Selected from the highest-scoring investigation signals, with category diversification to avoid repetitive results. Cards are ordered by opportunity score; a higher-scoring signal of an already well-represented type may appear in a section below. Scores are deterministic and are not probabilities. Everything here is a starting point for verification, not evidence of demand.
Schedule change78Lead relevance · Very high
Why this ranks high. Large 91 MW multi-unit signal, 13 registrations moving together, unusually large schedule shift (518 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.
Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Lead relevance78
- Project scale (MW)23
- Event type12
- Lifecycle stage10
- Recency8
- Operator identified10
- Multi-unit evidence9
- Size of change6
Signal materiality73
- Event type16
- Size of change24
- MW affected18
- Units affected15
Commissioning delayed by up to 518 days — 13 units / 91 MW
Zerbst/Anhalt, Sachsen-Anhalt · Operator: Windpark Packendorfer Teich GmbH & Co. KG
13 units · 91 MW
Wind · Wind turbine (horizontal-axis)
Planned commissioning: Dec 2026 → Jun 2028 (+518 days)
What changed
13 wind units registered a later planned commissioning date (+518 days).
Why it may matter
A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.
Evidence
- MaStR evidence: HIGH
- Registry only · external search not performed
Possible relevance
Project schedulingEngineeringConstruction timingSupplier timing
Verify next
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
- Units with a new planned date
- 13
- Planned commissioning (same for every unit)
- Dec 2026 → Jun 2028 (+518 days)
- Project development or development-management services
- Engineering and environmental services
How to verify
- Verify whether the date change reflects real rescheduling or a registry correction
- Check permitting and construction status
- Look for recent developer updates
Evidence and source lineage
MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“paken wea…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 13 registered MaStR units
Snapshot transition: 23 Oct 2026 → 24 Oct 2026
MaStR unit IDs: SEE909646504302, SEE927898740927, SEE928440590182, SEE931230328049, SEE931320565200, SEE955774817371, SEE968796931451, SEE969527234735, SEE970308949052, SEE974463276114, SEE978092683718, SEE985046872029, SEE987879268604
Commercial signals (13): cmvm02hxv1usewtqsvc9ud2l7, cmvm02hxv1usgwtqs60kljy7c, cmvm02hxv1ushwtqsepkebnjr, cmvm02hxv1usiwtqss7vmfeqm, cmvm02hxv1usjwtqs786kd1sc, cmvm02hxw1usnwtqsg8i5lcg6, cmvm02hxw1uspwtqs9hap4pfx, cmvm02hxw1usqwtqsqm0exkkp, cmvm02hxw1usrwtqsirgaaid2, cmvm02hxw1usuwtqs82q9czzb, cmvm02hxw1usvwtqs96ax35ex, cmvm02hxw1uszwtqs737nenjf, cmvm02hxw1ut0wtqsapqvyyqh
Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“paken wea…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Underlying registrations (13)
New planned asset73Lead relevance · High
Why this ranks high. Mid-sized 23.6 MW signal, 4 registrations moving together, freshly registered planned asset and the registered operator is known. External corroboration is only partial.
Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Lead relevance73
- Project scale (MW)16
- Event type20
- Lifecycle stage10
- Recency8
- Operator identified10
- Multi-unit evidence6
- External verification3
Signal materiality42
- Event type20
- MW affected12
- Units affected10
New planned wind development signal — 4 units / 23.6 MW
Ludwigsfelde, Brandenburg · Operator: Energiequelle GmbH
4 planned units · 23.6 MW · First observed 24 Oct 2026
Wind · Wind turbine (horizontal-axis)
Planned commissioning: 30 Jun 2028
What changed
4 new planned wind units totalling 23.6 MW were first observed in this MaStR snapshot.
Why it may matter
A multi-unit planned development of this scale may represent an early commercial signal worth investigating.
Evidence
- MaStR evidence: HIGH
- Partially corroborated externally · 5 independent sources
Project corroboration does not establish procurement activity.
External evidence predates registry detection; newly observed does not necessarily mean a new project.
Possible relevance
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
Verify next
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
- Planned units first observed
- 4
- Total registered capacity
- 23.6 MW
- Capacity per unit
- 4.8–7 MW per unit
- First observed in MaStR snapshot
- 24 Oct 2026
- Planned commissioning
- 30 Jun 2028
- Project development or development-management services
- Grid-connection / interconnection and electrical infrastructure services
- Engineering and environmental services
- Civil works and balance-of-plant
- Turbine-related services (supply, transport, installation, service)
How to verify
- Identify the developer or project company
- Check planning and permitting status
- Search municipal planning documents
- Search recent company announcements
- Search tenders and procurement notices
- Verify whether construction or supplier selection has started
External evidence details
What we found
External verification: Partially corroborated
Some external sources mention a wind development in Ludwigsfelde associated with Energiequelle GmbH, but the match to the registered project is incomplete. Public project evidence found as early as 14 Feb 2024; GridGraph first observed the MaStR registration on 24 Oct 2026. Related commercial activity (for example a supplier order or tender) was found for this company or place, but it cannot yet be tied to this exact registered project.
- Project company
- Energiequelle GmbH
- Developer
- Energiequelle GmbH
- Project evidence
- Partial
- Commercial evidence
- Related activity, not pinned to this project
- News | EnergiequelleDeveloper announcement · energiequelle.com · Published 7 Oct 2026 · medium confidenceSupports: project exists, company identity, locationVerified from page text
- Wind turbine in Ludwigsfelde | EnergiequelleDeveloper announcement · energiequelle.de · Published 8 Jan 2025 · medium confidenceSupports: project exists, company identity, locationVerified from page text
- Baubeginn Ludwigsfelde | EnergiequelleDeveloper announcement · energiequelle.de · Published 14 Feb 2024 · medium confidenceSupports: project exists, company identity, location, project stageVerified from page text
- Windenergieanlage in Ludwigsfelde in Betrieb genommen | EnergiequelleDeveloper announcement · energiequelle.de · Published 8 Jan 2025 · medium confidenceSupports: project exists, company identity, location, project stageVerified from page text
- Energiequelle GmbH feiert Baubeginn in Ludwigsfelde | windmesse.deNews / press report · w3.windmesse.de · Published 14 Feb 2024 · medium confidenceSupports: project exists, company identity, location, project stage, procurement activityVerified from page text
- Windenergie | EnergiequelleDeveloper project page · energiequelle.de · Publication date unknown · low confidenceSupports: company identity, commissioning timelineJudged from search excerpt only
- Energiequelle GmbH erhält Genehmigungen für zwei Windparks in Niedersachsen und Nordrhein-WestfalenNews / press report · w3.windmesse.de · Published 31 Jan 2025 · low confidenceSupports: company identityVerified from page text
- Energiequelle GmbH beginnt mit dem Bau des Windparks Eulitz - Windbranche.deNews / press report · windbranche.de · Publication date unknown · low confidenceSupports: company identityVerified from page text
Related commercial activity (for example a supplier order or tender) was found for this company or place, but it cannot yet be tied to this exact registered project.
5 independent external sources.
Registry lead relevance: 70 → After external verification: 73 (+3) +3: identity or project only partially corroborated; +1 related commercial activity that cannot yet be pinned to this exact group.
Evidence and source lineage
MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Partially corroborated — 5 independent external sources at medium confidence or better. External evidence is additional context and never replaces or downgrades the MaStR record; project corroboration is not evidence of procurement or buyer intent.
Grouping: Likely site group — Shared unit-name pattern (“wp ludwigsfelde ortsteile…”); Same planned/commissioning date on every unit
Presentation group: 4 registered MaStR units
Snapshot transition: First tracked snapshot → 24 Oct 2026
MaStR unit IDs: SEE942520157461, SEE971930804863, SEE984347773103, SEE993395124744
Commercial signals (4): cmvm02hxv1uskwtqsrx1a54g6, cmvm02hxw1usswtqsch3spzty, cmvm02hxw1usywtqsd791x7c6, cmvm02hxw1ut1wtqsjyr0p5p7
Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“wp ludwigsfelde ortsteile…”); Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Underlying registrations (4)
New planned asset63Lead relevance · High
Why this ranks high. Mid-sized 42 MW signal and 6 registrations moving together. Operator identity is unresolved, which reduces immediate actionability; external corroboration is only partial.
Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Lead relevance63
- Project scale (MW)19
- Event type20
- Lifecycle stage10
- Recency1
- Operator identified4
- Multi-unit evidence7
- External verification2
Signal materiality46
- Event type20
- MW affected14
- Units affected12
New planned wind development signal — 6 units / 42 MW
Schillsdorf, Schleswig-Holstein · Operator: Registered operator name not resolved
6 planned units · 42 MW · First observed 25 Sept 2026
Wind · Wind turbine (horizontal-axis)
Planned commissioning: 31 Dec 2028
What changed
6 new planned wind units totalling 42 MW were first observed in this MaStR snapshot.
Why it may matter
A multi-unit planned development of this scale may represent an early commercial signal worth investigating.
Evidence
- MaStR evidence: HIGH
- Partially corroborated externally · 1 independent source
Project corroboration does not establish procurement activity.
External evidence predates registry detection; newly observed does not necessarily mean a new project.
Possible relevance
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
Verify next
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
- Planned units first observed
- 6
- Total registered capacity
- 42 MW
- Capacity per unit
- 7 MW each
- First observed in MaStR snapshot
- 25 Sept 2026
- Planned commissioning
- 31 Dec 2028
- Project development or development-management services
- Grid-connection / interconnection and electrical infrastructure services
- Engineering and environmental services
- Civil works and balance-of-plant
- Turbine-related services (supply, transport, installation, service)
How to verify
- Identify the developer or project company
- Check planning and permitting status
- Search municipal planning documents
- Search recent company announcements
- Search tenders and procurement notices
- Verify whether construction or supplier selection has started
External evidence details
What we found
External verification: Partially corroborated
Some external sources mention a wind development in Schillsdorf, but the match to the registered project is incomplete. Public project evidence found as early as 12 Jan 2025; GridGraph first observed the MaStR registration on 25 Sept 2026. No public procurement evidence was found in this verification run.
- Project company
- Not resolved
- Developer
- Not identified
- Project evidence
- Partial
- Commercial evidence
- None found
- Windpark WP Altbokhorst Schillsdorf. Technische Daten, Anlagen und mehr. Wetterchen.de - Portal für Wetter und Klima.Web page · wetterchen.de · Published 12 Jan 2025 · medium confidenceSupports: project exists, locationVerified from page text
- Bebauungsplan Nr. 22Municipal planning document · amt-bokhorst-wankendorf.de · Published 3 Mar 2022 · low confidenceSupports: locationVerified from PDF text · page 11“BEGRÜNDUNG ZUM BEBAUUNGSPLAN NR. 22 DER GEMEINDE SCHILLSDORF Seite - 11 deren Anzahl begrenzt. So sind maximal zwei Wohnungen pro Wohngebäude zulässig. Um einer unerwünschten Verdichtung entgegen zu wirken, ist darüber hinaus eine Mindestgröße der Baugrundstücke festgesetzt. Diese beträgt 800 m² und korrespondiert mit den langen schmalen …”Older source: weighed lower unless it clearly describes the same ongoing project.
- Windrad soll von Schillsdorf nach Tasdorf rückenNews / press report · shz.de · Published 22 Oct 2020 · low confidenceSupports: locationVerified from page textOlder source: weighed lower unless it clearly describes the same ongoing project.
- Schillsdorf: Windenergie Zubau (Onshore) in 2025News / press report · windbranche.de · Publication date unknown · low confidenceSupports: locationVerified from page text
No public procurement evidence was found in this verification run.
1 independent external source.
Registry lead relevance: 61 → After external verification: 63 (+2) +2: identity or project only partially corroborated.
Evidence and source lineage
MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Partially corroborated — 1 independent external source at medium confidence or better. External evidence is additional context and never replaces or downgrades the MaStR record; project corroboration is not evidence of procurement or buyer intent.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 6 registered MaStR units
Snapshot transition: First tracked snapshot → 25 Sept 2026
MaStR unit IDs: SEE991356672983, SEE995765850444, SEE907176281373, SEE913919210807, SEE956868942504, SEE973613250141
Commercial signals (6): cmugfshg13evowt1klpvxzbce, cmugfshg23evtwt1k59xq2f4b, cmugfshg23evxwt1kno2reder, cmugfshg23ew2wt1k1pe6mq21, cmugfshg43ewfwt1kyhsckgje, cmugfshg53ewrwt1kymx3kzj6
Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Underlying registrations (6)
New planned asset61Lead relevance · High
Why this ranks high. Mid-sized 20.4 MW signal, 3 registrations moving together and the registered operator is known.
Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Lead relevance61
- Project scale (MW)15
- Event type20
- Lifecycle stage10
- Recency1
- Operator identified10
- Multi-unit evidence5
Signal materiality39
- Event type20
- MW affected11
- Units affected8
New planned wind development signal — 3 units / 20.4 MW
Nordwestuckermark, Brandenburg · Operator: REW Regenerative Energien Wichmannsdorf GmbH
3 planned units · 20.4 MW · First observed 25 Sept 2026
Wind · Wind turbine (horizontal-axis)
Planned commissioning: 01 Jul 2028
What changed
3 new planned wind units totalling 20.4 MW were first observed in this MaStR snapshot.
Why it may matter
A multi-unit planned development of this scale may represent an early commercial signal worth investigating.
Evidence
- MaStR evidence: HIGH
- Search or evidence retrieval incomplete
Possible relevance
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
Verify next
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
- Planned units first observed
- 3
- Total registered capacity
- 20.4 MW
- Capacity per unit
- 6.8 MW each
- First observed in MaStR snapshot
- 25 Sept 2026
- Planned commissioning
- 01 Jul 2028
- Project development or development-management services
- Grid-connection / interconnection and electrical infrastructure services
- Engineering and environmental services
- Civil works and balance-of-plant
- Turbine-related services (supply, transport, installation, service)
How to verify
- Identify the developer or project company
- Check planning and permitting status
- Search municipal planning documents
- Search recent company announcements
- Search tenders and procurement notices
- Verify whether construction or supplier selection has started
External evidence details
What we found
External verification: Search or evidence retrieval incomplete
External search or evidence retrieval could not be completed. This opportunity needs another verification attempt.
- Project company
- REW Regenerative Energien Wichmannsdorf GmbH (registered in MaStR; not confirmed externally)
- Developer
- Not identified
- Project evidence
- None
- Commercial evidence
- None found
- Genehmigung zum Vorhaben Errichtung und Betrieb von ...Permit document · lfu.brandenburg.de · Publication date unknown · low confidenceSupports: company identityJudged from search excerpt only
- mit Postzustellurkunde UKA Umweltgerechte Kraftanlagen ...Permit document · lfu.brandenburg.de · Published 27 Apr 2026 · low confidenceSupports: locationVerified from PDF text · page 1“… zur wesentlichen Änderung von acht Windkraftanlagen (WKA) am Standort in 17291 Nordwestuckermark. Sehr geehrte Damen und Herren, auf den zuvor genannten Antrag ergeht nach der Durchführung des immissionsschutzrechtlichen Genehmigungsverfahrens folgende I. Entscheidung 1. Der Firma UKA Umweltgerechte Kraftanlagen GmbH & Co. KG, Dr. Eberle …”
- Geplante Windkraftanlagen in Nordwestuckermark: NefinoWeb page · nefino.de · Publication date unknown · low confidenceSupports: locationVerified from page text
No public procurement evidence was found in this verification run.
No independent external sources.
Registry lead relevance: 61 (unchanged by external verification) External search or evidence retrieval was incomplete; registry score unchanged.
Evidence and source lineage
MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Search or evidence retrieval incomplete — Search or evidence retrieval incomplete
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 3 registered MaStR units
Snapshot transition: First tracked snapshot → 25 Sept 2026
MaStR unit IDs: SEE913673021480, SEE959917598288, SEE979231402917
Commercial signals (3): cmugfshg23ew1wt1k5rvw81pl, cmugfshg43ewiwt1kh5dv8zp7, cmugfshg53ewswt1krl03zex9
Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Underlying registrations (3)
New planned asset59Lead relevance · Moderate
Why this ranks here. Freshly registered planned asset and the registered operator is known. It affects only one 6.6 MW unit; external corroboration is only partial.
Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Lead relevance59
- Project scale (MW)9
- Event type20
- Lifecycle stage10
- Recency8
- Operator identified10
- External verification2
New planned wind unit — 6.6 MW
Grunow-Dammendorf, Brandenburg · Operator: UKA Umweltgerechte Kraftanlagen GmbH & Co. KG
1 planned unit · 6.6 MW · First observed 24 Oct 2026
Wind · Wind turbine (horizontal-axis)
Planned commissioning: 30 Sept 2029
What changed
A new planned wind unit of 6.6 MW was first observed in this MaStR snapshot.
Why it may matter
A newly registered planned asset may be an early sign of a development worth a quick look.
Evidence
- MaStR evidence: HIGH
- Partially corroborated externally · 2 independent sources
Project corroboration does not establish procurement activity.
External evidence predates registry detection; newly observed does not necessarily mean a new project.
Possible relevance
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
Verify next
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
- Registered capacity
- 6.6 MW
- First observed in MaStR snapshot
- 24 Oct 2026
- Planned commissioning
- 30 Sept 2029
- Project development or development-management services
- Grid-connection / interconnection and electrical infrastructure services
- Engineering and environmental services
- Civil works and balance-of-plant
- Turbine-related services (supply, transport, installation, service)
How to verify
- Identify the developer or project company
- Check planning and permitting status
- Search municipal planning documents
- Search recent company announcements
- Search tenders and procurement notices
- Verify whether construction or supplier selection has started
External evidence details
What we found
External verification: Partially corroborated
Some external sources mention a wind development in Grunow-Dammendorf, but the match to the registered project is incomplete. Public project evidence found as early as 16 Feb 2026; GridGraph first observed the MaStR registration on 24 Oct 2026. No public procurement evidence was found in this verification run.
- Project company
- UKA Umweltgerechte Kraftanlagen GmbH & Co. KG (registered in MaStR; not confirmed externally)
- Developer
- Not identified
- Project evidence
- Partial
- Commercial evidence
- None found
No public procurement evidence was found in this verification run.
2 independent external sources.
Registry lead relevance: 57 → After external verification: 59 (+2) +2: identity or project only partially corroborated.
Evidence and source lineage
MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Partially corroborated — 2 independent external sources at medium confidence or better. External evidence is additional context and never replaces or downgrades the MaStR record; project corroboration is not evidence of procurement or buyer intent.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: First tracked snapshot → 24 Oct 2026
MaStR unit IDs: SEE942854983262
Commercial signals (1): cmvm02hxv1uslwtqsl8p0xora
Grouping basisSingle unit
A single MaStR registration.
Underlying registrations (1)
Operator change54Lead relevance · Moderate
Why this ranks here. Mid-sized 17.1 MW signal and 3 registrations moving together. Operator identity is unresolved, which reduces immediate actionability; no external evidence yet.
Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Lead relevance54
- Project scale (MW)14
- Event type13
- Lifecycle stage10
- Recency8
- Operator identified4
- Multi-unit evidence5
Signal materiality32
- Event type14
- MW affected10
- Units affected8
Registered operator changed on 3 wind units — 3 units / 17.1 MW
Quarnbek, Schleswig-Holstein · Operator: Registered operator name not resolved
3 units · 17.1 MW
Wind · Wind turbine (horizontal-axis)
What changed
The registered operator changed on 3 wind units.
Why it may matter
A registered operator change can be a useful trigger for investigating ownership, project restructuring, or a change in the commercial entity responsible for the asset. It does not by itself establish an acquisition or ownership transfer.
Evidence
- MaStR evidence: HIGH
- Registry only · external search not performed
Possible relevance
Asset transactionsFinancingDue diligenceDeveloper intelligence
Verify next
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
- Units with an operator change
- 3
- Previous registered operator
- Denker & Wulf AG
- New registered operator
- Operator ID ABR984716177570 (name not resolved)
- Project development or development-management services
- Asset or company transaction advisory and technical due diligence
- Financing or refinancing discussions
How to verify
- Look up the new registered operator in the commercial register (Handelsregister)
- Check whether the previous and new operators are related entities
- Search for announcements of a sale, financing or restructuring
Evidence and source lineage
MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 3 registered MaStR units
Snapshot transition: 23 Oct 2026 → 24 Oct 2026
MaStR unit IDs: SEE974256075887, SEE981297117957, SEE982530202904
Commercial signals (3): cmvm02hxw1ustwtqsuu1xmf1e, cmvm02hxw1uswwtqswbv66myi, cmvm02hxw1usxwtqsrma08ay3
Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Underlying registrations (3)