Intelligence brief

German Energy Asset Change Intelligence — 2026-11-03

A curated, source-traceable view of registered MaStR asset updates.

Coverage: 28 Oct – 03 Nov 2026Latest MaStR snapshot: 3 Nov 2026Snapshots compared: 2

Covers about a week of snapshots. Do not compare its counts with daily reports.

Source coverageLatest MaStR snapshot: 3 Nov 2026Changes compared with: 28 Oct 2026Brief generated: 3 Nov 2026
8Top opportunities shown
The diversified selection shown in the Top section. 39 grouped events score above the investigation threshold in total. A registry signal only: it does not establish procurement activity or buyer intent.
9New development signals
24Major schedule shifts
6Operator changes
17Commissioning events
240.01 MWNewly planned capacity

58 grouped events (units merged into likely site groups; not confirmed projects). Unit-level records: 155 registry changes across 154 registrations, 1.17 GW registered capacity.

Start here

  1. 78Commissioning delayed by up to 97 days — 27 units / 405 MW · Ausschließliche Wirtschaftszone
  2. 75New planned wind development signal — 15 units / 90 MW · Wedemark, Niedersachsen
  3. 71Commissioning delayed by up to 90 days — 7 units / 47.6 MW · Bronkow, Brandenburg
  4. 70New planned wind development signal — 8 units / 53.3 MW · Prenzlau, Brandenburg
  5. 70New planned hydro development signal — 3 units / 22.8 MW · Forbach, Baden-Württemberg

Receive a filtered weekly brief for your market

Tell us which Bundesländer and technologies you care about and we'll follow up with a weekly brief scoped to that — not the full report.

Relevant Bundesländer (optional)
Relevant technologies (optional)

We'll only use this to follow up with a filtered weekly brief for your market. Read how your data is stored and how to withdraw at any time in our Privacy Policy.

Top opportunities to investigate (8)

Selected from the highest-scoring investigation signals, with category diversification to avoid repetitive results. Cards are ordered by opportunity score; a higher-scoring signal of an already well-represented type may appear in a section below. Scores are deterministic and are not probabilities. Everything here is a starting point for verification, not evidence of demand.

Schedule change
78Lead relevance · Very high

Why this ranks high. Large 405 MW multi-unit signal, 27 registrations moving together and the registered operator is known.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance78

  • Project scale (MW)25
  • Event type12
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Multi-unit evidence9
  • Size of change4

Signal materiality65

  • Event type16
  • Size of change14
  • MW affected20
  • Units affected15

Commissioning delayed by up to 97 days — 27 units / 405 MW

Ausschließliche Wirtschaftszone · Operator: Nordseecluster A GmbH & Co. KG

27 units · 405 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 25 Sept 2026

27 wind units registered a later planned commissioning date (+36 days to +97 days).

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
27
Planned commissioning before
25 Sept 2026
Planned commissioning now
31 Oct – 31 Dec 2026
Shift per unit
+36 to +97 days
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Planned/commissioning dates within 61 days of each other
Presentation group: 27 registered MaStR units
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE900513297235, SEE902663504331, SEE906006978216, SEE909382805954, SEE910064003308, SEE912766297955, SEE914229395819, SEE920019158410, SEE920824374135, SEE924000723038, SEE939755406938, SEE949339640498, SEE952197771259, SEE958300498112, SEE958327266701, SEE961975761351, SEE964309087554, SEE965247303478, SEE967113701593, SEE971714837612, SEE973119472863, SEE976669730117, SEE989188540167, SEE993505953028, SEE994396655169, SEE998932559942, SEE999304048637
Commercial signals (27): cmw0azqhj13edwtvoarsknhgn, cmw0azqhj13eewtvo0b010c6a, cmw0azqhj13elwtvo3uaq3ez5, cmw0azqhk13epwtvo9wbenbm4, cmw0azqhk13erwtvom9usopfv, cmw0azqhk13euwtvolwdar141, cmw0azqhk13evwtvo0mn0fwa9, cmw0azqhk13f6wtvo7ve1lofz, cmw0azqhk13f8wtvo710naeso, cmw0azqhl13fjwtvoo0orv16u, cmw0azqhl13fuwtvozweegdrf, cmw0azqhm13g0wtvof03w2din, cmw0azqhm13g6wtvokw392yne, cmw0azqhm13gcwtvoii3lj2mj, cmw0azqhm13gdwtvos8vxti55, cmw0azqhm13giwtvot0q5rsmi, cmw0azqhn13gkwtvocje0vkh8, cmw0azqhn13gmwtvow1cssycd, cmw0azqhn13gowtvo10pkmahr, cmw0azqhn13gtwtvozzpuho3h, cmw0azqhn13gxwtvo8gh0vked, cmw0azqhn13h0wtvonvvldvbj, cmw0azqho13hlwtvomst86zx3, cmw0azqho13hpwtvo801pqs6m, cmw0azqho13hswtvokhibblmy, cmw0azqhp13hzwtvog3b6ay3h, cmw0azqhp13i0wtvoaiws0y8n

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Planned/commissioning dates within 61 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
New planned asset
75Lead relevance · Very high

Why this ranks high. Large 90 MW multi-unit signal, 15 registrations moving together and the registered operator is known. External corroboration is only partial.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance75

  • Project scale (MW)23
  • Event type20
  • Lifecycle stage10
  • Recency1
  • Operator identified10
  • Multi-unit evidence9
  • External verification2

Signal materiality53

  • Event type20
  • MW affected18
  • Units affected15

New planned wind development signal — 15 units / 90 MW

Wedemark, Niedersachsen · Operator: enercity Erneuerbare Projekte GmbH & Co. KG

15 planned units · 90 MW · First observed 05 Oct 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 31 Mar 2029

15 new planned wind units totalling 90 MW were first observed in this MaStR snapshot.

A multi-unit planned development of this scale may represent an early commercial signal worth investigating.

  • MaStR evidence: HIGH
  • Partially corroborated externally · 3 independent sources

Project corroboration does not establish procurement activity.

Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
15
Total registered capacity
90 MW
Capacity per unit
6 MW each
First observed in MaStR snapshot
05 Oct 2026
Planned commissioning
31 Mar 2029
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
External evidence details

External verification: Partially corroborated

Some external sources mention a wind development in Wedemark, but the match to the registered project is incomplete. No public procurement evidence was found in this verification run.

Project company
enercity Erneuerbare Projekte GmbH & Co. KG (registered in MaStR; not confirmed externally)
Developer
Not identified
Project evidence
Partial
Commercial evidence
None found

No public procurement evidence was found in this verification run.

3 independent external sources.

Registry lead relevance: 73 → After external verification: 75 (+2) +2: identity or project only partially corroborated.

Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Partially corroborated — 3 independent external sources at medium confidence or better. External evidence is additional context and never replaces or downgrades the MaStR record; project corroboration is not evidence of procurement or buyer intent.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 15 registered MaStR units
Snapshot transition: First tracked snapshot → 5 Oct 2026
MaStR unit IDs: SEE923204127666, SEE925495710510, SEE929685830927, SEE933695925719, SEE944728701927, SEE961214323166, SEE967149497125, SEE969928819470, SEE971781082830, SEE973642474112, SEE984735409928, SEE986137951142, SEE990224736680, SEE990607072633, SEE992996000013
Commercial signals (15): cmuvj7xi90y3awtd4yhgsv1sc, cmuvj7xi90y3gwtd4hahtor5s, cmuvj7xia0y3pwtd4205sg4ij, cmuvj7xia0y3xwtd4ua3060fd, cmuvj7xib0y4mwtd44efl6lhn, cmuvj7xid0y5twtd4pooq49rz, cmuvj7xie0y6gwtd4d6twpthf, cmuvj7xie0y6owtd4qgv0kixh, cmuvj7xie0y6twtd4hti0cw18, cmuvj7xif0y71wtd47c2vritx, cmuvj7xig0y7ywtd49o6c9b8n, cmuvj7xig0y80wtd4pcpwm7zx, cmuvj7xig0y89wtd4chy661fo, cmuvj7xig0y8cwtd4laercppk, cmuvj7xih0y8nwtd4u387e01a

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
71Lead relevance · High

Why this ranks high. Large 47.6 MW multi-unit signal, 7 registrations moving together and the registered operator is known.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance71

  • Project scale (MW)20
  • Event type12
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Multi-unit evidence7
  • Size of change4

Signal materiality57

  • Event type16
  • Size of change14
  • MW affected15
  • Units affected12

Commissioning delayed by up to 90 days — 7 units / 47.6 MW

Bronkow, Brandenburg · Operator: UGE Bronkow Nord Eins GmbH & Co. KG Umweltgereche Energie

7 units · 47.6 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 07 Oct 2026 – 03 Mar 2027

7 wind units registered a later planned commissioning date (+53 days to +90 days).

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
7
Planned commissioning before
07 Oct 2026 – 03 Mar 2027
Planned commissioning now
30 Nov 2026 – 30 Apr 2027
Shift per unit
+53 to +90 days
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“bronkow…”); Identical registered capacity
Presentation group: 7 registered MaStR units
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE903927066626, SEE904780070980, SEE911259769474, SEE922401898782, SEE922955001027, SEE983215630630, SEE993748963082
Commercial signals (7): cmw0azqhj13efwtvob0l8hq51, cmw0azqhj13ehwtvo6zov6ub7, cmw0azqhk13etwtvo0zjnwjyo, cmw0azqhl13fcwtvow949gec1, cmw0azqhl13fewtvo5mz0le4g, cmw0azqho13h7wtvoee05pz6r, cmw0azqho13hqwtvotgppjqv2

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“bronkow…”); Identical registered capacity
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
New planned asset
70Lead relevance · High

Why this ranks high. Large 53.3 MW multi-unit signal, 8 registrations moving together and the registered operator is known. External corroboration is only partial.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance70

  • Project scale (MW)20
  • Event type20
  • Lifecycle stage10
  • Recency1
  • Operator identified10
  • Multi-unit evidence7
  • External verification2

Signal materiality48

  • Event type20
  • MW affected15
  • Units affected13

New planned wind development signal — 8 units / 53.3 MW

Prenzlau, Brandenburg · Operator: Denker & Wulf AG

8 planned units · 53.3 MW · First observed 05 Oct 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 30 Sept 2029

8 new planned wind units totalling 53.3 MW were first observed in this MaStR snapshot.

A multi-unit planned development of this scale may represent an early commercial signal worth investigating.

  • MaStR evidence: HIGH
  • Partially corroborated externally · 1 independent source

Project corroboration does not establish procurement activity.

Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
8
Total registered capacity
53.3 MW
Capacity per unit
5.7–6.8 MW per unit
First observed in MaStR snapshot
05 Oct 2026
Planned commissioning
30 Sept 2029
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
External evidence details

External verification: Partially corroborated

Some external sources mention a wind development in Prenzlau, but the match to the registered project is incomplete. No public procurement evidence was found in this verification run.

Project company
Denker & Wulf AG (registered in MaStR; not confirmed externally)
Developer
Not identified
Project evidence
Partial
Commercial evidence
None found

No public procurement evidence was found in this verification run.

1 independent external source.

Registry lead relevance: 68 → After external verification: 70 (+2) +2: identity or project only partially corroborated.

Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Partially corroborated — 1 independent external source at medium confidence or better. External evidence is additional context and never replaces or downgrades the MaStR record; project corroboration is not evidence of procurement or buyer intent.
Grouping: Likely site group — Shared unit-name pattern (“klinkow…”); Same planned/commissioning date on every unit
Presentation group: 8 registered MaStR units
Snapshot transition: First tracked snapshot → 5 Oct 2026
MaStR unit IDs: SEE915528647494, SEE926660470154, SEE945328682050, SEE946805941325, SEE949430444445, SEE969302871469, SEE970027004919, SEE993569694714
Commercial signals (8): cmuvj7xi80y2uwtd4bfcmngp8, cmuvj7xi90y3iwtd4ntcq4lsz, cmuvj7xib0y4qwtd4wiwqfvhz, cmuvj7xib0y4vwtd4h09cf2jl, cmuvj7xic0y53wtd4sm4yausv, cmuvj7xie0y6lwtd4g8vwte8a, cmuvj7xie0y6pwtd45tfcdgh4, cmuvj7xih0y8owtd4pbwnjfb4

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“klinkow…”); Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
New planned asset
70Lead relevance · High

Why this ranks high. Mid-sized 22.8 MW signal, 3 registrations moving together, freshly registered planned asset and the registered operator is known. External corroboration is only partial.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance70

  • Project scale (MW)15
  • Event type20
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Multi-unit evidence5
  • External verification2

Signal materiality40

  • Event type20
  • MW affected12
  • Units affected8

New planned hydro development signal — 3 units / 22.8 MW

Forbach, Baden-Württemberg · Operator: EnBW Energie Baden-Württemberg AG

3 planned units · 22.8 MW · First observed 03 Nov 2026

Hydro

Planned commissioning: 31 Dec 2027

3 new planned hydro units totalling 22.8 MW were first observed in this MaStR snapshot.

A multi-unit planned development of this scale may represent an early commercial signal worth investigating.

  • MaStR evidence: HIGH
  • Partially corroborated externally · 6 independent sources

Project corroboration does not establish procurement activity.

External evidence predates registry detection; newly observed does not necessarily mean a new project.

Developer servicesGrid connectionElectrical BOPCivil / BOPEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
3
Total registered capacity
22.8 MW
Capacity per unit
3.1–13 MW per unit
First observed in MaStR snapshot
03 Nov 2026
Planned commissioning
31 Dec 2027
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
External evidence details

External verification: Partially corroborated

Some external sources mention a energy development in Forbach associated with EnBW Energie Baden-Württemberg AG, but the match to the registered project is incomplete. Public project evidence found as early as 16 May 2023; GridGraph first observed the MaStR registration on 3 Nov 2026. No public procurement evidence was found in this verification run.

Project company
EnBW Energie Baden-Württemberg AG
Developer
EnBW Energie Baden-Württemberg AG
Project evidence
Partial
Commercial evidence
None found

No public procurement evidence was found in this verification run.

6 independent external sources.

Registry lead relevance: 68 → After external verification: 70 (+2) +2: identity or project only partially corroborated.

Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Partially corroborated — 6 independent external sources at medium confidence or better. External evidence is additional context and never replaces or downgrades the MaStR record; project corroboration is not evidence of procurement or buyer intent.
Grouping: Likely site group — Shared unit-name pattern (“psw forbach murgwerk m…”); Same planned/commissioning date on every unit
Presentation group: 3 registered MaStR units
Snapshot transition: First tracked snapshot → 3 Nov 2026
MaStR unit IDs: SEE951236468785, SEE957613817085, SEE985152689177
Commercial signals (3): cmw0azqhm13g3wtvokw2rh9f0, cmw0azqhm13gawtvo6ze9au3u, cmw0azqho13hbwtvorg94vz7q

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“psw forbach murgwerk m…”); Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
New planned asset
70Lead relevance · High

Why this ranks high. Mid-sized 14 MW signal, freshly registered planned asset, the registered operator is known and external evidence identifies the project company and corroborates the development, increasing actionability.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance70

  • Project scale (MW)13
  • Event type20
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Multi-unit evidence3
  • External verification6

Signal materiality34

  • Event type20
  • MW affected9
  • Units affected5

New planned wind development signal — 2 units / 14 MW

Beiersdorf-Freudenberg, Brandenburg · Operator: Green Wind Energy GmbH

2 planned units · 14 MW · First observed 03 Nov 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 03 Apr 2028

2 new planned wind units totalling 14 MW were first observed in this MaStR snapshot.

A newly registered planned asset may be an early sign of a development worth a quick look.

  • MaStR evidence: HIGH
  • Externally corroborated · 2 independent sources

Project corroboration does not establish procurement activity.

External evidence predates registry detection; newly observed does not necessarily mean a new project.

Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
2
Total registered capacity
14 MW
Capacity per unit
7 MW each
First observed in MaStR snapshot
03 Nov 2026
Planned commissioning
03 Apr 2028
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
External evidence details

External verification: Corroborated

External sources corroborate a planned wind development in Beiersdorf-Freudenberg associated with Green Wind Energy GmbH. A public source also matches the registered project scale. At least one source refers to planning or permitting. Public project evidence found as early as 7 Dec 2023; GridGraph first observed the MaStR registration on 3 Nov 2026. No public procurement evidence was found in this verification run.

Project company
Green Wind Energy GmbH
Developer
Green Wind Energy GmbH
Project evidence
Strong
Commercial evidence
None found

No public procurement evidence was found in this verification run.

2 independent external sources.

Registry lead relevance: 64 → After external verification: 70 (+6) +6: project corroborated and developer / project company identified by an external source.

Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Corroborated — 2 independent external sources at medium confidence or better. External evidence is additional context and never replaces or downgrades the MaStR record; project corroboration is not evidence of procurement or buyer intent.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: First tracked snapshot → 3 Nov 2026
MaStR unit IDs: SEE921774930907, SEE973118983582
Commercial signals (2): cmw0azqhk13fawtvo2h8caztf, cmw0azqhn13gwwtvok8q4f3lk

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Multiple changes
58Lead relevance · Moderate

Why this ranks here. Capacity and schedule changes recorded together on the same units and the registered operator is known. It affects only one 4.4 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance58

  • Project scale (MW)7
  • Event type14
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Several changes together5
  • Size of change4

Signal materiality46

  • Event type18
  • Size of change16
  • MW affected6
  • Several changes together6

Multiple registry changes (capacity + schedule) — 4.4 MW

Datteln, Nordrhein-Westfalen · Operator: Windkraft Datteln GmbH & Co. KG

1 unit · 4.4 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: May 2027 → Dec 2026 (-124 days)

Registered capacity changed from 5.56 MW to 4.4 MW (-1.16 MW, -21%). The registered planned commissioning date moved by -124 days (May 2027 → Dec 2026).

Several registry changes were recorded together on the same units. That may indicate a substantive update to the project rather than a routine correction, and is worth investigating.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Design / technologyGrid connectionEngineeringEquipment sizingProject schedulingConstruction timing
Design change?Permit & grid documentsDeveloper updatesRegistry correction?
Facts, hypotheses and how to verify
Registered capacity
5.56 MW → 4.4 MW (-1.16 MW / -21%)
Planned commissioning
May 2027 → Dec 2026 (-124 days)
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Check whether the change reflects a design or turbine-model change
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Compare with permit and grid-connection documents
  • Check permitting and construction status
  • Look for recent developer announcements
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE995342838797
Commercial signals (2): cmw0azqhp13huwtvoy9wu1o5m, cmw0azqhp13hvwtvox1gcnu8n

Grouping basisSingle unit
A single MaStR registration.
Capacity change
52Lead relevance · Moderate

Why this ranks here. The registered operator is known. It affects only one 6 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance52

  • Project scale (MW)8
  • Event type14
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Size of change2

Signal materiality34

  • Event type18
  • Size of change9
  • MW affected7

Registered wind capacity reduced (-1 MW) — 6 MW

Arnsberg, Nordrhein-Westfalen · Operator: VERBUND Green Power Deutschland GmbH

1 unit · 6 MW

Wind · Wind turbine (horizontal-axis)

Registered capacity changed from 7 MW to 6 MW (-1 MW, -14%).

A smaller registered capacity may indicate a scaled-back or redesigned project, which could change the scope of engineering and equipment requirements.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Design / technologyGrid connectionEngineeringEquipment sizing
Design change?Permit & grid documentsDeveloper updates
Facts, hypotheses and how to verify
Registered capacity
7 MW → 6 MW (-1 MW / -14%)
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Check whether the change reflects a design or turbine-model change
  • Compare with permit and grid-connection documents
  • Look for recent developer announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE910489791477
Commercial signals (1): cmw0azqhk13eswtvon96q9gjk

Grouping basisSingle unit
A single MaStR registration.
↑ Back to top

Receive a filtered weekly brief for your market

Tell us which Bundesländer and technologies you care about and we'll follow up with a weekly brief scoped to that — not the full report.

Relevant Bundesländer (optional)
Relevant technologies (optional)

We'll only use this to follow up with a filtered weekly brief for your market. Read how your data is stored and how to withdraw at any time in our Privacy Policy.

New developments (5)

New planned asset
65Lead relevance · High

Why this ranks high. Mid-sized 28.8 MW signal, 4 registrations moving together and freshly registered planned asset. Operator identity is unresolved, which reduces immediate actionability.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance65

  • Project scale (MW)17
  • Event type20
  • Lifecycle stage10
  • Recency8
  • Operator identified4
  • Multi-unit evidence6

Signal materiality43

  • Event type20
  • MW affected13
  • Units affected10

New planned wind development signal — 4 units / 28.8 MW

Beverungen, Nordrhein-Westfalen · Operator: Registered operator name not resolved

4 planned units · 28.8 MW · First observed 03 Nov 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 31 Oct 2028

4 new planned wind units totalling 28.8 MW were first observed in this MaStR snapshot.

A multi-unit planned development of this scale may represent an early commercial signal worth investigating.

  • MaStR evidence: HIGH
  • Search or evidence retrieval incomplete
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
4
Total registered capacity
28.8 MW
Capacity per unit
7.2 MW each
First observed in MaStR snapshot
03 Nov 2026
Planned commissioning
31 Oct 2028
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
External evidence details

External verification: Search or evidence retrieval incomplete

External search or evidence retrieval could not be completed. This opportunity needs another verification attempt.

Project company
Not resolved
Developer
Not identified
Project evidence
None
Commercial evidence
None found
  • - 1 - Stellungnahme Stadt Beverungen zur 2. Änderung des ...Municipal planning document · landesplanung.nrw.de · Published 22 Jun 2023 · low confidenceSupports: locationVerified from PDF text · page 3“• Stellungnahme der Stadt Beverungen zur 2. Änderung des LEP NRW • Ratsbeschluss vom 22.06.2023 • - 3 - Auf dem Gebiet der Stadt Beverungen sind bereits jetzt 37 Anlagen mit einer Leistung von 52,6 MW installiert. Das entspricht 21,02 % der Anlagen und 19,75 % der Leistung der Anlagen im Kreis Höxter mit seinen 10 Kommunen. Auch der aktue …”Older source: weighed lower unless it clearly describes the same ongoing project.
  • FREIFLÄCHEN-PHOTOVOLTAIKANLAGE AM ...Municipal planning document · beverungen.de · Published 25 Sept 2025 · low confidenceSupports: locationVerified from PDF text · page 9“FF-PVA am Twerberg 57. Änderung des Flächennutzungsplans der Stadt Beverungen Begründung mit Umweltbericht – Offenlegungsexemplar Stand: 24.09.2025 4 mit PV-Modulen bestückt (vgl. 5.2). Diese werden somit nur auf der östlichen Teilfläche A16 installiert. Die Teilflächen A26 und A3 werden komplett beplant (vgl. BIOPLAN 2025). Die Erweiteru …”
  • Aktuelle Verfahren (FNP und BP) – Stadt BeverungenMunicipal planning document · beverungen.de · Publication date unknown · low confidenceSupports: locationVerified from page text

No public procurement evidence was found in this verification run.

No independent external sources.

Registry lead relevance: 65 (unchanged by external verification) External search or evidence retrieval was incomplete; registry score unchanged.

Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Search or evidence retrieval incomplete — Search or evidence retrieval incomplete
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 4 registered MaStR units
Snapshot transition: First tracked snapshot → 3 Nov 2026
MaStR unit IDs: SEE909046211848, SEE948606419560, SEE968517821634, SEE988879588693
Commercial signals (4): cmw0azqhj13eowtvocj2fek9p, cmw0azqhl13fywtvohfeobgnv, cmw0azqhn13gpwtvo7i6huhq3, cmw0azqho13hkwtvo09t3k41e

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
New planned asset
63Lead relevance · High

Why this ranks high. Mid-sized 22.8 MW signal, 4 registrations moving together and freshly registered planned asset. Operator identity is unresolved, which reduces immediate actionability.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance63

  • Project scale (MW)15
  • Event type20
  • Lifecycle stage10
  • Recency8
  • Operator identified4
  • Multi-unit evidence6

Signal materiality42

  • Event type20
  • MW affected12
  • Units affected10

New planned wind development signal — 4 units / 22.8 MW

Sülstorf, Mecklenburg-Vorpommern · Operator: Registered operator name not resolved

4 planned units · 22.8 MW · First observed 03 Nov 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 30 Jun 2029

4 new planned wind units totalling 22.8 MW were first observed in this MaStR snapshot.

A multi-unit planned development of this scale may represent an early commercial signal worth investigating.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
4
Total registered capacity
22.8 MW
Capacity per unit
5.7 MW each
First observed in MaStR snapshot
03 Nov 2026
Planned commissioning
30 Jun 2029
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 4 registered MaStR units
Snapshot transition: First tracked snapshot → 3 Nov 2026
MaStR unit IDs: SEE951248041594, SEE966278206837, SEE987891215952, SEE991548759584
Commercial signals (4): cmw0azqhm13g4wtvo51vxz83v, cmw0azqhn13gnwtvoa71jnpky, cmw0azqho13hgwtvoqm5yimtr, cmw0azqho13hnwtvo734i8rfe

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
New planned asset
52Lead relevance · Moderate

Why this ranks here. Freshly registered planned asset and the registered operator is known. It affects only one 1.56 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance52

  • Project scale (MW)4
  • Event type20
  • Lifecycle stage10
  • Recency8
  • Operator identified10

Signal materiality24

  • Event type20
  • MW affected4

New planned biomass unit — 1.56 MW

Eichendorf, Bayern · Operator: SIS Bioenergie GbR

1 planned unit · 1.56 MW · First observed 03 Nov 2026

Biomass · Verbrennungsmotor

Planned commissioning: 09 Nov 2026

A new planned biomass unit of 1.56 MW was first observed in this MaStR snapshot.

A newly registered planned asset may be an early sign of a development worth a quick look.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Developer servicesGrid connectionElectrical BOPCivil / BOPEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Registered capacity
1.56 MW
First observed in MaStR snapshot
03 Nov 2026
Planned commissioning
09 Nov 2026
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: First tracked snapshot → 3 Nov 2026
MaStR unit IDs: SEE987407940736
Commercial signals (1): cmw0azqho13hewtvopcmbdu0f

Grouping basisSingle unit
A single MaStR registration.
New planned asset
51Lead relevance · Moderate

Why this ranks here. Freshly registered planned asset and the registered operator is known. It affects only one 1.19 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance51

  • Project scale (MW)3
  • Event type20
  • Lifecycle stage10
  • Recency8
  • Operator identified10

Signal materiality23

  • Event type20
  • MW affected3

New planned biomass unit — 1.19 MW

Wilhermsdorf, Bayern · Operator: Niederhöfer Energie GmbH & Co. KG

1 planned unit · 1.19 MW · First observed 03 Nov 2026

Biomass · Verbrennungsmotor

Planned commissioning: 15 Dec 2026

A new planned biomass unit of 1.19 MW was first observed in this MaStR snapshot.

A newly registered planned asset may be an early sign of a development worth a quick look.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Developer servicesGrid connectionElectrical BOPCivil / BOPEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Registered capacity
1.19 MW
First observed in MaStR snapshot
03 Nov 2026
Planned commissioning
15 Dec 2026
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: First tracked snapshot → 3 Nov 2026
MaStR unit IDs: SEE906485652430
Commercial signals (1): cmw0azqhj13emwtvo9v88br3j

Grouping basisSingle unit
A single MaStR registration.
New planned asset
50Lead relevance · Moderate

Why this ranks here. Freshly registered planned asset. Operator identity is unresolved, which reduces immediate actionability; it affects only one 5.56 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance50

  • Project scale (MW)8
  • Event type20
  • Lifecycle stage10
  • Recency8
  • Operator identified4

Signal materiality26

  • Event type20
  • MW affected6

New planned wind unit — 5.56 MW

Chemnitz, Sachsen · Operator: Registered operator name not resolved

1 planned unit · 5.56 MW · First observed 03 Nov 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 30 Jun 2028

A new planned wind unit of 5.56 MW was first observed in this MaStR snapshot.

A newly registered planned asset may be an early sign of a development worth a quick look.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Registered capacity
5.56 MW
First observed in MaStR snapshot
03 Nov 2026
Planned commissioning
30 Jun 2028
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: First tracked snapshot → 3 Nov 2026
MaStR unit IDs: SEE932920774313
Commercial signals (1): cmw0azqhl13fqwtvoiqqmsn42

Grouping basisSingle unit
A single MaStR registration.
↑ Back to top

Major schedule changes (12)

Schedule change
66Lead relevance · High

Why this ranks high. Mid-sized 18 MW signal, 4 registrations moving together, unusually large schedule shift (397 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance66

  • Project scale (MW)14
  • Event type12
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Multi-unit evidence6
  • Size of change6

Signal materiality59

  • Event type16
  • Size of change22
  • MW affected11
  • Units affected10

Commissioning delayed by up to 397 days — 4 units / 18 MW

Olsberg, Nordrhein-Westfalen · Operator: Windpark Olsberg GmbH & Co. KG

4 units · 18 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Oct 2027 → Dec 2028 (+397 days)

4 wind units registered a later planned commissioning date (+397 days).

A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
4
Planned commissioning (same for every unit)
Oct 2027 → Dec 2028 (+397 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 4 registered MaStR units
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE917426735488, SEE919438590697, SEE952886224813, SEE962305753411
Commercial signals (4): cmw0azqhk13eywtvoks2spsu0, cmw0azqhk13f2wtvomwvaq26z, cmw0azqhm13g7wtvoeattmr0k, cmw0azqhm13gjwtvon1jsmv0f

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
66Lead relevance · High

Why this ranks high. Mid-sized 27.2 MW signal, 4 registrations moving together and the registered operator is known.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance66

  • Project scale (MW)16
  • Event type12
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Multi-unit evidence6
  • Size of change4

Signal materiality55

  • Event type16
  • Size of change17
  • MW affected12
  • Units affected10

Commissioning delayed by up to 161 days — 4 units / 27.2 MW

Twistetal, Hessen · Operator: UGE Matzenhöhe GmbH & Co. KG Umweltgerechte Energie

4 units · 27.2 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 05 Oct – 03 Dec 2026

4 wind units registered a later planned commissioning date (+148 days to +161 days).

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
4
Planned commissioning before
05 Oct – 03 Dec 2026
Planned commissioning now
15 Mar – 30 Apr 2027
Shift per unit
+148 to +161 days
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“matzenhöhe…”); Identical registered capacity; Planned/commissioning dates within 46 days of each other
Presentation group: 4 registered MaStR units
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE933007843762, SEE938640213439, SEE969837388845, SEE995601388452
Commercial signals (4): cmw0azqhl13frwtvotjmhyvt2, cmw0azqhl13ftwtvoilglksiu, cmw0azqhn13gqwtvohmuz6egk, cmw0azqhp13hwwtvopzq87g4e

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“matzenhöhe…”); Identical registered capacity; Planned/commissioning dates within 46 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
64Lead relevance · High

Why this ranks high. Mid-sized 30 MW signal and the registered operator is known.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance64

  • Project scale (MW)17
  • Event type12
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Multi-unit evidence3
  • Size of change4

Signal materiality48

  • Event type16
  • Size of change14
  • MW affected13
  • Units affected5

Commissioning delayed by up to 91 days — 2 units / 30 MW

Ausschließliche Wirtschaftszone · Operator: EnBW He Dreiht GmbH & Co. KG

2 units · 30 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Oct 2026 → Dec 2026 (+91 days)

2 wind units registered a later planned commissioning date (+91 days).

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
2
Planned commissioning (same for every unit)
Oct 2026 → Dec 2026 (+91 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE983599520046, SEE998812552131
Commercial signals (2): cmw0azqho13h8wtvo12nlzeq2, cmw0azqhp13hywtvodzj4up9r

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
62Lead relevance · High

Why this ranks high. Mid-sized 14.4 MW signal, 3 registrations moving together and the registered operator is known.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance62

  • Project scale (MW)13
  • Event type12
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Multi-unit evidence5
  • Size of change4

Signal materiality48

  • Event type16
  • Size of change14
  • MW affected10
  • Units affected8

Commissioning delayed by up to 91 days — 3 units / 14.4 MW

Schnaudertal, Sachsen-Anhalt · Operator: EE Schnaudertal GmbH & Co. KG

3 units · 14.4 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 14 Oct – 30 Oct 2026

3 wind units registered a later planned commissioning date (+87 days to +91 days).

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
3
Planned commissioning before
14 Oct – 30 Oct 2026
Planned commissioning now
11 Jan – 29 Jan 2027
Shift per unit
+87 to +91 days
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Planned/commissioning dates within 18 days of each other
Presentation group: 3 registered MaStR units
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE919923544457, SEE956212762963, SEE980980753830
Commercial signals (3): cmw0azqhk13f3wtvohg2lbj32, cmw0azqhm13g8wtvo32675o0i, cmw0azqhn13h4wtvosggk5x8i

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Planned/commissioning dates within 18 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
61Lead relevance · High

Why this ranks high. Mid-sized 24.8 MW signal, 4 registrations moving together and the registered operator is known.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance61

  • Project scale (MW)16
  • Event type8
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Multi-unit evidence6
  • Size of change3

Signal materiality51

  • Event type16
  • Size of change13
  • MW affected12
  • Units affected10

Commissioning delayed by up to 77 days — 4 units / 24.8 MW

Willebadessen, Nordrhein-Westfalen · Operator: ENGIE Windpark Peckelsheim GmbH

4 units · 24.8 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 15 Oct – 01 Nov 2026

4 wind units registered a later planned commissioning date (+60 days to +77 days).

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
4
Planned commissioning before
15 Oct – 01 Nov 2026
Planned commissioning now
31 Dec 2026
Shift per unit
+60 to +77 days
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 4 registered MaStR units
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE919408612350, SEE971204353172, SEE972294789810, SEE996134566553
Commercial signals (4): cmw0azqhk13f1wtvo1t7bh9ku, cmw0azqhn13grwtvo3c8vodtk, cmw0azqhn13gvwtvomoqz7hl5, cmw0azqhp13hxwtvoug1d3mrw

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
58Lead relevance · Moderate

Why this ranks here. Mid-sized 14.4 MW signal, 4 registrations moving together and the registered operator is known. No external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance58

  • Project scale (MW)13
  • Event type8
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Multi-unit evidence6
  • Size of change3

Signal materiality49

  • Event type16
  • Size of change13
  • MW affected10
  • Units affected10

Commissioning delayed by up to 76 days — 4 units / 14.4 MW

Erftstadt, Nordrhein-Westfalen · Operator: Energiepark Erftstadt-Erp I GmbH & Co. KG

4 units · 14.4 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Oct 2026 → Dec 2026 (+76 days)

4 wind units registered a later planned commissioning date (+76 days).

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
4
Planned commissioning (same for every unit)
Oct 2026 → Dec 2026 (+76 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 4 registered MaStR units
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE907462005508, SEE916200538826, SEE917123022393, SEE921980270941
Commercial signals (4): cmw0azqhj13enwtvo00j7afuc, cmw0azqhk13ewwtvoshrfkoml, cmw0azqhk13exwtvo6eu8ui8r, cmw0azqhk13fbwtvo96mqtlrb

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
58Lead relevance · Moderate

Why this ranks here. Mid-sized 16.68 MW signal, 3 registrations moving together and the registered operator is known. No external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance58

  • Project scale (MW)14
  • Event type8
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Multi-unit evidence5
  • Size of change3

Signal materiality47

  • Event type16
  • Size of change13
  • MW affected10
  • Units affected8

Commissioning delayed by up to 78 days — 3 units / 16.68 MW

Mehring, Rheinland-Pfalz · Operator: Windpark Mehringer Höhe GmbH & Co. KG

3 units · 16.68 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 25 Sept – 05 Nov 2026

3 wind units registered a later planned commissioning date (+70 days to +78 days).

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
3
Planned commissioning before
25 Sept – 05 Nov 2026
Planned commissioning now
04 Dec 2026 – 22 Jan 2027
Shift per unit
+70 to +78 days
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Planned/commissioning dates within 49 days of each other
Presentation group: 3 registered MaStR units
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE923892472925, SEE947496605527, SEE957483549192
Commercial signals (3): cmw0azqhl13fiwtvoe1ij1xt3, cmw0azqhl13fwwtvof94x8woy, cmw0azqhm13g9wtvobhhm5ypq

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Planned/commissioning dates within 49 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
57Lead relevance · Moderate

Why this ranks here. Mid-sized 16.68 MW signal, 3 registrations moving together and the registered operator is known. No external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance57

  • Project scale (MW)14
  • Event type8
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Multi-unit evidence5
  • Size of change2

Signal materiality42

  • Event type16
  • Size of change8
  • MW affected10
  • Units affected8

Commissioning delayed by up to 31 days — 3 units / 16.68 MW

Wittgert, Rheinland-Pfalz · Operator: Windpark Haiderbachhöhe GmbH & Co. KG

3 units · 16.68 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 14 Oct 2026 → 14 Nov 2026 (+31 days)

3 wind units registered a later planned commissioning date (+31 days).

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
3
Planned commissioning (same for every unit)
14 Oct 2026 → 14 Nov 2026 (+31 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 3 registered MaStR units
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE920422933673, SEE984272177441, SEE986742691730
Commercial signals (3): cmw0azqhk13f7wtvo8y7nd3bu, cmw0azqho13hawtvo593qmm4r, cmw0azqho13hcwtvoti8xi7jh

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
56Lead relevance · Moderate

Why this ranks here. 3 registrations moving together and the registered operator is known. Small combined capacity (12.78 MW); no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance56

  • Project scale (MW)12
  • Event type8
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Multi-unit evidence5
  • Size of change3

Signal materiality45

  • Event type16
  • Size of change12
  • MW affected9
  • Units affected8

Commissioning delayed by up to 61 days — 3 units / 12.78 MW

Hasenmoor, Schleswig-Holstein · Operator: Windpark GmbH & Co. Hasenmoor KG

3 units · 12.78 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Oct 2026 → Dec 2026 (+61 days)

3 wind units registered a later planned commissioning date (+61 days).

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
3
Planned commissioning (same for every unit)
Oct 2026 → Dec 2026 (+61 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“hasenmoor e wea…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 3 registered MaStR units
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE920016952578, SEE950764073393, SEE976443544732
Commercial signals (3): cmw0azqhk13f5wtvoudyipcvn, cmw0azqhm13g2wtvo2sfvcer6, cmw0azqhn13gzwtvou0mmov2n

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“hasenmoor e wea…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
56Lead relevance · Moderate

Why this ranks here. 3 registrations moving together and the registered operator is known. Small combined capacity (12.78 MW); no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance56

  • Project scale (MW)12
  • Event type8
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Multi-unit evidence5
  • Size of change3

Signal materiality45

  • Event type16
  • Size of change12
  • MW affected9
  • Units affected8

Commissioning delayed by up to 61 days — 3 units / 12.78 MW

Struvenhütten, Schleswig-Holstein · Operator: Windpark GmbH & Co. Hasenmoor KG

3 units · 12.78 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Oct 2026 → Dec 2026 (+61 days)

3 wind units registered a later planned commissioning date (+61 days).

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
3
Planned commissioning (same for every unit)
Oct 2026 → Dec 2026 (+61 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“struvenhütten e wea…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 3 registered MaStR units
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE929232817296, SEE952115711718, SEE958398584360
Commercial signals (3): cmw0azqhl13fmwtvoauh6yttf, cmw0azqhm13g5wtvo8jjmr3uz, cmw0azqhm13gewtvo98nuzy6d

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“struvenhütten e wea…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
55Lead relevance · Moderate

Why this ranks here. Unusually large schedule shift (365 days) and the registered operator is known. It affects only one 7.2 MW unit; it may still reflect a registry correction rather than a new commercial need; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance55

  • Project scale (MW)9
  • Event type12
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Size of change6

Signal materiality45

  • Event type16
  • Size of change22
  • MW affected7

Commissioning delayed by 365 days — 7.2 MW

Melbeck, Niedersachsen · Operator: Bürgerwindpark Häcklingen-Melbeck Betriebsgesellschaft mbH & Co. KG

1 unit · 7.2 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Oct 2026 → Oct 2027 (+365 days)

The registered planned commissioning date moved by +365 days (Oct 2026 → Oct 2027).

A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Planned commissioning
Oct 2026 → Oct 2027 (+365 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE987670223895
Commercial signals (1): cmw0azqho13hfwtvoyzuypdcj

Grouping basisSingle unit
A single MaStR registration.
Schedule change
55Lead relevance · Moderate

Why this ranks here. Unusually large schedule shift (391 days) and the registered operator is known. It affects only one 6.8 MW unit; it may still reflect a registry correction rather than a new commercial need; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance55

  • Project scale (MW)9
  • Event type12
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Size of change6

Signal materiality45

  • Event type16
  • Size of change22
  • MW affected7

Commissioning delayed by 391 days — 6.8 MW

Brakel, Nordrhein-Westfalen · Operator: Windpark Möncheberg GmbH & Co. KG

1 unit · 6.8 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Jun 2027 → Jul 2028 (+391 days)

The registered planned commissioning date moved by +391 days (Jun 2027 → Jul 2028).

A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Planned commissioning
Jun 2027 → Jul 2028 (+391 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE978362246452
Commercial signals (1): cmw0azqhn13h3wtvoa9rdzk7h

Grouping basisSingle unit
A single MaStR registration.
↑ Back to top

Operator / company changes (6)

Operator change
51Lead relevance · Moderate

Why this ranks here. Mid-sized 13.6 MW signal. Operator identity is unresolved, which reduces immediate actionability; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance51

  • Project scale (MW)13
  • Event type13
  • Lifecycle stage10
  • Recency8
  • Operator identified4
  • Multi-unit evidence3

Signal materiality28

  • Event type14
  • MW affected9
  • Units affected5

Registered operator changed on 2 wind units — 2 units / 13.6 MW

Groß Luckow, Mecklenburg-Vorpommern · Operator: Registered operator name not resolved

2 units · 13.6 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 2 wind units.

A registered operator change can be a useful trigger for investigating ownership, project restructuring, or a change in the commercial entity responsible for the asset. It does not by itself establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Units with an operator change
2
Previous registered operator
MBBF Windparkplanung GmbH & Co. KG
New registered operator
Operator ID ABR906673744367 (name not resolved)
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE904979333124, SEE935968965712
Commercial signals (2): cmw0azqhj13ejwtvo9ezza60p, cmw0azqhl13fswtvo481rxqtg

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Operator change
50Lead relevance · Moderate

Why this ranks here. Operator identity is unresolved, which reduces immediate actionability; small combined capacity (12 MW); no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance50

  • Project scale (MW)12
  • Event type13
  • Lifecycle stage10
  • Recency8
  • Operator identified4
  • Multi-unit evidence3

Signal materiality28

  • Event type14
  • MW affected9
  • Units affected5

Registered operator changed on 2 wind units — 2 units / 12 MW

Bedburg-Hau, Nordrhein-Westfalen · Operator: Registered operator name not resolved

2 units · 12 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 2 wind units.

A registered operator change can be a useful trigger for investigating ownership, project restructuring, or a change in the commercial entity responsible for the asset. It does not by itself establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Units with an operator change
2
Previous registered operator
Operator ID ABR990346269721 (name not resolved)
New registered operator
Operator ID ABR963641870411 (name not resolved)
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE987101740212, SEE988846851591
Commercial signals (2): cmw0azqho13hdwtvomahshmjn, cmw0azqho13hjwtvo64wbcqbg

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Operator change
50Lead relevance · Moderate

Why this ranks here. Operator identity is unresolved, which reduces immediate actionability; small combined capacity (12 MW); no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance50

  • Project scale (MW)12
  • Event type13
  • Lifecycle stage10
  • Recency8
  • Operator identified4
  • Multi-unit evidence3

Signal materiality28

  • Event type14
  • MW affected9
  • Units affected5

Registered operator changed on 2 wind units — 2 units / 12 MW

Uckerland, Brandenburg · Operator: Registered operator name not resolved

2 units · 12 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 2 wind units.

A registered operator change can be a useful trigger for investigating ownership, project restructuring, or a change in the commercial entity responsible for the asset. It does not by itself establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Units with an operator change
2
Previous registered operator
TANDEM Investitions- und Beteiligungsgesellschaft für ökologische Projekte mbH
New registered operator
Operator ID ABR920848847097 (name not resolved)
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“wea rep…”); Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE923079053701, SEE949169917340
Commercial signals (2): cmw0azqhl13ffwtvo2iidggld, cmw0azqhl13fzwtvo02epgwaa

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“wea rep…”); Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Operator change
49Lead relevance · Moderate

Why this ranks here. The registered operator is known. It affects only one 5.7 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance49

  • Project scale (MW)8
  • Event type13
  • Lifecycle stage10
  • Recency8
  • Operator identified10

Signal materiality21

  • Event type14
  • MW affected7

Registered operator changed on a wind unit — 5.7 MW

Grevenbroich, Nordrhein-Westfalen · Operator: InfraStruktur Neuss AöR

1 unit · 5.7 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 1 wind unit.

A registered operator change can be a useful trigger for investigating ownership, project restructuring, or a change in the commercial entity responsible for the asset. It does not by itself establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Previous registered operator
Energiekontor AG
New registered operator
InfraStruktur Neuss AöR
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE958247358050
Commercial signals (1): cmw0azqhm13gbwtvolcj6p7kw

Grouping basisSingle unit
A single MaStR registration.
Operator change
49Lead relevance · Moderate

Why this ranks here. The registered operator is known. It affects only one 5.56 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance49

  • Project scale (MW)8
  • Event type13
  • Lifecycle stage10
  • Recency8
  • Operator identified10

Signal materiality20

  • Event type14
  • MW affected6

Registered operator changed on a wind unit — 5.56 MW

Kall, Nordrhein-Westfalen · Operator: GLS Windpark Schleiden GmbH & Co. KG Betriebsgesellschaft

1 unit · 5.56 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 1 wind unit.

A registered operator change can be a useful trigger for investigating ownership, project restructuring, or a change in the commercial entity responsible for the asset. It does not by itself establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Previous registered operator
SK Wind GmbH & Co. KG
New registered operator
GLS Windpark Schleiden GmbH & Co. KG Betriebsgesellschaft
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE988219460757
Commercial signals (1): cmw0azqho13hhwtvov7b5tfct

Grouping basisSingle unit
A single MaStR registration.
Operator change
44Lead relevance · Low

Why this ranks here. Operator identity is unresolved, which reduces immediate actionability; it affects only one 7 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance44

  • Project scale (MW)9
  • Event type13
  • Lifecycle stage10
  • Recency8
  • Operator identified4

Signal materiality21

  • Event type14
  • MW affected7

Registered operator changed on a wind unit — 7 MW

Wettlingen, Rheinland-Pfalz · Operator: Registered operator name not resolved

1 unit · 7 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 1 wind unit.

A registered operator change can be a useful trigger for investigating ownership, project restructuring, or a change in the commercial entity responsible for the asset. It does not by itself establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Previous registered operator
Windenergie Bitburg-Land Planungsgesellschaft mbH
New registered operator
Operator ID ABR996931774120 (name not resolved)
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE976882969189
Commercial signals (1): cmw0azqhn13h1wtvo5xrs4e15

Grouping basisSingle unit
A single MaStR registration.
↑ Back to top

Recently commissioned assets (12)

Commissioned asset
43Lead relevance · Low

Why this ranks here. Mid-sized 13.6 MW signal and the registered operator is known. Already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance43

  • Project scale (MW)13
  • Event type6
  • Lifecycle stage3
  • Recency8
  • Operator identified10
  • Multi-unit evidence3

Signal materiality26

  • Event type12
  • MW affected9
  • Units affected5

2 wind units commissioned — 2 units / 13.6 MW

Bördeland, Sachsen-Anhalt · Operator: Windpark Biere GmbH & Co. KG

2 units · 13.6 MW

Wind · Wind turbine (horizontal-axis)

2 wind units (13.6 MW) moved from planned to commissioned status in MaStR, with registered commissioning dates between 28 Oct – 29 Oct 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Units commissioned
2
Total registered capacity
13.6 MW
Commissioned between
28 Oct – 29 Oct 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“bie r…”); Identical registered capacity; Planned/commissioning dates within 1 days of each other
Presentation group: 2 registered MaStR units
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE904542985941, SEE959774797350
Commercial signals (2): cmw0azqhj13egwtvorndp538t, cmw0azqhm13gfwtvo109l144i

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“bie r…”); Identical registered capacity; Planned/commissioning dates within 1 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Commissioned asset
42Lead relevance · Low

Why this ranks here. The registered operator is known. Small combined capacity (12.4 MW); already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance42

  • Project scale (MW)12
  • Event type6
  • Lifecycle stage3
  • Recency8
  • Operator identified10
  • Multi-unit evidence3

Signal materiality26

  • Event type12
  • MW affected9
  • Units affected5

2 wind units commissioned — 2 units / 12.4 MW

Günstedt, Thüringen · Operator: meridian Windpark Günstedt GmbH & Co.KG

2 units · 12.4 MW

Wind · Wind turbine (horizontal-axis)

2 wind units (12.4 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 28 Oct 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Units commissioned
2
Total registered capacity
12.4 MW
Commissioning date
28 Oct 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE909768416286, SEE919323670619
Commercial signals (2): cmw0azqhk13eqwtvobl7iqmnt, cmw0azqhk13f0wtvoigl74lz8

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Commissioned asset
40Lead relevance · Low

Why this ranks here. The registered operator is known. Small combined capacity (8.2 MW); already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance40

  • Project scale (MW)10
  • Event type6
  • Lifecycle stage3
  • Recency8
  • Operator identified10
  • Multi-unit evidence3

Signal materiality24

  • Event type12
  • MW affected7
  • Units affected5

2 wind units commissioned — 2 units / 8.2 MW

Uelvesbüll, Schleswig-Holstein · Operator: Windpark Barneckemoor GmbH & Co.KG

2 units · 8.2 MW

Wind · Wind turbine (horizontal-axis)

2 wind units (8.2 MW) moved from planned to commissioned status in MaStR, with registered commissioning dates between 15 Oct – 29 Oct 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Units commissioned
2
Total registered capacity
8.2 MW
Commissioned between
15 Oct – 29 Oct 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“vensys…”); Identical registered capacity; Planned/commissioning dates within 14 days of each other
Presentation group: 2 registered MaStR units
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE949406884497, SEE964322441661
Commercial signals (2): cmw0azqhm13g1wtvov83g7dqg, cmw0azqhn13glwtvotnr0x1w0

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“vensys…”); Identical registered capacity; Planned/commissioning dates within 14 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Commissioned asset
40Lead relevance · Low

Why this ranks here. Mid-sized 15 MW signal and the registered operator is known. Only one registered unit; already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance40

  • Project scale (MW)13
  • Event type6
  • Lifecycle stage3
  • Recency8
  • Operator identified10

Signal materiality22

  • Event type12
  • MW affected10

Wind unit commissioned — 15 MW — MaStR SEE994982674826

Ausschließliche Wirtschaftszone · Operator: Nordseecluster A GmbH & Co. KG

1 unit · 15 MW

Wind · Wind turbine (horizontal-axis)

1 wind unit (15 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 16 Oct 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Registered capacity
15 MW
Commissioning date
16 Oct 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE994982674826
Commercial signals (1): cmw0azqhp13htwtvo9ee9lw68

Grouping basisSingle unit
Stable MaStR location ID: SEL909010631399
A single MaStR registration.
Commissioned asset
40Lead relevance · Low

Why this ranks here. Mid-sized 15 MW signal and the registered operator is known. Only one registered unit; already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance40

  • Project scale (MW)13
  • Event type6
  • Lifecycle stage3
  • Recency8
  • Operator identified10

Signal materiality22

  • Event type12
  • MW affected10

Wind unit commissioned — 15 MW — MaStR SEE926317316675

Ausschließliche Wirtschaftszone · Operator: EnBW He Dreiht GmbH & Co. KG

1 unit · 15 MW

Wind · Wind turbine (horizontal-axis)

1 wind unit (15 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 22 Oct 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Registered capacity
15 MW
Commissioning date
22 Oct 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE926317316675
Commercial signals (1): cmw0azqhl13flwtvo94x9chqy

Grouping basisSingle unit
Stable MaStR location ID: SEL969640524546
A single MaStR registration.
Commissioned asset
36Lead relevance · Low

Why this ranks here. The registered operator is known. It affects only one 7.2 MW unit; already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance36

  • Project scale (MW)9
  • Event type6
  • Lifecycle stage3
  • Recency8
  • Operator identified10

Signal materiality19

  • Event type12
  • MW affected7

Wind unit commissioned — 7.2 MW

Borken, Nordrhein-Westfalen · Operator: Windenergie Hee GmbH & Co. KG

1 unit · 7.2 MW

Wind · Wind turbine (horizontal-axis)

1 wind unit (7.2 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 30 Oct 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Registered capacity
7.2 MW
Commissioning date
30 Oct 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE931482209714
Commercial signals (1): cmw0azqhl13fowtvodsvwwl6c

Grouping basisSingle unit
Stable MaStR location ID: SEL932665852529
A single MaStR registration.
Commissioned asset
36Lead relevance · Low

Why this ranks here. The registered operator is known. It affects only one 7.2 MW unit; already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance36

  • Project scale (MW)9
  • Event type6
  • Lifecycle stage3
  • Recency8
  • Operator identified10

Signal materiality19

  • Event type12
  • MW affected7

Wind unit commissioned — 7.2 MW

Sengenthal, Bayern · Operator: Max Bögl Stiftung & Co. KG Max Bögl Stiftung & Co. KG

1 unit · 7.2 MW

Wind · Wind turbine (horizontal-axis)

1 wind unit (7.2 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 29 Oct 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Registered capacity
7.2 MW
Commissioning date
29 Oct 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE983901061946
Commercial signals (1): cmw0azqho13h9wtvoc8ly6qr2

Grouping basisSingle unit
Stable MaStR location ID: SEL950899397555
A single MaStR registration.
Commissioned asset
36Lead relevance · Low

Why this ranks here. The registered operator is known. It affects only one 7 MW unit; already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance36

  • Project scale (MW)9
  • Event type6
  • Lifecycle stage3
  • Recency8
  • Operator identified10

Signal materiality19

  • Event type12
  • MW affected7

Wind unit commissioned — 7 MW

Bad Wünnenberg, Nordrhein-Westfalen · Operator: SE-Wind GmbH & Co. KG

1 unit · 7 MW

Wind · Wind turbine (horizontal-axis)

1 wind unit (7 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 20 Oct 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Registered capacity
7 MW
Commissioning date
20 Oct 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE971349645606
Commercial signals (1): cmw0azqhn13gswtvoxiwah7gn

Grouping basisSingle unit
Stable MaStR location ID: SEL905106178526
A single MaStR registration.
Commissioned asset
36Lead relevance · Low

Why this ranks here. The registered operator is known. It affects only one 6.8 MW unit; already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance36

  • Project scale (MW)9
  • Event type6
  • Lifecycle stage3
  • Recency8
  • Operator identified10

Signal materiality19

  • Event type12
  • MW affected7

Wind unit commissioned — 6.8 MW

Marienmünster, Nordrhein-Westfalen · Operator: Bürgerwind Marienmünster II GmbH & Co. KG

1 unit · 6.8 MW

Wind · Wind turbine (horizontal-axis)

1 wind unit (6.8 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 29 Oct 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Registered capacity
6.8 MW
Commissioning date
29 Oct 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE923394966250
Commercial signals (1): cmw0azqhl13fhwtvogvv264ht

Grouping basisSingle unit
Stable MaStR location ID: SEL927201531655
A single MaStR registration.
Commissioned asset
36Lead relevance · Low

Why this ranks here. The registered operator is known. It affects only one 6.8 MW unit; already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance36

  • Project scale (MW)9
  • Event type6
  • Lifecycle stage3
  • Recency8
  • Operator identified10

Signal materiality19

  • Event type12
  • MW affected7

Wind unit commissioned — 6.8 MW

Bad Wünnenberg, Nordrhein-Westfalen · Operator: Heide-Wind GmbH& Co. KG

1 unit · 6.8 MW

Wind · Wind turbine (horizontal-axis)

1 wind unit (6.8 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 21 Oct 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Registered capacity
6.8 MW
Commissioning date
21 Oct 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE904938620418
Commercial signals (1): cmw0azqhj13eiwtvou0nk4jxa

Grouping basisSingle unit
Stable MaStR location ID: SEL945912364478
A single MaStR registration.
Commissioned asset
35Lead relevance · Low

Why this ranks here. The registered operator is known. It affects only one 6.2 MW unit; already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance35

  • Project scale (MW)8
  • Event type6
  • Lifecycle stage3
  • Recency8
  • Operator identified10

Signal materiality19

  • Event type12
  • MW affected7

Wind unit commissioned — 6.2 MW

Groitzsch, Sachsen · Operator: Windpark Breunsdorf I GmbH

1 unit · 6.2 MW

Wind · Wind turbine (horizontal-axis)

1 wind unit (6.2 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 22 Oct 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Registered capacity
6.2 MW
Commissioning date
22 Oct 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE991782946146
Commercial signals (1): cmw0azqho13howtvogih1gu31

Grouping basisSingle unit
Stable MaStR location ID: SEL923437877857
A single MaStR registration.
Commissioned asset
35Lead relevance · Low

Why this ranks here. The registered operator is known. It affects only one 6.2 MW unit; already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance35

  • Project scale (MW)8
  • Event type6
  • Lifecycle stage3
  • Recency8
  • Operator identified10

Signal materiality19

  • Event type12
  • MW affected7

Wind unit commissioned — 6.2 MW

Rastede, Niedersachsen · Operator: BGK GmbH & Co. KG

1 unit · 6.2 MW

Wind · Wind turbine (horizontal-axis)

1 wind unit (6.2 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 29 Oct 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Registered capacity
6.2 MW
Commissioning date
29 Oct 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE905455264093
Commercial signals (1): cmw0azqhj13ekwtvohlypraui

Grouping basisSingle unit
Stable MaStR location ID: SEL929863943296
A single MaStR registration.
↑ Back to top

Other registry changes (1)

Smaller registry changes, listed for completeness.

Schedule change
42Lead relevance · Low

Why this ranks here. The registered operator is known. Small combined capacity (3.12 MW); short date shifts are common registry maintenance; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance42

  • Project scale (MW)6
  • Event type4
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Multi-unit evidence3
  • Size of change1

Signal materiality31

  • Event type16
  • Size of change5
  • MW affected5
  • Units affected5

Commissioning delayed by up to 17 days — 2 units / 3.12 MW

Lauchringen, Baden-Württemberg · Operator: Schwab Energie GmbH

2 units · 3.12 MW

Biomass · Verbrennungsmotor

Planned commissioning: 15 Oct 2026 → 01 Nov 2026 (+17 days)

2 biomass units registered a later planned commissioning date (+17 days).

A short date shift is common and may be routine registry maintenance. Worth attention mainly if it is part of a wider pattern.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
2
Planned commissioning (same for every unit)
15 Oct 2026 → 01 Nov 2026 (+17 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“schwab energie gmbh satellit bhkw…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: 28 Oct 2026 → 3 Nov 2026
MaStR unit IDs: SEE921553748501, SEE977055597413
Commercial signals (2): cmw0azqhk13f9wtvohgv9w160, cmw0azqhn13h2wtvoe8yliwwt

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“schwab energie gmbh satellit bhkw…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
↑ Back to top

Receive a filtered weekly brief for your market

Tell us which Bundesländer and technologies you care about and we'll follow up with a weekly brief scoped to that — not the full report.

Relevant Bundesländer (optional)
Relevant technologies (optional)

We'll only use this to follow up with a filtered weekly brief for your market. Read how your data is stored and how to withdraw at any time in our Privacy Policy.