Schedule change
71Lead relevance · High

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance71

  • Project scale (MW)20
  • Event type12
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Multi-unit evidence7
  • Size of change4

Signal materiality57

  • Event type16
  • Size of change14
  • MW affected15
  • Units affected12

Commissioning delayed by up to 90 days — 7 units / 47.6 MW

Bronkow, Brandenburg · Operator: UGE Bronkow Nord Eins GmbH & Co. KG Umweltgereche Energie

7 units · 47.6 MW

Asset typeHorizontalläufer
Energy carrierWind
Registered operatorUGE Bronkow Nord Eins GmbH & Co. KG Umweltgereche Energie

7 wind units registered a later planned commissioning date (+53 days to +90 days).

Why this ranks high. Large 47.6 MW multi-unit signal, 7 registrations moving together and the registered operator is known.

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.
Developer servicesEngineeringMarket intelligence

Investigation hypotheses only. They are not evidence that any of these needs currently exist.

Units with a new planned date
7
Planned commissioning before
07 Oct 2026 – 03 Mar 2027
Planned commissioning now
30 Nov 2026 – 30 Apr 2027
Shift per unit
+53 to +90 days

GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“bronkow…”); Identical registered capacity
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Asset type (MaStR)
Horizontalläufer
Energy carrier (MaStR)
Wind
Operating status (MaStR)
In Planung

MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.

Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.

28 Oct 2026 → 3 Nov 2026

← Back to the brief · 2026-11-03