Commissioning delayed by 391 days — 6.8 MW
Brakel, Nordrhein-Westfalen · Operator: Windpark Möncheberg GmbH & Co. KG
1 unit · 6.8 MW
- MaStR evidence: HIGH
- Registry only · external search not performed
What changed
The registered planned commissioning date moved by +391 days (Jun 2027 → Jul 2028).
Why this ranks here. Unusually large schedule shift (391 days) and the registered operator is known. It affects only one 6.8 MW unit; it may still reflect a registry correction rather than a new commercial need; no external evidence yet.
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Project development or development-management services
- Engineering and environmental services
Verify next
- Verify whether the date change reflects real rescheduling or a registry correction
- Check permitting and construction status
- Look for recent developer updates
Change summary
- Planned commissioning
- Jun 2027 → Jul 2028 (+391 days)
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (1)
SEE978362246452View official MaStR record ↗
Grouping basis
A single MaStR registration.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Planung
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.
Snapshot transition
28 Oct 2026 → 3 Nov 2026