66Lead relevance · High
Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Lead relevance66
- Project scale (MW)14
- Event type12
- Lifecycle stage10
- Recency8
- Operator identified10
- Multi-unit evidence6
- Size of change6
Signal materiality59
- Event type16
- Size of change22
- MW affected11
- Units affected10
Commissioning delayed by up to 397 days — 4 units / 18 MW
Olsberg, Nordrhein-Westfalen · Operator: Windpark Olsberg GmbH & Co. KG
4 units · 18 MW
- MaStR evidence: HIGH
- Registry only · external search not performed
What changed
4 wind units registered a later planned commissioning date (+397 days).
Why this ranks high. Mid-sized 18 MW signal, 4 registrations moving together, unusually large schedule shift (397 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Project development or development-management services
- Engineering and environmental services
Verify next
- Verify whether the date change reflects real rescheduling or a registry correction
- Check permitting and construction status
- Look for recent developer updates
Change summary
- Units with a new planned date
- 4
- Planned commissioning (same for every unit)
- Oct 2027 → Dec 2028 (+397 days)
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (4)
SEE917426735488View official MaStR record ↗SEE919438590697View official MaStR record ↗SEE952886224813View official MaStR record ↗SEE962305753411View official MaStR record ↗
Grouping basis
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Planung
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.
Snapshot transition
28 Oct 2026 → 3 Nov 2026