
Commercial signals (5): cmvb9v0kr138vwtdw640d89te, cmvb9v0ks139mwtdwkh1dgt7q, cmvb9v0kt13a1wtdwgcjrwuho, cmvb9v0kt13agwtdwm7ntp3vv, cmvb9v0kq1380wtdwzqrn3lqn

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“wp forst briesnig…”); Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
New planned asset
63Lead relevance · High

Why this ranks high. Mid-sized 28.8 MW signal and 4 registrations moving together. Operator identity is unresolved, which reduces immediate actionability.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance63

  • Project scale (MW)17
  • Event type20
  • Lifecycle stage10
  • Recency6
  • Operator identified4
  • Multi-unit evidence6

Signal materiality43

  • Event type20
  • MW affected13
  • Units affected10

New planned wind development signal — 4 units / 28.8 MW

Jänschwalde, Brandenburg · Operator: Registered operator name not resolved

4 planned units · 28.8 MW · First observed 15 Oct 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 29 Sept 2029

4 new planned wind units totalling 28.8 MW were first observed in this MaStR snapshot.

A multi-unit planned development of this scale may represent an early commercial signal worth investigating.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
4
Total registered capacity
28.8 MW
Capacity per unit
7.2 MW each
First observed in MaStR snapshot
15 Oct 2026
Planned commissioning
29 Sept 2029
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“wp forst briesnig…”); Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 4 registered MaStR units
Snapshot transition: First tracked snapshot → 15 Oct 2026
MaStR unit IDs: SEE928532550452, SEE960387567377, SEE960495157026, SEE970959012266
Commercial signals (4): cmvb9v0ks139kwtdwbvzzjzp2, cmvb9v0kv13b7wtdwp8nkr09t, cmvb9v0kv13b8wtdw04w907ui, cmvb9v0kw13bywtdw4v9gmx4a

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“wp forst briesnig…”); Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
New planned asset
62Lead relevance · High

Why this ranks high. Freshly registered planned asset and the registered operator is known. Small combined capacity (11.12 MW).

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance62

  • Project scale (MW)12
  • Event type20
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Multi-unit evidence3

Signal materiality33

  • Event type20
  • MW affected8
  • Units affected5

New planned wind development signal — 2 units / 11.12 MW

Hagen, Nordrhein-Westfalen · Operator: SL Windenergie GmbH

2 planned units · 11.12 MW · First observed 17 Oct 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 15 Oct 2027

2 new planned wind units totalling 11.12 MW were first observed in this MaStR snapshot.

A newly registered planned asset may be an early sign of a development worth a quick look.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
2
Total registered capacity
11.12 MW
Capacity per unit
5.56 MW each
First observed in MaStR snapshot
17 Oct 2026
Planned commissioning
15 Oct 2027
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“hohlimerw…”); Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: First tracked snapshot → 17 Oct 2026
MaStR unit IDs: SEE935125323676, SEE918195783953
Commercial signals (2): cmvbwy1122uhawts4q9kil083, cmvbwy1142uibwts4v9f63ph8

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“hohlimerw…”); Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
New planned asset
56Lead relevance · Moderate

Why this ranks here. Freshly registered planned asset. Operator identity is unresolved, which reduces immediate actionability; small combined capacity (11.4 MW); no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance56

  • Project scale (MW)12
  • Event type20
  • Lifecycle stage10
  • Recency7
  • Operator identified4
  • Multi-unit evidence3

Signal materiality34

  • Event type20
  • MW affected9
  • Units affected5

New planned wind development signal — 2 units / 11.4 MW

Werbach, Baden-Württemberg · Operator: Registered operator name not resolved

2 planned units · 11.4 MW · First observed 17 Oct 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 01 Jan 2029

2 new planned wind units totalling 11.4 MW were first observed in this MaStR snapshot.

A newly registered planned asset may be an early sign of a development worth a quick look.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
2
Total registered capacity
11.4 MW
Capacity per unit
5.7 MW each
First observed in MaStR snapshot
17 Oct 2026
Planned commissioning
01 Jan 2029
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“wp werbach…”); Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: First tracked snapshot → 17 Oct 2026
MaStR unit IDs: SEE956726693463, SEE912627400586
Commercial signals (2): cmvbwy1132uhrwts4kw8hpt2v, cmvbwy1132ui5wts441wjox2v

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“wp werbach…”); Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
New planned asset
54Lead relevance · Moderate

Why this ranks here. The registered operator is known. Small combined capacity (2.07 MW); no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance54

  • Project scale (MW)5
  • Event type20
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence3

Signal materiality29

  • Event type20
  • MW affected4
  • Units affected5

New planned gas-generation development signal — 2 units / 2.07 MW

Bad Salzuflen, Nordrhein-Westfalen · Operator: Stadtwerke Bad Salzuflen GmbH

2 planned units · 2.07 MW · First observed 15 Oct 2026

Gas generation · Verbrennungsmotor

Planned commissioning: 23 Nov 2026

2 new planned gas-generation units totalling 2.07 MW were first observed in this MaStR snapshot.

A newly registered planned asset may be an early sign of a development worth a quick look.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Developer servicesGrid connectionElectrical BOPCivil / BOPEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
2
Total registered capacity
2.07 MW
Capacity per unit
1.03 MW each
First observed in MaStR snapshot
15 Oct 2026
Planned commissioning
23 Nov 2026
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
Related registry activity
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: First tracked snapshot → 15 Oct 2026
MaStR unit IDs: SEE976898531059, SEE943064558684
Commercial signals (2): cmvb9v0kx13cfwtdwl6orexa2, cmvb9v0kt13a9wtdw6erepifk

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
New planned asset
54Lead relevance · Moderate

Why this ranks here. The registered operator is known. It affects only one 6 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance54

  • Project scale (MW)8
  • Event type20
  • Lifecycle stage10
  • Recency6
  • Operator identified10

Signal materiality27

  • Event type20
  • MW affected7

New planned wind unit — 6 MW

Brilon, Nordrhein-Westfalen · Operator: Briloner Hochfläche Wind GmbH & Co. KG

1 planned unit · 6 MW · First observed 15 Oct 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 01 Nov 2028

A new planned wind unit of 6 MW was first observed in this MaStR snapshot.

A newly registered planned asset may be an early sign of a development worth a quick look.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Registered capacity
6 MW
First observed in MaStR snapshot
15 Oct 2026
Planned commissioning
01 Nov 2028
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: First tracked snapshot → 15 Oct 2026
MaStR unit IDs: SEE976733601435
Commercial signals (1): cmvb9v0kw13cewtdwgaa8f46t

Grouping basisSingle unit
A single MaStR registration.
New planned asset
52Lead relevance · Moderate

Why this ranks here. The registered operator is known. It affects only one 3.36 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance52

  • Project scale (MW)6
  • Event type20
  • Lifecycle stage10
  • Recency6
  • Operator identified10

Signal materiality25

  • Event type20
  • MW affected5

New planned biomass unit — 3.36 MW

Pfronstetten, Baden-Württemberg · Operator: Firma Bioenergie Aichelau GmbH & Co.KG

1 planned unit · 3.36 MW · First observed 15 Oct 2026

Biomass · Verbrennungsmotor

Planned commissioning: 30 Nov 2026

A new planned biomass unit of 3.36 MW was first observed in this MaStR snapshot.

A newly registered planned asset may be an early sign of a development worth a quick look.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Developer servicesGrid connectionElectrical BOPCivil / BOPEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Registered capacity
3.36 MW
First observed in MaStR snapshot
15 Oct 2026
Planned commissioning
30 Nov 2026
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: First tracked snapshot → 15 Oct 2026
MaStR unit IDs: SEE960696607474
Commercial signals (1): cmvb9v0kv13b9wtdwp3oppzk2

Grouping basisSingle unit
A single MaStR registration.
New planned asset
51Lead relevance · Moderate

Why this ranks here. The registered operator is known. It affects only one 2.15 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance51

  • Project scale (MW)5
  • Event type20
  • Lifecycle stage10
  • Recency6
  • Operator identified10

Signal materiality24

  • Event type20
  • MW affected4

New planned biomass unit — 2.15 MW

Pommerby, Schleswig-Holstein · Operator: Biogas Niedamm GmbH & Co. KG

1 planned unit · 2.15 MW · First observed 15 Oct 2026

Biomass · Verbrennungsmotor

Planned commissioning: 01 Apr 2027

A new planned biomass unit of 2.15 MW was first observed in this MaStR snapshot.

A newly registered planned asset may be an early sign of a development worth a quick look.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Developer servicesGrid connectionElectrical BOPCivil / BOPEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Registered capacity
2.15 MW
First observed in MaStR snapshot
15 Oct 2026
Planned commissioning
01 Apr 2027
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: First tracked snapshot → 15 Oct 2026
MaStR unit IDs: SEE901747148188
Commercial signals (1): cmvb9v0kq1384wtdw80i9nj7u

Grouping basisSingle unit
A single MaStR registration.
New planned asset
50Lead relevance · Moderate

Why this ranks here. The registered operator is known. It affects only one 2 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance50

  • Project scale (MW)4
  • Event type20
  • Lifecycle stage10
  • Recency6
  • Operator identified10

Signal materiality24

  • Event type20
  • MW affected4

New planned gas-generation unit — 2 MW

Hamburg, Hamburg · Operator: Hamburger Energiewerke GmbH

1 planned unit · 2 MW · First observed 15 Oct 2026

Gas generation · Verbrennungsmotor

Planned commissioning: 01 Sept 2027

A new planned gas-generation unit of 2 MW was first observed in this MaStR snapshot.

A newly registered planned asset may be an early sign of a development worth a quick look.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Developer servicesGrid connectionElectrical BOPCivil / BOPEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Registered capacity
2 MW
First observed in MaStR snapshot
15 Oct 2026
Planned commissioning
01 Sept 2027
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: First tracked snapshot → 15 Oct 2026
MaStR unit IDs: SEE976375460827
Commercial signals (1): cmvb9v0kw13cdwtdwqfcydlml

Grouping basisSingle unit
A single MaStR registration.
New planned asset
48Lead relevance · Moderate

Why this ranks here. Operator identity is unresolved, which reduces immediate actionability; it affects only one 6 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance48

  • Project scale (MW)8
  • Event type20
  • Lifecycle stage10
  • Recency6
  • Operator identified4

Signal materiality27

  • Event type20
  • MW affected7

New planned wind unit — 6 MW

Lugau/Erzgeb., Sachsen · Operator: Registered operator name not resolved

1 planned unit · 6 MW · First observed 15 Oct 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 30 Jun 2028

A new planned wind unit of 6 MW was first observed in this MaStR snapshot.

A newly registered planned asset may be an early sign of a development worth a quick look.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Registered capacity
6 MW
First observed in MaStR snapshot
15 Oct 2026
Planned commissioning
30 Jun 2028
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: First tracked snapshot → 15 Oct 2026
MaStR unit IDs: SEE998696377868
Commercial signals (1): cmvb9v0ky13d7wtdwb6wc5cgi

Grouping basisSingle unit
A single MaStR registration.
↑ Back to top

Major schedule changes (12)

Schedule change
69Lead relevance · High

Why this ranks high. Mid-sized 40.8 MW signal, 6 registrations moving together and the registered operator is known.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance69

  • Project scale (MW)19
  • Event type12
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Multi-unit evidence7
  • Size of change4

Signal materiality59

  • Event type16
  • Size of change17
  • MW affected14
  • Units affected12

Commissioning delayed by up to 150 days — 6 units / 40.8 MW

Schkölen, Thüringen · Operator: Windpark Wetzdorf Repowering

6 units · 40.8 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Oct 2026 → Feb 2027 (+150 days)

6 wind units registered a later planned commissioning date (+150 days).

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
6
Planned commissioning (same for every unit)
Oct 2026 → Feb 2027 (+150 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 6 registered MaStR units
Snapshot transition: 15 Oct 2026 → 17 Oct 2026
MaStR unit IDs: SEE919951377201, SEE923901667403, SEE998857505413, SEE965850317916, SEE934826202389, SEE905300219773
Commercial signals (6): cmvbwy1142uidwts4r7em43ky, cmvbwy1142uigwts4uvdb29ks, cmvbwy1142uinwts4seul4akz, cmvbwy1162ujswts4eaeutjzi, cmvbwy1122uh9wts408cy5spt, cmvbwy1132uhvwts4cna9bcgf

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
67Lead relevance · High

Why this ranks high. Mid-sized 29.56 MW signal, 5 registrations moving together, unusually large schedule shift (272 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance67

  • Project scale (MW)17
  • Event type12
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Multi-unit evidence6
  • Size of change5

Signal materiality60

  • Event type16
  • Size of change20
  • MW affected13
  • Units affected11

Commissioning delayed by up to 272 days — 5 units / 29.56 MW

Bad Lippspringe, Nordrhein-Westfalen · Operator: BöcksWind GmbH & Co.KG

5 units · 29.56 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 01 Oct – 01 Dec 2026

5 wind units registered a later planned commissioning date (+211 days to +272 days).

A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
5
Planned commissioning before
01 Oct – 01 Dec 2026
Planned commissioning now
30 Jun 2027
Shift per unit
+211 to +272 days
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“böcksgrund e…”); Same planned/commissioning date on every unit
Presentation group: 5 registered MaStR units
Snapshot transition: 15 Oct 2026 → 17 Oct 2026
MaStR unit IDs: SEE990943035040, SEE965072673098, SEE999107365085, SEE967916891880, SEE973360097150
Commercial signals (5): cmvbwy1152uiwwts4mt847oqe, cmvbwy1162ujvwts4biipsyh0, cmvbwy1122uhgwts4idw5kk39, cmvbwy1162ujpwts4jxhvlg6m, cmvbwy1152ujgwts4mctyr7ki

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“böcksgrund e…”); Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
67Lead relevance · High

Why this ranks high. Mid-sized 28.8 MW signal, 4 registrations moving together, unusually large schedule shift (305 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance67

  • Project scale (MW)17
  • Event type12
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Multi-unit evidence6
  • Size of change5

Signal materiality60

  • Event type16
  • Size of change21
  • MW affected13
  • Units affected10

Commissioning delayed by up to 305 days — 4 units / 28.8 MW

Warendorf, Nordrhein-Westfalen · Operator: Windpark Milte GmbH & Co. KG

4 units · 28.8 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Oct 2026 → Aug 2027 (+305 days)

4 wind units registered a later planned commissioning date (+305 days).

A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
4
Planned commissioning (same for every unit)
Oct 2026 → Aug 2027 (+305 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 4 registered MaStR units
Snapshot transition: 15 Oct 2026 → 17 Oct 2026
MaStR unit IDs: SEE924425954161, SEE970413929987, SEE971097865257, SEE977467883111
Commercial signals (4): cmvbwy1142uihwts4u6n84vh9, cmvbwy1162ujnwts4qgb792de, cmvbwy1162ujlwts483khm426, cmvbwy1152uj7wts4cb2q2105

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
67Lead relevance · High

Why this ranks high. Mid-sized 37 MW signal, 6 registrations moving together and the registered operator is known.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance67

  • Project scale (MW)18
  • Event type12
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence7
  • Size of change4

Signal materiality58

  • Event type16
  • Size of change16
  • MW affected14
  • Units affected12

Commissioning delayed by up to 124 days — 6 units / 37 MW

Jakobsdorf, Mecklenburg-Vorpommern · Operator: Windpark Grünkordshagen-Zandershagen GmbH & Co. KG

6 units · 37 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Sept 2026 → Jan 2027 (+124 days)

6 wind units registered a later planned commissioning date (+124 days).

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
6
Planned commissioning (same for every unit)
Sept 2026 → Jan 2027 (+124 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“grüza…”); Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 6 registered MaStR units
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE980549705379, SEE978064296410, SEE968646402209, SEE905887539615, SEE937575460505, SEE949817886288
Commercial signals (6): cmvb9v0kx13cowtdw8ai0punz, cmvb9v0kx13chwtdw7fkmsd0c, cmvb9v0kv13bswtdwgdclsllm, cmvb9v0kq1389wtdwlfn5zszb, cmvb9v0kt13a2wtdwono6y3p6, cmvb9v0ku13alwtdw107rjbth

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“grüza…”); Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
67Lead relevance · High

Why this ranks high. Mid-sized 36 MW signal, 5 registrations moving together and the registered operator is known.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance67

  • Project scale (MW)18
  • Event type12
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Multi-unit evidence6
  • Size of change4

Signal materiality55

  • Event type16
  • Size of change14
  • MW affected14
  • Units affected11

Commissioning delayed by up to 92 days — 5 units / 36 MW

Plettenberg, Nordrhein-Westfalen · Operator: P-Wind Plettenberg GmbH

5 units · 36 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Oct 2026 → Jan 2027 (+92 days)

5 wind units registered a later planned commissioning date (+92 days).

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
5
Planned commissioning (same for every unit)
Oct 2026 → Jan 2027 (+92 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 5 registered MaStR units
Snapshot transition: 15 Oct 2026 → 17 Oct 2026
MaStR unit IDs: SEE992971035214, SEE958240705868, SEE976515000425, SEE925886507651, SEE976829942756
Commercial signals (5): cmvbwy1142uirwts4cr8t72ny, cmvbwy1172uk3wts4krlp7gnn, cmvbwy1152ujbwts4fr8v75lw, cmvbwy1142uiiwts4azpeetz4, cmvbwy1152uj9wts41bei6m82

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
66Lead relevance · High

Why this ranks high. Mid-sized 26.56 MW signal, 4 registrations moving together, unusually large schedule shift (427 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance66

  • Project scale (MW)16
  • Event type12
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence6
  • Size of change6

Signal materiality61

  • Event type16
  • Size of change23
  • MW affected12
  • Units affected10

Commissioning delayed by up to 427 days — 4 units / 26.56 MW

Heimbach, Nordrhein-Westfalen · Operator: Energiekontor AG

4 units · 26.56 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Jun 2028 → Aug 2029 (+427 days)

4 wind units registered a later planned commissioning date (+427 days).

A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
4
Planned commissioning (same for every unit)
Jun 2028 → Aug 2029 (+427 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 4 registered MaStR units
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE998986367241, SEE965502154814, SEE900322653802, SEE951129821246
Commercial signals (4): cmvb9v0ky13d8wtdwmk9jas0t, cmvb9v0kv13bkwtdwrk1yjr9r, cmvb9v0kq1381wtdwguaexkqn, cmvb9v0ku13aqwtdwypg6o26q

Grouping basisLikely site group
Supporting registry evidence: Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
65Lead relevance · High

Why this ranks high. Mid-sized 36 MW signal, unusually large schedule shift (184 days) and the registered operator is known. The grouping evidence is limited; it may still reflect a registry correction rather than a new commercial need.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance65

  • Project scale (MW)18
  • Event type12
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence4
  • Size of change5

Signal materiality60

  • Event type16
  • Size of change18
  • MW affected14
  • Units affected12

Commissioning rescheduled — 6 units / 36 MW

Brakel, Nordrhein-Westfalen · Operator: Windpark Brakel Modexen GmbH & Co. KG

6 units · 36 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 30 Jun 2026 – 02 Oct 2028

6 wind units registered a changed planned commissioning date (-106 days to +184 days).

A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
6
Planned commissioning before
30 Jun 2026 – 02 Oct 2028
Planned commissioning now
31 Dec 2026 – 18 Jun 2028
Shift per unit
-106 to +184 days
Direction
1 later, 5 earlier
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Conservative group — Identical registered capacity
Presentation group: 6 registered MaStR units
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE935124201180, SEE966882375998, SEE950375424249, SEE955913444895, SEE906898020611, SEE912988239399
Commercial signals (6): cmvb9v0kt139wwtdw69h93wdb, cmvb9v0kv13bpwtdwao6egq5e, cmvb9v0ku13aowtdwntoovb92, cmvb9v0ku13axwtdwyacg3a4b, cmvb9v0kq138ewtdwlmrwqpon, cmvb9v0kr138rwtdw6g11nl9c

Grouping basisConservative group
Supporting registry evidence: Identical registered capacity
These registrations are grouped for presentation because they share location/operator/category characteristics. GridGraph does not assert that this grouping represents one canonical development project.
Schedule change
65Lead relevance · High

Why this ranks high. Mid-sized 17.04 MW signal, 4 registrations moving together, unusually large schedule shift (366 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance65

  • Project scale (MW)14
  • Event type12
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Multi-unit evidence6
  • Size of change6

Signal materiality58

  • Event type16
  • Size of change22
  • MW affected10
  • Units affected10

Commissioning delayed by up to 366 days — 4 units / 17.04 MW

Siesbach, Rheinland-Pfalz · Operator: GERES Power III GmbH

4 units · 17.04 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 30 Sept – 01 Oct 2026

4 wind units registered a later planned commissioning date (+365 days to +366 days).

A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
4
Planned commissioning before
30 Sept – 01 Oct 2026
Planned commissioning now
30 Sept – 02 Oct 2027
Shift per unit
+365 to +366 days
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Planned/commissioning dates within 2 days of each other
Presentation group: 4 registered MaStR units
Snapshot transition: 15 Oct 2026 → 17 Oct 2026
MaStR unit IDs: SEE989434687158, SEE999160794976, SEE975142514848, SEE956912610199
Commercial signals (4): cmvbwy1152uixwts426rtrm5q, cmvbwy1142uilwts4lvb0a2ef, cmvbwy1152ujdwts4rr6qm3jq, cmvbwy1172uk4wts4tl6b8dqk

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Planned/commissioning dates within 2 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
64Lead relevance · High

Why this ranks high. Mid-sized 16.8 MW signal, 4 registrations moving together, unusually large schedule shift (220 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance64

  • Project scale (MW)14
  • Event type12
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Multi-unit evidence6
  • Size of change5

Signal materiality55

  • Event type16
  • Size of change19
  • MW affected10
  • Units affected10

Commissioning moved forward by up to 220 days — 4 units / 16.8 MW

Niederer Fläming, Brandenburg · Operator: Windpark Hohenseefeld 3 GmbH & Co. KG

4 units · 16.8 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 31 Aug 2028

4 wind units registered an earlier planned commissioning date (-220 days to -199 days).

An earlier registered commissioning date may indicate a compressed delivery window and could bring supplier or service requirements forward. It may also be a registry correction.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
4
Planned commissioning before
31 Aug 2028
Planned commissioning now
24 Jan – 14 Feb 2028
Shift per unit
-220 to -199 days
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Planned/commissioning dates within 21 days of each other
Presentation group: 4 registered MaStR units
Snapshot transition: 15 Oct 2026 → 17 Oct 2026
MaStR unit IDs: SEE964270315205, SEE995531731663, SEE905869163425, SEE943509979821
Commercial signals (4): cmvbwy1162ujywts4fluh22io, cmvbwy1142uiowts4cz0z6jcq, cmvbwy1132uhwwts40ve2qq01, cmvbwy1122uhewts4o3cxvgf6

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Planned/commissioning dates within 21 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
63Lead relevance · High

Why this ranks high. Mid-sized 17.1 MW signal, 3 registrations moving together, unusually large schedule shift (243 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance63

  • Project scale (MW)14
  • Event type12
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Multi-unit evidence5
  • Size of change5

Signal materiality54

  • Event type16
  • Size of change20
  • MW affected10
  • Units affected8

Commissioning delayed by up to 243 days — 3 units / 17.1 MW

Zölkow, Mecklenburg-Vorpommern · Operator: Windpark Kladrum Mitte GmbH & Co. KG

3 units · 17.1 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Oct 2026 → Jun 2027 (+243 days)

3 wind units registered a later planned commissioning date (+243 days).

A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
3
Planned commissioning (same for every unit)
Oct 2026 → Jun 2027 (+243 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“kladrumvii n wea…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 3 registered MaStR units
Snapshot transition: 15 Oct 2026 → 17 Oct 2026
MaStR unit IDs: SEE987678872583, SEE970648118606, SEE927549044640
Commercial signals (3): cmvbwy1152uj0wts4zb0fld3g, cmvbwy1162ujmwts48bibr2t1, cmvbwy1172uk6wts4sul5jczg

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“kladrumvii n wea…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
63Lead relevance · High

Why this ranks high. Mid-sized 20.4 MW signal, 3 registrations moving together and the registered operator is known.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance63

  • Project scale (MW)15
  • Event type12
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Multi-unit evidence5
  • Size of change4

Signal materiality51

  • Event type16
  • Size of change16
  • MW affected11
  • Units affected8

Commissioning delayed by up to 137 days — 3 units / 20.4 MW

Bleicherode, Thüringen · Operator: Energiequelle GmbH

3 units · 20.4 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 01 Oct 2026

3 wind units registered a later planned commissioning date (+109 days to +137 days).

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
3
Planned commissioning before
01 Oct 2026
Planned commissioning now
18 Jan – 15 Feb 2027
Shift per unit
+109 to +137 days
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“wp werther west…”); Identical registered capacity; Planned/commissioning dates within 28 days of each other
Presentation group: 3 registered MaStR units
Snapshot transition: 15 Oct 2026 → 17 Oct 2026
MaStR unit IDs: SEE916718398516, SEE933236650797, SEE910052597970
Commercial signals (3): cmvbwy1132ui9wts4uglflbga, cmvbwy1122uh7wts4m0x1rl7w, cmvbwy1132ui2wts4nz341p7m

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“wp werther west…”); Identical registered capacity; Planned/commissioning dates within 28 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
62Lead relevance · High

Why this ranks high. Mid-sized 13.5 MW signal, 3 registrations moving together, unusually large schedule shift (385 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance62

  • Project scale (MW)13
  • Event type12
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence5
  • Size of change6

Signal materiality55

  • Event type16
  • Size of change22
  • MW affected9
  • Units affected8

Commissioning delayed by up to 385 days — 3 units / 13.5 MW

Frechen, Nordrhein-Westfalen · Operator: Energiepark Frechen WP GmbH & Co. KG

3 units · 13.5 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Jun 2026 → Jul 2027 (+385 days)

3 wind units registered a later planned commissioning date (+385 days).

A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
3
Planned commissioning (same for every unit)
Jun 2026 → Jul 2027 (+385 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 3 registered MaStR units
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE995094827391, SEE911014313560, SEE929582252976
Commercial signals (3): cmvb9v0ky13d2wtdwt1ylakee, cmvb9v0kr138nwtdwhvzv8ent, cmvb9v0ks139lwtdw2krvfdk2

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
↑ Back to top

Capacity changes (8)

Multiple changes
63Lead relevance · High

Why this ranks high. Capacity and schedule changes recorded together on the same units and the registered operator is known. Small combined capacity (8.4 MW).

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance63

  • Project scale (MW)10
  • Event type14
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence3
  • Several changes together5
  • Size of change5

Signal materiality55

  • Event type18
  • Size of change18
  • MW affected8
  • Units affected5
  • Several changes together6

Multiple registry changes (capacity + schedule) — 2 units / 8.4 MW

Nordwalde, Nordrhein-Westfalen · Operator: EE Nordwalde ApS & Co. KG

2 units · 8.4 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Sept 2027 → Apr 2028 (+184 days)

2 wind units registered a capacity change; combined registered capacity moved from 12 MW to 8.4 MW (-3.6 MW). 2 wind units registered a later planned commissioning date (+184 days).

Several registry changes were recorded together on the same units. That may indicate a substantive update to the project rather than a routine correction, and is worth investigating.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Design / technologyGrid connectionEngineeringEquipment sizingProject schedulingConstruction timing
Design change?Permit & grid documentsDeveloper updatesRegistry correction?
Facts, hypotheses and how to verify
Per-unit change
2 units changed from 6 MW to 4.2 MW each
Combined registered capacity now
8.4 MW
Combined change
-3.6 MW (-30%)
Units with a new planned date
2
Planned commissioning (same for every unit)
Sept 2027 → Apr 2028 (+184 days)
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Check whether the change reflects a design or turbine-model change
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Compare with permit and grid-connection documents
  • Check permitting and construction status
  • Look for recent developer announcements
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“nordwalde ee…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE968605967312, SEE973984788557
Commercial signals (4): cmvb9v0kv13bqwtdwqowrck3o, cmvb9v0kw13c3wtdw0eq5rhan, cmvb9v0kv13brwtdwr8ugvlpj, cmvb9v0kw13c4wtdwlx5cy0vy

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“nordwalde ee…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Multiple changes
61Lead relevance · High

Why this ranks high. Capacity and schedule changes recorded together on the same units and the registered operator is known. It affects only one 6.9 MW unit.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance61

  • Project scale (MW)9
  • Event type14
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Several changes together5
  • Size of change6

Signal materiality55

  • Event type18
  • Size of change24
  • MW affected7
  • Several changes together6

Multiple registry changes (capacity + schedule) — 6.9 MW

Lünne, Niedersachsen · Operator: Raiffeisen Lünne Projektentwicklung GmbH

1 unit · 6.9 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Dec 2026 → Jun 2028 (+548 days)

Registered capacity changed from 6 MW to 6.9 MW (+0.9 MW, +15%). The registered planned commissioning date moved by +548 days (Dec 2026 → Jun 2028).

Several registry changes were recorded together on the same units. That may indicate a substantive update to the project rather than a routine correction, and is worth investigating.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Design / technologyGrid connectionEngineeringEquipment sizingProject schedulingConstruction timing
Design change?Permit & grid documentsDeveloper updatesRegistry correction?
Facts, hypotheses and how to verify
Registered capacity
6 MW → 6.9 MW (+0.9 MW / +15%)
Planned commissioning
Dec 2026 → Jun 2028 (+548 days)
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Check whether the change reflects a design or turbine-model change
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Compare with permit and grid-connection documents
  • Check permitting and construction status
  • Look for recent developer announcements
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 15 Oct 2026 → 17 Oct 2026
MaStR unit IDs: SEE973233914485
Commercial signals (2): cmvbwy1162ujiwts4gqdwkixk, cmvbwy1162ujhwts4j2lfz05c

Grouping basisSingle unit
A single MaStR registration.
Capacity change
61Lead relevance · High

Why this ranks high. Mid-sized 14 MW signal and the registered operator is known.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance61

  • Project scale (MW)13
  • Event type14
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence3
  • Size of change5

Signal materiality52

  • Event type18
  • Size of change20
  • MW affected9
  • Units affected5

Registered wind capacity reduced (-14 MW) — 2 units / 14 MW

Gutow, Mecklenburg-Vorpommern · Operator: Projekt Windmüller Drgala GmbH

2 units · 14 MW

Wind · Wind turbine (horizontal-axis)

2 wind units registered a capacity change; combined registered capacity moved from 28 MW to 14 MW (-14 MW).

A smaller registered capacity may indicate a scaled-back or redesigned project, which could change the scope of engineering and equipment requirements.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Design / technologyGrid connectionEngineeringEquipment sizing
Design change?Permit & grid documentsDeveloper updates
Facts, hypotheses and how to verify
Per-unit change
2 units changed from 14 MW to 7 MW each
Combined registered capacity now
14 MW
Combined change
-14 MW (-50%)
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Check whether the change reflects a design or turbine-model change
  • Compare with permit and grid-connection documents
  • Look for recent developer announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“bülow e…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE954682631222, SEE965850479850
Commercial signals (2): cmvb9v0ku13avwtdwknvy7vmo, cmvb9v0kv13blwtdwd8sagm7a

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“bülow e…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Multiple changes
60Lead relevance · High

Why this ranks high. Capacity and schedule changes recorded together on the same units and the registered operator is known. It affects only one 7 MW unit.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance60

  • Project scale (MW)9
  • Event type14
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Several changes together5
  • Size of change6

Signal materiality53

  • Event type18
  • Size of change22
  • MW affected7
  • Several changes together6

Multiple registry changes (capacity + schedule) — 7 MW

Leiblfing, Bayern · Operator: Windpower Leiblfing 1 GmbH & Co. KG

1 unit · 7 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Dec 2026 → Dec 2027 (+365 days)

Registered capacity changed from 6 MW to 7 MW (+1 MW, +17%). The registered planned commissioning date moved by +365 days (Dec 2026 → Dec 2027).

Several registry changes were recorded together on the same units. That may indicate a substantive update to the project rather than a routine correction, and is worth investigating.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Design / technologyGrid connectionEngineeringEquipment sizingProject schedulingConstruction timing
Design change?Permit & grid documentsDeveloper updatesRegistry correction?
Facts, hypotheses and how to verify
Registered capacity
6 MW → 7 MW (+1 MW / +17%)
Planned commissioning
Dec 2026 → Dec 2027 (+365 days)
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Check whether the change reflects a design or turbine-model change
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Compare with permit and grid-connection documents
  • Check permitting and construction status
  • Look for recent developer announcements
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE924152115392
Commercial signals (2): cmvb9v0ks139cwtdw61v92lmv, cmvb9v0ks139dwtdwg6g5tq9o

Grouping basisSingle unit
A single MaStR registration.
Capacity change
56Lead relevance · Moderate

Why this ranks here. The registered operator is known. It affects only one 7 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance56

  • Project scale (MW)9
  • Event type14
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Size of change6

Signal materiality49

  • Event type18
  • Size of change24
  • MW affected7

Registered wind capacity increased (+4.7 MW) — 7 MW

Hagen, Nordrhein-Westfalen · Operator: SL Betriebs GmbH & Co. KG

1 unit · 7 MW

Wind · Wind turbine (horizontal-axis)

Registered capacity changed from 2.3 MW to 7 MW (+4.7 MW, +204%).

A larger registered capacity may indicate a changed project design, turbine or equipment choice, or grid-connection scope, and could affect engineering and equipment requirements.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Design / technologyGrid connectionEngineeringEquipment sizing
Design change?Permit & grid documentsDeveloper updates
Facts, hypotheses and how to verify
Registered capacity
2.3 MW → 7 MW (+4.7 MW / +204%)
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Check whether the change reflects a design or turbine-model change
  • Compare with permit and grid-connection documents
  • Look for recent developer announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 15 Oct 2026 → 17 Oct 2026
MaStR unit IDs: SEE931313710792
Commercial signals (1): cmvbwy1172uk7wts4lkdqvuzb

Grouping basisSingle unit
A single MaStR registration.
Capacity change
52Lead relevance · Moderate

Why this ranks here. The registered operator is known. It affects only one 4.26 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance52

  • Project scale (MW)7
  • Event type14
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Size of change5

Signal materiality45

  • Event type18
  • Size of change21
  • MW affected6

Registered wind capacity increased (+1.96 MW) — 4.26 MW

Breuna, Hessen · Operator: Hoppe & Dietz GbR

1 unit · 4.26 MW

Wind · Wind turbine (horizontal-axis)

Registered capacity changed from 2.3 MW to 4.26 MW (+1.96 MW, +85%).

A larger registered capacity may indicate a changed project design, turbine or equipment choice, or grid-connection scope, and could affect engineering and equipment requirements.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Design / technologyGrid connectionEngineeringEquipment sizing
Design change?Permit & grid documentsDeveloper updates
Facts, hypotheses and how to verify
Registered capacity
2.3 MW → 4.26 MW (+1.96 MW / +85%)
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Check whether the change reflects a design or turbine-model change
  • Compare with permit and grid-connection documents
  • Look for recent developer announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE978732212148
Commercial signals (1): cmvb9v0kx13ciwtdwkage4xa2

Grouping basisSingle unit
A single MaStR registration.
Capacity change
52Lead relevance · Moderate

Why this ranks here. The registered operator is known. It affects only one 7 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance52

  • Project scale (MW)9
  • Event type14
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Size of change3

Signal materiality35

  • Event type18
  • Size of change10
  • MW affected7

Registered wind capacity increased (+1 MW) — 7 MW

Biederbach, Baden-Württemberg · Operator: Windenergie Biederbach GmbH & Co. KG

1 unit · 7 MW

Wind · Wind turbine (horizontal-axis)

Registered capacity changed from 6 MW to 7 MW (+1 MW, +17%).

A larger registered capacity may indicate a changed project design, turbine or equipment choice, or grid-connection scope, and could affect engineering and equipment requirements.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Design / technologyGrid connectionEngineeringEquipment sizing
Design change?Permit & grid documentsDeveloper updates
Facts, hypotheses and how to verify
Registered capacity
6 MW → 7 MW (+1 MW / +17%)
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Check whether the change reflects a design or turbine-model change
  • Compare with permit and grid-connection documents
  • Look for recent developer announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE949753726785
Commercial signals (1): cmvb9v0ku13akwtdwgg3pvt78

Grouping basisSingle unit
A single MaStR registration.
Multiple changes
49Lead relevance · Moderate

Why this ranks here. Capacity and commissioning changes recorded together on the same units and the registered operator is known. It affects only one 2.6 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance49

  • Project scale (MW)5
  • Event type14
  • Lifecycle stage4
  • Recency6
  • Operator identified10
  • Several changes together5
  • Size of change5

Signal materiality48

  • Event type18
  • Size of change19
  • MW affected5
  • Several changes together6

Multiple registry changes (capacity + commissioning) — 2.6 MW

Bad Elster, Sachsen · Operator: eins energie in sachsen GmbH & Co. KG

1 unit · 2.6 MW

Gas generation · Verbrennungsmotor

Registered capacity changed from 5.2 MW to 2.6 MW (-2.6 MW, -50%). 1 gas-generation unit (2.6 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 30 Sept 2026.

Several registry changes were recorded together on the same units. That may indicate a substantive update to the project rather than a routine correction, and is worth investigating.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
EngineeringEquipment sizingO&M
Design change?Permit & grid documentsDeveloper updatesMaStR record
Facts, hypotheses and how to verify
Registered capacity
5.2 MW → 2.6 MW (-2.6 MW / -50%)
Registered capacity
2.6 MW
Commissioning date
30 Sept 2026
Lifecycle change
Planned → commissioned
  • Engineering and environmental services
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Check whether the change reflects a design or turbine-model change
  • Confirm operating status and commissioning date in the official MaStR record
  • Compare with permit and grid-connection documents
  • Identify the operating company and public information on service arrangements
  • Look for recent developer announcements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE928464269002
Commercial signals (2): cmvb9v0ks139jwtdw12tkks31, cmvb9v0ks139iwtdww99wruve

Grouping basisSingle unit
Stable MaStR location ID: SEL905985446327
A single MaStR registration.
↑ Back to top

Operator / company changes (12)

Operator change
57Lead relevance · Moderate

Why this ranks here. Mid-sized 35 MW signal and 5 registrations moving together. Operator identity is unresolved, which reduces immediate actionability; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance57

  • Project scale (MW)18
  • Event type13
  • Lifecycle stage10
  • Recency6
  • Operator identified4
  • Multi-unit evidence6

Signal materiality38

  • Event type14
  • MW affected13
  • Units affected11

Registered operator changed on 5 wind units — 5 units / 35 MW

Aschersleben, Sachsen-Anhalt · Operator: 2 registered operators (names not resolved)

5 units · 35 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 5 wind units, now registered to 2 different operators.

Several units moving from one registered operator to different registered operators may reflect project-company restructuring, for example separate operating entities per unit. That is worth checking against company records; the change alone does not establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Units with an operator change
5
Previous registered operator
Sabowind GmbH
New registered operator
2 different registered operators (names not resolved in MaStR reference data; IDs under per-unit values)
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“sw asc…”); Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 5 registered MaStR units
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE969097889007, SEE984690933391, SEE974454178632, SEE917922575137, SEE968763534135
Commercial signals (5): cmvb9v0kw13buwtdwipl50nnn, cmvb9v0kx13cqwtdwjsx0zsc5, cmvb9v0kw13c7wtdwjxbcd2g1, cmvb9v0kr1390wtdwdvlb77p5, cmvb9v0kw13btwtdwkb810ayl

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“sw asc…”); Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Operator change
56Lead relevance · Moderate

Why this ranks here. Mid-sized 42.9 MW signal. Operator identity is unresolved, which reduces immediate actionability; the grouping evidence is limited; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance56

  • Project scale (MW)19
  • Event type13
  • Lifecycle stage10
  • Recency6
  • Operator identified4
  • Multi-unit evidence4

Signal materiality40

  • Event type14
  • MW affected14
  • Units affected12

Registered operator changed on 7 wind units — 7 units / 42.9 MW

Pattensen, Niedersachsen · Operator: Registered operator name not resolved

7 units · 42.9 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 7 wind units.

A registered operator change can be a useful trigger for investigating ownership, project restructuring, or a change in the commercial entity responsible for the asset. It does not by itself establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Units with an operator change
7
Previous registered operator
EnBW Windkraftprojekte GmbH
New registered operator
Operator ID ABR904185947986 (name not resolved)
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Conservative group
Presentation group: 7 registered MaStR units
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE911272041731, SEE914809738241, SEE977886054192, SEE994350822187, SEE904305622557, SEE909958327422, SEE954955110645
Commercial signals (7): cmvb9v0kr138owtdwdavb5suw, cmvb9v0kr138swtdw4u08yqc8, cmvb9v0kx13cgwtdwutuhehes, cmvb9v0kx13d0wtdwskzr0uub, cmvb9v0kq1387wtdwrdisodk5, cmvb9v0kr138jwtdw3t6mkj1e, cmvb9v0ku13awwtdwgslycw70

Grouping basisConservative group
These registrations are grouped for presentation because they share location/operator/category characteristics. GridGraph does not assert that this grouping represents one canonical development project.
Operator change
56Lead relevance · Moderate

Why this ranks here. Mid-sized 31 MW signal and 5 registrations moving together. Operator identity is unresolved, which reduces immediate actionability; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance56

  • Project scale (MW)17
  • Event type13
  • Lifecycle stage10
  • Recency6
  • Operator identified4
  • Multi-unit evidence6

Signal materiality38

  • Event type14
  • MW affected13
  • Units affected11

Registered operator changed on 5 wind units — 5 units / 31 MW

Kirschroth, Rheinland-Pfalz · Operator: Registered operator name not resolved

5 units · 31 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 5 wind units.

A registered operator change can be a useful trigger for investigating ownership, project restructuring, or a change in the commercial entity responsible for the asset. It does not by itself establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Units with an operator change
5
Previous registered operator
NOTUS energy Plan GmbH & Co. KG
New registered operator
Operator ID ABR920591866154 (name not resolved)
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 5 registered MaStR units
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE931943870996, SEE929816984253, SEE917900952561, SEE908182266552, SEE966696507554
Commercial signals (5): cmvb9v0ks139swtdw34ee91do, cmvb9v0ks139nwtdw8nraslbj, cmvb9v0kr138zwtdwjkb7xkyd, cmvb9v0kr138hwtdwkqmgpv0l, cmvb9v0kv13bowtdwxwr0fafw

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Operator change
55Lead relevance · Moderate

Why this ranks here. Mid-sized 14.4 MW signal and the registered operator is known. No external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance55

  • Project scale (MW)13
  • Event type13
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence3

Signal materiality29

  • Event type14
  • MW affected10
  • Units affected5

Registered operator changed on 2 wind units — 2 units / 14.4 MW

Thedinghausen, Niedersachsen · Operator: QE Windpark Beppener Bruch GmbH

2 units · 14.4 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 2 wind units.

A registered operator change can be a useful trigger for investigating ownership, project restructuring, or a change in the commercial entity responsible for the asset. It does not by itself establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Units with an operator change
2
Previous registered operator
WindStrom Erneuerbare Energien GmbH & Co. KG
New registered operator
QE Windpark Beppener Bruch GmbH
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“beppener bruch rep…”); Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE921982365416, SEE976343202817
Commercial signals (2): cmvb9v0ks1398wtdwqqsy1hay, cmvb9v0kw13ccwtdwfblrg214

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“beppener bruch rep…”); Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Operator change
53Lead relevance · Moderate

Why this ranks here. Mid-sized 21 MW signal and 3 registrations moving together. Operator identity is unresolved, which reduces immediate actionability; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance53

  • Project scale (MW)15
  • Event type13
  • Lifecycle stage10
  • Recency6
  • Operator identified4
  • Multi-unit evidence5

Signal materiality33

  • Event type14
  • MW affected11
  • Units affected8

Registered operator changed on 3 wind units — 3 units / 21 MW

Marsberg, Nordrhein-Westfalen · Operator: Registered operator name not resolved

3 units · 21 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 3 wind units.

A registered operator change can be a useful trigger for investigating ownership, project restructuring, or a change in the commercial entity responsible for the asset. It does not by itself establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Units with an operator change
3
Previous registered operator
Operator ID ABR928291291924 (name not resolved)
New registered operator
Operator ID ABR996868001795 (name not resolved)
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 3 registered MaStR units
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE944045826150, SEE915835652594, SEE962323158182
Commercial signals (3): cmvb9v0kt13acwtdwvzfd93sz, cmvb9v0kr138uwtdwti0s1xw7, cmvb9v0kv13bewtdwdh675yb8

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Operator change
49Lead relevance · Moderate

Why this ranks here. Operator identity is unresolved, which reduces immediate actionability; small combined capacity (11.2 MW); no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance49

  • Project scale (MW)12
  • Event type13
  • Lifecycle stage10
  • Recency7
  • Operator identified4
  • Multi-unit evidence3

Signal materiality27

  • Event type14
  • MW affected8
  • Units affected5

Registered operator changed on 2 wind units — 2 units / 11.2 MW

Gleina, Sachsen-Anhalt · Operator: Registered operator name not resolved

2 units · 11.2 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 2 wind units.

A registered operator change can be a useful trigger for investigating ownership, project restructuring, or a change in the commercial entity responsible for the asset. It does not by itself establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Units with an operator change
2
Previous registered operator
EnBW Windkraftprojekte GmbH
New registered operator
Operator ID ABR955509489507 (name not resolved)
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“baumersroda i…”); Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: 15 Oct 2026 → 17 Oct 2026
MaStR unit IDs: SEE974524790931, SEE980536408603
Commercial signals (2): cmvbwy1152ujewts412ux1eit, cmvbwy1152uj4wts4akecxl2o

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“baumersroda i…”); Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Operator change
48Lead relevance · Moderate

Why this ranks here. Operator identity is unresolved, which reduces immediate actionability; small combined capacity (11.12 MW); no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance48

  • Project scale (MW)12
  • Event type13
  • Lifecycle stage10
  • Recency6
  • Operator identified4
  • Multi-unit evidence3

Signal materiality27

  • Event type14
  • MW affected8
  • Units affected5

Registered operator changed on 2 wind units — 2 units / 11.12 MW

Dockendorf, Rheinland-Pfalz · Operator: Registered operator name not resolved

2 units · 11.12 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 2 wind units.

A registered operator change can be a useful trigger for investigating ownership, project restructuring, or a change in the commercial entity responsible for the asset. It does not by itself establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Units with an operator change
2
Previous registered operator
Windenergie Bitburg-Land Planungsgesellschaft mbH
New registered operator
Operator ID ABR922566456865 (name not resolved)
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE972732123435, SEE920275182112
Commercial signals (2): cmvb9v0kw13c2wtdwpwk1sb7x, cmvb9v0kr1395wtdwew7io5db

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Operator change
47Lead relevance · Moderate

Why this ranks here. Operator identity is unresolved, which reduces immediate actionability; small combined capacity (10.5 MW); no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance47

  • Project scale (MW)11
  • Event type13
  • Lifecycle stage10
  • Recency6
  • Operator identified4
  • Multi-unit evidence3

Signal materiality27

  • Event type14
  • MW affected8
  • Units affected5

Registered operator changed on 2 wind units — 2 units / 10.5 MW

Nordwestuckermark, Brandenburg · Operator: Registered operator name not resolved

2 units · 10.5 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 2 wind units.

A registered operator change can be a useful trigger for investigating ownership, project restructuring, or a change in the commercial entity responsible for the asset. It does not by itself establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Units with an operator change
2
Previous registered operator
MLK Brandenburg Windpark Entwicklungs GmbH & Co. KG
New registered operator
Operator ID ABR911387637546 (name not resolved)
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“mlk wp horst…”); Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE965375636790, SEE930756682567
Commercial signals (2): cmvb9v0kv13bjwtdw2f1tq3az, cmvb9v0ks139qwtdwbh2gbysq

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“mlk wp horst…”); Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Operator change
41Lead relevance · Low

Why this ranks here. Operator identity is unresolved, which reduces immediate actionability; it affects only one 5.56 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance41

  • Project scale (MW)8
  • Event type13
  • Lifecycle stage10
  • Recency6
  • Operator identified4

Signal materiality20

  • Event type14
  • MW affected6

Registered operator changed on a wind unit — 5.56 MW

Ingendorf, Rheinland-Pfalz · Operator: Registered operator name not resolved

1 unit · 5.56 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 1 wind unit.

A registered operator change can be a useful trigger for investigating ownership, project restructuring, or a change in the commercial entity responsible for the asset. It does not by itself establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Previous registered operator
Windenergie Bitburg-Land Planungsgesellschaft mbH
New registered operator
Operator ID ABR922566456865 (name not resolved)
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE922169236970
Commercial signals (1): cmvb9v0ks1399wtdwix4z9rkh

Grouping basisSingle unit
A single MaStR registration.
Operator change
41Lead relevance · Low

Why this ranks here. Operator identity is unresolved, which reduces immediate actionability; it affects only one 5.56 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance41

  • Project scale (MW)8
  • Event type13
  • Lifecycle stage10
  • Recency6
  • Operator identified4

Signal materiality20

  • Event type14
  • MW affected6

Registered operator changed on a wind unit — 5.56 MW

Wettlingen, Rheinland-Pfalz · Operator: Registered operator name not resolved

1 unit · 5.56 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 1 wind unit.

A registered operator change can be a useful trigger for investigating ownership, project restructuring, or a change in the commercial entity responsible for the asset. It does not by itself establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Previous registered operator
Windenergie Bitburg-Land Planungsgesellschaft mbH
New registered operator
Operator ID ABR922566456865 (name not resolved)
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE906044624397
Commercial signals (1): cmvb9v0kq138cwtdw2u5hc7jy

Grouping basisSingle unit
A single MaStR registration.
Operator change
40Lead relevance · Low

Why this ranks here. Operator identity is unresolved, which reduces immediate actionability; small combined capacity (8.52 MW); no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance40

  • Project scale (MW)10
  • Event type13
  • Lifecycle stage4
  • Recency6
  • Operator identified4
  • Multi-unit evidence3

Signal materiality27

  • Event type14
  • MW affected8
  • Units affected5

Registered operator changed on 2 wind units — 2 units / 8.52 MW

Diepholz, Niedersachsen · Operator: 2 registered operators (names not resolved)

2 units · 8.52 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 2 wind units, now registered to 2 different operators.

Several units moving from one registered operator to different registered operators may reflect project-company restructuring, for example separate operating entities per unit. That is worth checking against company records; the change alone does not establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligenceO&M
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Units with an operator change
2
Previous registered operator
Westwind Projektierungs GmbH & Co. KG
New registered operator
2 different registered operators (names not resolved in MaStR reference data; IDs under per-unit values)
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Site-level (shared MaStR location ID) — Shared stable MaStR location ID
Presentation group: 2 registered MaStR units
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE959906428558, SEE962226547151
Commercial signals (2): cmvb9v0kv13b6wtdwu830jddc, cmvb9v0kv13bdwtdwmsgxroid

Grouping basisSite-level (shared MaStR location ID)
Supporting registry evidence: Shared stable MaStR location ID
These registrations share a stable MaStR location ID. GridGraph still does not assert that they form one canonical development project.
Operator change
40Lead relevance · Low

Why this ranks here. Operator identity is unresolved, which reduces immediate actionability; it affects only one 4.2 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance40

  • Project scale (MW)6
  • Event type13
  • Lifecycle stage10
  • Recency7
  • Operator identified4

Signal materiality20

  • Event type14
  • MW affected6

Registered operator changed on a wind unit — 4.2 MW

Prenzlau, Brandenburg · Operator: Registered operator name not resolved

1 unit · 4.2 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 1 wind unit.

A registered operator change can be a useful trigger for investigating ownership, project restructuring, or a change in the commercial entity responsible for the asset. It does not by itself establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Previous registered operator
Affeldt Wind Güstow
New registered operator
Operator ID ABR911387637546 (name not resolved)
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 15 Oct 2026 → 17 Oct 2026
MaStR unit IDs: SEE938294352034
Commercial signals (1): cmvbwy1122uhdwts47xpjf9b4

Grouping basisSingle unit
A single MaStR registration.
↑ Back to top

Recently commissioned assets (12)

Commissioned asset
46Lead relevance · Moderate

Why this ranks here. Mid-sized 21 MW signal, 3 registrations moving together and the registered operator is known. Already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance46

  • Project scale (MW)15
  • Event type6
  • Lifecycle stage3
  • Recency7
  • Operator identified10
  • Multi-unit evidence5

Signal materiality31

  • Event type12
  • MW affected11
  • Units affected8

3 wind units commissioned — 3 units / 21 MW

Bedburg, Nordrhein-Westfalen · Operator: RWE Windpark Bedburg A44n GmbH & Co. KG

3 units · 21 MW

Wind · Wind turbine (horizontal-axis)

3 wind units (21 MW) moved from planned to commissioned status in MaStR, with registered commissioning dates between 23 Sept – 14 Oct 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Units commissioned
3
Total registered capacity
21 MW
Commissioned between
23 Sept – 14 Oct 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“wind onshore bedburg…”); Identical registered capacity; Planned/commissioning dates within 21 days of each other
Presentation group: 3 registered MaStR units
Snapshot transition: 15 Oct 2026 → 17 Oct 2026
MaStR unit IDs: SEE917791857488, SEE991747988044, SEE986769530517
Commercial signals (3): cmvbwy1142uiawts41zprgd9a, cmvbwy1142uitwts419oq2p1k, cmvbwy1152uj1wts4wrkzlmqo

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“wind onshore bedburg…”); Identical registered capacity; Planned/commissioning dates within 21 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Commissioned asset
45Lead relevance · Moderate

Why this ranks here. Mid-sized 21 MW signal, 3 registrations moving together and the registered operator is known. Already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance45

  • Project scale (MW)15
  • Event type6
  • Lifecycle stage3
  • Recency6
  • Operator identified10
  • Multi-unit evidence5

Signal materiality31

  • Event type12
  • MW affected11
  • Units affected8

3 wind units commissioned — 3 units / 21 MW

Blankenhain, Thüringen · Operator: meridian Windpark Kleinlohma GmbH & Co. KG

3 units · 21 MW

Wind · Wind turbine (horizontal-axis)

3 wind units (21 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 24 Sept 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Units commissioned
3
Total registered capacity
21 MW
Commissioning date
24 Sept 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 3 registered MaStR units
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE989403528130, SEE943916843111, SEE950208476223
Commercial signals (3): cmvb9v0kx13ctwtdwh6ck5h7x, cmvb9v0kt13aawtdwakvw0y10, cmvb9v0ku13amwtdw9732qv1h

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Commissioned asset
44Lead relevance · Low

Why this ranks here. Mid-sized 18.6 MW signal, 3 registrations moving together and the registered operator is known. Already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance44

  • Project scale (MW)14
  • Event type6
  • Lifecycle stage3
  • Recency6
  • Operator identified10
  • Multi-unit evidence5

Signal materiality31

  • Event type12
  • MW affected11
  • Units affected8

3 wind units commissioned — 3 units / 18.6 MW

Günstedt, Thüringen · Operator: meridian Windpark Günstedt GmbH & Co.KG

3 units · 18.6 MW

Wind · Wind turbine (horizontal-axis)

3 wind units (18.6 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 17 Sept 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Units commissioned
3
Total registered capacity
18.6 MW
Commissioning date
17 Sept 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 3 registered MaStR units
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE920007650674, SEE963937530036, SEE948812296214
Commercial signals (3): cmvb9v0kr1394wtdw52fjbe2z, cmvb9v0kv13bfwtdwlqcdxq6n, cmvb9v0ku13ajwtdwdhy3ilk9

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Commissioned asset
43Lead relevance · Low

Why this ranks here. Mid-sized 21.9 MW signal and the registered operator is known. The grouping evidence is limited; already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance43

  • Project scale (MW)15
  • Event type6
  • Lifecycle stage3
  • Recency6
  • Operator identified10
  • Multi-unit evidence3

Signal materiality33

  • Event type12
  • MW affected11
  • Units affected10

4 wind units commissioned — 4 units / 21.9 MW

Seewald, Baden-Württemberg · Operator: Windpark Seewald GmbH & Co. KG

4 units · 21.9 MW

Wind · Wind turbine (horizontal-axis)

4 wind units (21.9 MW) moved from planned to commissioned status in MaStR, with registered commissioning dates between 07 Oct – 14 Oct 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Units commissioned
4
Total registered capacity
21.9 MW
Commissioned between
07 Oct – 14 Oct 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Conservative group — Planned/commissioning dates within 7 days of each other
Presentation group: 4 registered MaStR units
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE922873382420, SEE972161122559, SEE956536975353, SEE925628601005
Commercial signals (4): cmvb9v0ks139awtdws2oj78vz, cmvb9v0kw13bzwtdwqpvivg98, cmvb9v0ku13azwtdwncvgy18p, cmvb9v0ks139gwtdwansvij1c

Grouping basisConservative group
Supporting registry evidence: Planned/commissioning dates within 7 days of each other
These registrations are grouped for presentation because they share location/operator/category characteristics. GridGraph does not assert that this grouping represents one canonical development project.
Commissioned asset
42Lead relevance · Low

Why this ranks here. Mid-sized 14 MW signal and the registered operator is known. Already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance42

  • Project scale (MW)13
  • Event type6
  • Lifecycle stage3
  • Recency7
  • Operator identified10
  • Multi-unit evidence3

Signal materiality26

  • Event type12
  • MW affected9
  • Units affected5

2 wind units commissioned — 2 units / 14 MW

Groß Buchwald, Schleswig-Holstein · Operator: GREE Groß Buchwald-Bissee GmbH & Co. KG

2 units · 14 MW

Wind · Wind turbine (horizontal-axis)

2 wind units (14 MW) moved from planned to commissioned status in MaStR, with registered commissioning dates between 01 Oct – 14 Oct 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Units commissioned
2
Total registered capacity
14 MW
Commissioned between
01 Oct – 14 Oct 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Planned/commissioning dates within 13 days of each other
Presentation group: 2 registered MaStR units
Snapshot transition: 15 Oct 2026 → 17 Oct 2026
MaStR unit IDs: SEE935935551122, SEE976078156218
Commercial signals (2): cmvbwy1122uhcwts4c9yu1o3w, cmvbwy1152ujcwts4ugqft4m1

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Planned/commissioning dates within 13 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Commissioned asset
42Lead relevance · Low

Why this ranks here. Mid-sized 13.6 MW signal and the registered operator is known. Already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance42

  • Project scale (MW)13
  • Event type6
  • Lifecycle stage3
  • Recency7
  • Operator identified10
  • Multi-unit evidence3

Signal materiality26

  • Event type12
  • MW affected9
  • Units affected5

2 wind units commissioned — 2 units / 13.6 MW

Düren, Nordrhein-Westfalen · Operator: RWE Wind Onshore & PV Deutschland GmbH

2 units · 13.6 MW

Wind · Wind turbine (horizontal-axis)

2 wind units (13.6 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 08 Oct 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Units commissioned
2
Total registered capacity
13.6 MW
Commissioning date
08 Oct 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“wind onshore düren merken…”); Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: 15 Oct 2026 → 17 Oct 2026
MaStR unit IDs: SEE934497543521, SEE989145903295
Commercial signals (2): cmvbwy1122uh8wts4yd5hr7vw, cmvbwy1152uizwts4caeqzjh6

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“wind onshore düren merken…”); Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Commissioned asset
41Lead relevance · Low

Why this ranks here. Mid-sized 14.4 MW signal and the registered operator is known. Already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance41

  • Project scale (MW)13
  • Event type6
  • Lifecycle stage3
  • Recency6
  • Operator identified10
  • Multi-unit evidence3

Signal materiality27

  • Event type12
  • MW affected10
  • Units affected5

2 wind units commissioned — 2 units / 14.4 MW

Oberkirch, Baden-Württemberg · Operator: Windpark Hummelsebene GmbH & Co. KG

2 units · 14.4 MW

Wind · Wind turbine (horizontal-axis)

2 wind units (14.4 MW) moved from planned to commissioned status in MaStR, with registered commissioning dates between 01 Oct – 09 Oct 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Units commissioned
2
Total registered capacity
14.4 MW
Commissioned between
01 Oct – 09 Oct 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“hummelsebene…”); Identical registered capacity; Planned/commissioning dates within 8 days of each other
Presentation group: 2 registered MaStR units
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE924209903408, SEE940077001756
Commercial signals (2): cmvb9v0ks139fwtdw6tiouex0, cmvb9v0kt13a8wtdwc8zqsei7

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“hummelsebene…”); Identical registered capacity; Planned/commissioning dates within 8 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Commissioned asset
41Lead relevance · Low

Why this ranks here. Mid-sized 13.6 MW signal and the registered operator is known. Already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance41

  • Project scale (MW)13
  • Event type6
  • Lifecycle stage3
  • Recency6
  • Operator identified10
  • Multi-unit evidence3

Signal materiality26

  • Event type12
  • MW affected9
  • Units affected5

2 wind units commissioned — 2 units / 13.6 MW

Marienmünster, Nordrhein-Westfalen · Operator: Bürgerwind Marienmünster I GmbH & Co. KG

2 units · 13.6 MW

Wind · Wind turbine (horizontal-axis)

2 wind units (13.6 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 08 Oct 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Units commissioned
2
Total registered capacity
13.6 MW
Commissioning date
08 Oct 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE964835940767, SEE900433381939
Commercial signals (2): cmvb9v0kv13bhwtdw7f0x9733, cmvb9v0kq1383wtdw1505iw40

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Commissioned asset
41Lead relevance · Low

Why this ranks here. Mid-sized 13.6 MW signal and the registered operator is known. Already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance41

  • Project scale (MW)13
  • Event type6
  • Lifecycle stage3
  • Recency6
  • Operator identified10
  • Multi-unit evidence3

Signal materiality26

  • Event type12
  • MW affected9
  • Units affected5

2 wind units commissioned — 2 units / 13.6 MW

Weißenbrunn, Bayern · Operator: Bürgerwindpark Weißenbrunn-Gössersdorf GmbH & Co. KG

2 units · 13.6 MW

Wind · Wind turbine (horizontal-axis)

2 wind units (13.6 MW) moved from planned to commissioned status in MaStR, with registered commissioning dates between 21 Sept – 28 Sept 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Units commissioned
2
Total registered capacity
13.6 MW
Commissioned between
21 Sept – 28 Sept 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“wea bürgerwindpark weißenbrunn gössersdorf…”); Identical registered capacity; Planned/commissioning dates within 7 days of each other
Presentation group: 2 registered MaStR units
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE972612951066, SEE964269791041
Commercial signals (2): cmvb9v0kw13c1wtdwpqojxbzo, cmvb9v0kv13bgwtdwc5q2set7

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“wea bürgerwindpark weißenbrunn gössersdorf…”); Identical registered capacity; Planned/commissioning dates within 7 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Commissioned asset
41Lead relevance · Low

Why this ranks here. The registered operator is known. Small combined capacity (12 MW); already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance41

  • Project scale (MW)12
  • Event type6
  • Lifecycle stage3
  • Recency7
  • Operator identified10
  • Multi-unit evidence3

Signal materiality26

  • Event type12
  • MW affected9
  • Units affected5

2 wind units commissioned — 2 units / 12 MW

Kirchhundem, Nordrhein-Westfalen · Operator: Windpark Kirchhundem GmbH

2 units · 12 MW

Wind · Wind turbine (horizontal-axis)

2 wind units (12 MW) moved from planned to commissioned status in MaStR, with registered commissioning dates between 13 Oct – 14 Oct 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Units commissioned
2
Total registered capacity
12 MW
Commissioned between
13 Oct – 14 Oct 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“wp kirchhundem…”); Identical registered capacity; Planned/commissioning dates within 1 days of each other
Presentation group: 2 registered MaStR units
Snapshot transition: 15 Oct 2026 → 17 Oct 2026
MaStR unit IDs: SEE945889137327, SEE989205288843
Commercial signals (2): cmvbwy1122uhfwts4348essex, cmvbwy1152uiywts4bmupk0oi

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“wp kirchhundem…”); Identical registered capacity; Planned/commissioning dates within 1 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Commissioned asset
39Lead relevance · Low

Why this ranks here. Mid-sized 15 MW signal and the registered operator is known. Only one registered unit; already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance39

  • Project scale (MW)13
  • Event type6
  • Lifecycle stage3
  • Recency7
  • Operator identified10

Signal materiality22

  • Event type12
  • MW affected10

Wind unit commissioned — 15 MW — MaStR SEE977283513094

Ausschließliche Wirtschaftszone · Operator: EnBW He Dreiht GmbH & Co. KG

1 unit · 15 MW

Wind · Wind turbine (horizontal-axis)

1 wind unit (15 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 23 Sept 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Registered capacity
15 MW
Commissioning date
23 Sept 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 15 Oct 2026 → 17 Oct 2026
MaStR unit IDs: SEE977283513094
Commercial signals (1): cmvbwy1152uj8wts449wi2ry3

Grouping basisSingle unit
Stable MaStR location ID: SEL934908846456
A single MaStR registration.
Commissioned asset
39Lead relevance · Low

Why this ranks here. Mid-sized 15 MW signal and the registered operator is known. Only one registered unit; already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance39

  • Project scale (MW)13
  • Event type6
  • Lifecycle stage3
  • Recency7
  • Operator identified10

Signal materiality22

  • Event type12
  • MW affected10

Wind unit commissioned — 15 MW — MaStR SEE951024907250

Ausschließliche Wirtschaftszone · Operator: EnBW He Dreiht GmbH & Co. KG

1 unit · 15 MW

Wind · Wind turbine (horizontal-axis)

1 wind unit (15 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 11 Oct 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Registered capacity
15 MW
Commissioning date
11 Oct 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 15 Oct 2026 → 17 Oct 2026
MaStR unit IDs: SEE951024907250
Commercial signals (1): cmvbwy1122uhnwts401eyezh6

Grouping basisSingle unit
Stable MaStR location ID: SEL951658670926
A single MaStR registration.
↑ Back to top

Other registry changes (3)

Smaller registry changes, listed for completeness.

Schedule change
57Lead relevance · Moderate

Why this ranks here. Mid-sized 37.2 MW signal, 6 registrations moving together and the registered operator is known. Short date shifts are common registry maintenance; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance57

  • Project scale (MW)18
  • Event type4
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence7
  • Size of change2

Signal materiality48

  • Event type16
  • Size of change6
  • MW affected14
  • Units affected12

Commissioning delayed by up to 20 days — 6 units / 37.2 MW

Bad Berleburg, Nordrhein-Westfalen · Operator: K E Energy Holding GmbH & Co. KG

6 units · 37.2 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 25 Apr 2028 → 15 May 2028 (+20 days)

6 wind units registered a later planned commissioning date (+20 days).

A short date shift is common and may be routine registry maintenance. Worth attention mainly if it is part of a wider pattern.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
6
Planned commissioning (same for every unit)
25 Apr 2028 → 15 May 2028 (+20 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“bärenkopf…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 6 registered MaStR units
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE996019448844, SEE994138283353, SEE936013108597, SEE972213049179, SEE975305836329, SEE961059275255
Commercial signals (6): cmvb9v0ky13d4wtdwm89h9w5l, cmvb9v0kx13cywtdw7jx0eehu, cmvb9v0kt139ywtdwzupe0bun, cmvb9v0kw13c0wtdw0cgf8yl1, cmvb9v0kw13c9wtdwsoefemk3, cmvb9v0kv13bbwtdwhz8of132

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“bärenkopf…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
47Lead relevance · Moderate

Why this ranks here. The registered operator is known. Small combined capacity (11.4 MW); short date shifts are common registry maintenance; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance47

  • Project scale (MW)12
  • Event type4
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Multi-unit evidence3
  • Size of change1

Signal materiality35

  • Event type16
  • Size of change5
  • MW affected9
  • Units affected5

Commissioning delayed by up to 18 days — 2 units / 11.4 MW

Groß Luckow, Mecklenburg-Vorpommern · Operator: wpd Windpark Groß Luckow GmbH & Co. KG

2 units · 11.4 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 30 Nov 2026

2 wind units registered a later planned commissioning date (+4 days to +18 days).

A short date shift is common and may be routine registry maintenance. Worth attention mainly if it is part of a wider pattern.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
2
Planned commissioning before
30 Nov 2026
Planned commissioning now
04 Dec – 18 Dec 2026
Shift per unit
+4 to +18 days
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“grolu…”); Identical registered capacity; Planned/commissioning dates within 14 days of each other
Presentation group: 2 registered MaStR units
Snapshot transition: 15 Oct 2026 → 17 Oct 2026
MaStR unit IDs: SEE980128738590, SEE969520468847
Commercial signals (2): cmvbwy1152uj6wts4ci3t8tc8, cmvbwy1162ujowts49s4zceqt

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“grolu…”); Identical registered capacity; Planned/commissioning dates within 14 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
40Lead relevance · Low

Why this ranks here. The registered operator is known. It affects only one 6.8 MW unit; short date shifts are common registry maintenance; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance40

  • Project scale (MW)9
  • Event type4
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Size of change1

Signal materiality26

  • Event type16
  • Size of change3
  • MW affected7

Commissioning delayed by 10 days — 6.8 MW

Marienfließ, Brandenburg · Operator: KWE Windpark Meyenburg Zwei GmbH & Co. KG

1 unit · 6.8 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 21 Dec 2026 → 31 Dec 2026 (+10 days)

The registered planned commissioning date moved by +10 days (21 Dec 2026 → 31 Dec 2026).

A short date shift is common and may be routine registry maintenance. Worth attention mainly if it is part of a wider pattern.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Planned commissioning
21 Dec 2026 → 31 Dec 2026 (+10 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 6 Oct 2026 → 15 Oct 2026
MaStR unit IDs: SEE974396952383
Commercial signals (1): cmvb9v0kw13c5wtdw2qon0vnu

Grouping basisSingle unit
A single MaStR registration.
↑ Back to top

Receive a filtered weekly brief for your market

Tell us which Bundesländer and technologies you care about and we'll follow up with a weekly brief scoped to that — not the full report.

Relevant Bundesländer (optional)
Relevant technologies (optional)

We'll only use this to follow up with a filtered weekly brief for your market. Read how your data is stored and how to withdraw at any time in our Privacy Policy.