Schedule change
66Lead relevance · High

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance66

  • Project scale (MW)14
  • Event type12
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Multi-unit evidence6
  • Size of change6

Signal materiality59

  • Event type16
  • Size of change22
  • MW affected11
  • Units affected10

Commissioning delayed by up to 397 days — 4 units / 18 MW

Olsberg, Nordrhein-Westfalen · Operator: Windpark Olsberg GmbH & Co. KG

4 units · 18 MW

Asset typeHorizontalläufer
Energy carrierWind
Registered operatorWindpark Olsberg GmbH & Co. KG

4 wind units registered a later planned commissioning date (+397 days).

Why this ranks high. Mid-sized 18 MW signal, 4 registrations moving together, unusually large schedule shift (397 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.

A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.
Developer servicesEngineeringMarket intelligence

Investigation hypotheses only. They are not evidence that any of these needs currently exist.

Units with a new planned date
4
Planned commissioning (same for every unit)
Oct 2027 → Dec 2028 (+397 days)

GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Asset type (MaStR)
Horizontalläufer
Energy carrier (MaStR)
Wind
Operating status (MaStR)
In Planung

MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.

Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.

28 Oct 2026 → 3 Nov 2026

← Back to the brief · 2026-11-03