Intelligence brief

German Energy Asset Change Intelligence — 2026-09-20

A curated, source-traceable view of registered MaStR asset updates.

Coverage: 13–20 Sept 2026Latest MaStR snapshot: 20 Sept 2026Snapshots compared: 7

Covers about a week of snapshots. Do not compare its counts with daily reports.

Source coverageLatest MaStR snapshot: 20 Sept 2026Changes compared with: 19 Sept 2026Brief generated: 24 Sept 2026
8Top opportunities shown
The diversified selection shown in the Top section. 84 grouped events score above the investigation threshold in total. A registry signal only: it does not establish procurement activity or buyer intent.
32New development signals
46Major schedule shifts
5Operator changes
20Commissioning events
357.25 MWNewly planned capacity

111 grouped events (units merged into likely site groups; not confirmed projects). Unit-level records: 233 registry changes across 225 registrations, 1.34 GW registered capacity.

Start here

  1. 75New planned wind development signal — 7 units / 49 MW · Drebber, Niedersachsen
  2. 75New planned wind development signal — 4 units / 27.2 MW · Kirchenlamitz, Bayern
  3. 71New planned wind development signal — 5 units / 34 MW · Willebadessen, Nordrhein-Westfalen
  4. 68Commissioning delayed by up to 122 days — 6 units / 40.8 MW · Bördeland, Sachsen-Anhalt
  5. 68Registered wind capacity increased (+5 MW) — 5 units / 35 MW · Andervenne, Niedersachsen

Receive a filtered weekly brief for your market

Tell us which Bundesländer and technologies you care about and we'll follow up with a weekly brief scoped to that — not the full report.

Relevant Bundesländer (optional)
Relevant technologies (optional)

We'll only use this to follow up with a filtered weekly brief for your market. Read how your data is stored and how to withdraw at any time in our Privacy Policy.

Top opportunities to investigate (8)

Selected from the highest-scoring investigation signals, with category diversification to avoid repetitive results. Cards are ordered by opportunity score; a higher-scoring signal of an already well-represented type may appear in a section below. Scores are deterministic and are not probabilities. Everything here is a starting point for verification, not evidence of demand.

New planned asset
75Lead relevance · Very high

Why this ranks high. Large 49 MW multi-unit signal, 7 registrations moving together and the registered operator is known. External corroboration is only partial.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance75

  • Project scale (MW)20
  • Event type20
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence7
  • External verification2

Signal materiality47

  • Event type20
  • MW affected15
  • Units affected12

New planned wind development signal — 7 units / 49 MW

Drebber, Niedersachsen · Operator: Drebber Bürgerwindpark GmbH & Co. KG

7 planned units · 49 MW · First observed 16 Sept 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 31 Dec 2027

7 new planned wind units totalling 49 MW were first observed in this MaStR snapshot.

A multi-unit planned development of this scale may represent an early commercial signal worth investigating.

  • MaStR evidence: HIGH
  • Partially corroborated externally · 4 independent sources

Project corroboration does not establish procurement activity.

Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
7
Total registered capacity
49 MW
Capacity per unit
7 MW each
First observed in MaStR snapshot
16 Sept 2026
Planned commissioning
31 Dec 2027
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
External evidence details

External verification: Partially corroborated

Some external sources mention a wind development in Drebber associated with Drebber Bürgerwindpark GmbH & Co. KG, but the match to the registered project is incomplete. No public procurement evidence was found in this verification run.

Project company
Drebber Bürgerwindpark GmbH & Co. KG
Developer
Not identified
Project evidence
Partial
Commercial evidence
None found

No public procurement evidence was found in this verification run.

4 independent external sources.

Registry lead relevance: 73 → After external verification: 75 (+2) +2: identity or project only partially corroborated.

Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Partially corroborated — 4 independent external sources at medium confidence or better. External evidence is additional context and never replaces or downgrades the MaStR record; project corroboration is not evidence of procurement or buyer intent.
Grouping: Likely site group — Shared unit-name pattern (“drebber wea…”); Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 7 registered MaStR units
Snapshot transition: First tracked snapshot → 16 Sept 2026
MaStR unit IDs: SEE981980713046, SEE998961412010, SEE993853870589, SEE923284256379, SEE905787206136, SEE946975693048, SEE947608936099
Commercial signals (7): cmua8mg8c0et4wtuciqv4ass4, cmua8mg8d0etqwtucqobte081, cmua8mg8d0etjwtuc8g9v7s6f, cmua8mg890er2wtuc3s9tusye, cmua8mg880eqmwtuczjhlw8oj, cmua8mg8a0erqwtucpq2fvxtr, cmua8mg8a0erswtucb8xf4l0e

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“drebber wea…”); Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
New planned asset
75Lead relevance · Very high

Why this ranks high. Mid-sized 27.2 MW signal, 4 registrations moving together, freshly registered planned asset, the registered operator is known and external evidence identifies the project company and corroborates the development, increasing actionability.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance75

  • Project scale (MW)16
  • Event type20
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Multi-unit evidence6
  • External verification6

Signal materiality42

  • Event type20
  • MW affected12
  • Units affected10

New planned wind development signal — 4 units / 27.2 MW

Kirchenlamitz, Bayern · Operator: Primus Dritte Projekt GmbH & Co. KG

4 planned units · 27.2 MW · First observed 18 Sept 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 01 Dec 2028

4 new planned wind units totalling 27.2 MW were first observed in this MaStR snapshot.

A multi-unit planned development of this scale may represent an early commercial signal worth investigating.

  • MaStR evidence: HIGH
  • Externally corroborated · 3 independent sources

Project corroboration does not establish procurement activity.

External evidence predates registry detection; newly observed does not necessarily mean a new project.

Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
4
Total registered capacity
27.2 MW
Capacity per unit
6.8 MW each
First observed in MaStR snapshot
18 Sept 2026
Planned commissioning
01 Dec 2028
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
External evidence details

External verification: Corroborated

External sources corroborate a planned wind development in Kirchenlamitz associated with Primus Dritte Projekt GmbH & Co. KG. A public source also matches the registered project scale. At least one source refers to planning or permitting. Public project evidence found as early as 22 May 2025; GridGraph first observed the MaStR registration on 18 Sept 2026. No public procurement evidence was found in this verification run.

Project company
Primus Dritte Projekt GmbH & Co. KG
Developer
Not identified
Project evidence
Strong
Commercial evidence
None found
  • A M T S B L A T TMunicipal planning document · landkreis-wunsiedel.de · Published 22 May 2025 · high confidenceSupports: project exists, company identity, location, unit count, project stageVerified from PDF text · page 1“… (BImSchG) und Bayerischen Immissionsschutzgesetzes (BayImSchG) Antrag der Firma Primus Dritte Projekt GmbH & Co. KG, Ziegetsdorfer Straße 109, 93051 Regensburg, auf Erteilung eines Vorbescheids für die Errichtung und den Betrieb von vier Windenergieanlagen des Typs Nordex N175/6.X des Windparks Buchenberg, Gemeinde Kirchenlamitz 54 57 Sta …”
  • Kirchenlamitz: Keine Einwände gegen Windräder - Fichtelgebirge - FrankenpostNews / press report · frankenpost.de · Published 20 Jan 2026 · high confidenceSupports: project exists, company identity, location, unit countVerified from page text
  • WINOB Windpark Kirchenlamitz NordWeb page · cdn.prod.website-files.com · Publication date unknown · medium confidenceSupports: project exists, locationPDF · judged from search excerpt only
  • Veranstaltungshinweis - Bürgerversammlung zum Windpark Kirchenlamitz Nord am 11.06.2024Authority document · kirchenlamitz.de · Published 11 Jun 2024 · low confidenceSupports: locationVerified from page text
  • Landratsamt Neumarkt iPermit document · landkreis-neumarkt.de · Published 19 Apr 2024 · low confidenceSupports: company identityVerified from PDF text · page 1“… umarkt i. d. OPf. - Postfach 1405 - 92304 Neumarkt Gegen Postzustellungsurkunde Primus Dritte Projekt GmbH & Co. KG z. Hd. des Geschäftsführers Ziegetsdorfer Straße 109 93051 Regensburg Ihr Zeichen: Ihre Nachricht vom: Unser Zeichen: Sachbearbeiter: Zimmer-Nr.: Telefon: Telefax: E-Mail: Datum: Antrag vom 19.04.2024 45-170-380.H A 217 0918 …”
  • Regierung der OberpfalzPermit document · regierung.oberpfalz.bayern.de · Published 31 Mar 2026 · low confidenceSupports: company identityVerified from PDF text · page 1“… ismarckplatz Regierung der Oberpfalz – 93039 Regensburg Elekronische Zustellung Primus Dritte Projekt GmbH & CO. KG z.Hd. Herr Matthias Jochem o.V. Ziegetsdorfer Straße 109 93051 Regensburg Ihre Zeichen, Ihre Nachricht Unser Zeichen Bearbeiter(in) Regensburg ROP 8711.1-59-5 Herr Deml 31.03.2026 ,,,,, E-Mail Telefon / Telefax Zimmer-Nr. St …”

No public procurement evidence was found in this verification run.

3 independent external sources.

Registry lead relevance: 69 → After external verification: 75 (+6) +6: project corroborated and developer / project company identified by an external source.

Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Corroborated — 3 independent external sources at medium confidence or better. External evidence is additional context and never replaces or downgrades the MaStR record; project corroboration is not evidence of procurement or buyer intent.
Grouping: Likely site group — Shared unit-name pattern (“wp kirchenlamitz wea…”); Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 4 registered MaStR units
Snapshot transition: First tracked snapshot → 18 Sept 2026
MaStR unit IDs: SEE966233130351, SEE933089277165, SEE917429473356, SEE961121611257
Commercial signals (4): cmua8mg8f0ev3wtuc9ue2rd4h, cmua8mg8g0evqwtuc8lb1fz2f, cmua8mg8g0evjwtuci7ek9up5, cmua8mg8f0euvwtucah3sro81

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“wp kirchenlamitz wea…”); Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
New planned asset
71Lead relevance · High

Why this ranks high. Mid-sized 34 MW signal, 5 registrations moving together, freshly registered planned asset and the registered operator is known. A targeted external search found no reliable corroborating source yet, which is not proof that the project does not exist.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance71

  • Project scale (MW)18
  • Event type20
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Multi-unit evidence6

Signal materiality44

  • Event type20
  • MW affected13
  • Units affected11

New planned wind development signal — 5 units / 34 MW

Willebadessen, Nordrhein-Westfalen · Operator: Energiekontor AG

5 planned units · 34 MW · First observed 18 Sept 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 31 Jan 2030

5 new planned wind units totalling 34 MW were first observed in this MaStR snapshot.

A multi-unit planned development of this scale may represent an early commercial signal worth investigating.

  • MaStR evidence: HIGH
  • Registry only · external search performed; no project corroboration
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
5
Total registered capacity
34 MW
Capacity per unit
6.8 MW each
First observed in MaStR snapshot
18 Sept 2026
Planned commissioning
31 Jan 2030
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
External evidence details

External verification: Searched, no reliable evidence found

A targeted search (5 queries) found no sufficiently reliable external source for this wind development in Willebadessen. This does not show that the project does not exist. No public procurement evidence was found in this verification run.

Project company
Energiekontor AG (registered in MaStR; not confirmed externally)
Developer
Not identified
Project evidence
None
Commercial evidence
None found

We searched and found no reliable external evidence yet. This is not proof that the project does not exist.

  • Windpark Greinberg II GbR, Genehmigungsverfahren nach § 4 BImSchG in 34439 Willebadessen | UVP - UmweltverträglichkeitsprüfungenPermit document · uvp-verbund.de · Published 16 Oct 2025 · low confidenceSupports: locationVerified from page text
  • Aufstellung Teilflächennutzungsplan Windkraft zur ( ...Municipal planning document · willebadessen.de · Published 13 Jun 2023 · low confidenceSupports: locationVerified from PDF text · page 12“… ie bisher in der Region verwendeten üblichen Abmessungen hinaus geht. Die Stadt Willebadessen hat mit Unterstützung der KÖTTER Consulting Engineers GmbH & Co. KG, Rheine eine zukünftig zu erwartende Größe und Konfiguration entwickelt: Als Muster wird eine Windkraftanlage mit 8 MW Leistung, 200 m Rotordurchmesser, Nabenhöhe 220 m, Gesamthö …”Older source: weighed lower unless it clearly describes the same ongoing project.
  • Stadt Willebadessen Kreis Höxter Stadtteil ...Municipal planning document · willebadessen.de · Published 10 Jun 2022 · low confidenceSupports: locationVerified from PDF text · page 6“… gründung zur Aufstellung des vorhabenbezogenen Bebauungsplanes Nr. 17 der Stadt Willebadessen: „Sonderbaufläche Windenergie Willebadessen“ im Stadtteil Willebadessen Sonderbaufläche Windenergie Willebadessen Seite 3 Im wirksamen Flächennutzungsplan (FNP) stellt die Stadt Willebadessen zwei Konzentrationszonen für Windkraftanlagen dar. Es …”Older source: weighed lower unless it clearly describes the same ongoing project.

No public procurement evidence was found in this verification run.

No independent external sources.

Registry lead relevance: 71 (unchanged by external verification) Searched, but no reliable external evidence was found; registry score unchanged.

Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Searched, no reliable evidence found — a targeted search found no sufficiently reliable external source, which is not proof that the project does not exist. External evidence is additional context and never replaces or downgrades the MaStR record; project corroboration is not evidence of procurement or buyer intent.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 5 registered MaStR units
Snapshot transition: First tracked snapshot → 18 Sept 2026
MaStR unit IDs: SEE977827994266, SEE954648262774, SEE983176655222, SEE935038950747, SEE964933069131
Commercial signals (5): cmua8mg8f0ev8wtucg6rt7zsz, cmua8mg8h0evywtucwybuu7n4, cmua8mg8e0eunwtucrf9e8w5k, cmua8mg8g0evrwtuc53bgkqiv, cmua8mg8f0euzwtucvufy6tyg

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
68Lead relevance · High

Why this ranks high. Mid-sized 40.8 MW signal, 6 registrations moving together and the registered operator is known.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance68

  • Project scale (MW)19
  • Event type12
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence7
  • Size of change4

Signal materiality58

  • Event type16
  • Size of change16
  • MW affected14
  • Units affected12

Commissioning delayed by up to 122 days — 6 units / 40.8 MW

Bördeland, Sachsen-Anhalt · Operator: Windpark Biere GmbH & Co. KG

6 units · 40.8 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 30 Jun – 30 Sept 2026

6 wind units registered a later planned commissioning date (+30 days to +122 days).

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
6
Planned commissioning before
30 Jun – 30 Sept 2026
Planned commissioning now
30 Oct – 06 Nov 2026
Shift per unit
+30 to +122 days
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“bie r…”); Identical registered capacity; Planned/commissioning dates within 7 days of each other
Presentation group: 6 registered MaStR units
Snapshot transition: 14 Sept 2026 → 16 Sept 2026
MaStR unit IDs: SEE980262956379, SEE906241212045, SEE958151863114, SEE904542985941, SEE960926976110, SEE959774797350
Commercial signals (6): cmua8mg8c0et0wtuca0ebeiu3, cmua8mg880eqnwtucm5x3w9vg, cmua8mg8b0es3wtucfp19xlm7, cmua8mg880eqkwtuczhxecapw, cmua8mg8b0es7wtucg15q5cth, cmua8mg8b0es6wtucdi0ekgsi

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“bie r…”); Identical registered capacity; Planned/commissioning dates within 7 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Capacity change
68Lead relevance · High

Why this ranks high. Mid-sized 35 MW signal, 5 registrations moving together and the registered operator is known.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance68

  • Project scale (MW)18
  • Event type14
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Multi-unit evidence6
  • Size of change3

Signal materiality52

  • Event type18
  • Size of change10
  • MW affected13
  • Units affected11

Registered wind capacity increased (+5 MW) — 5 units / 35 MW

Andervenne, Niedersachsen · Operator: Windpark Andervenne/Handrup GmbH & Co. KG

5 units · 35 MW

Wind · Wind turbine (horizontal-axis)

5 wind units registered a capacity change; combined registered capacity moved from 30 MW to 35 MW (+5 MW).

A larger registered capacity may indicate a changed project design, turbine or equipment choice, or grid-connection scope, and could affect engineering and equipment requirements.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Design / technologyGrid connectionEngineeringEquipment sizing
Design change?Permit & grid documentsDeveloper updates
Facts, hypotheses and how to verify
Per-unit change
5 units changed from 6 MW to 7 MW each
Combined registered capacity now
35 MW
Combined change
+5 MW (+17%)
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Check whether the change reflects a design or turbine-model change
  • Compare with permit and grid-connection documents
  • Look for recent developer announcements
Related registry activity
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Identical registered change on every unit; Planned/commissioning dates within 77 days of each other
Presentation group: 5 registered MaStR units
Snapshot transition: 17 Sept 2026 → 18 Sept 2026
MaStR unit IDs: SEE993980427908, SEE907764600142, SEE910487618479, SEE911227906214, SEE954827990450
Commercial signals (5): cmua8mg8f0eurwtucyiilsa9f, cmua8mg8g0evcwtucksyr60sl, cmua8mg8g0evewtucdkbq5o0l, cmua8mg8g0evfwtucs2omiec7, cmua8mg8h0evzwtuc59dpyvj6

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Planned/commissioning dates within 77 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
New planned asset
68Lead relevance · High

Why this ranks high. Mid-sized 21 MW signal, 3 registrations moving together and the registered operator is known. External corroboration is only partial.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance68

  • Project scale (MW)15
  • Event type20
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence5
  • External verification2

Signal materiality39

  • Event type20
  • MW affected11
  • Units affected8

New planned wind development signal — 3 units / 21 MW

Barnstorf, Niedersachsen · Operator: Drebber Bürgerwindpark GmbH & Co. KG

3 planned units · 21 MW · First observed 16 Sept 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 31 Dec 2027

3 new planned wind units totalling 21 MW were first observed in this MaStR snapshot.

A multi-unit planned development of this scale may represent an early commercial signal worth investigating.

  • MaStR evidence: HIGH
  • Partially corroborated externally · 2 independent sources

Project corroboration does not establish procurement activity.

External evidence predates registry detection; newly observed does not necessarily mean a new project.

Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
3
Total registered capacity
21 MW
Capacity per unit
7 MW each
First observed in MaStR snapshot
16 Sept 2026
Planned commissioning
31 Dec 2027
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
External evidence details

External verification: Partially corroborated

Some external sources mention a wind development in Barnstorf, but the match to the registered project is incomplete. Public project evidence found as early as 6 Feb 2024; GridGraph first observed the MaStR registration on 16 Sept 2026. No public procurement evidence was found in this verification run.

Project company
Drebber Bürgerwindpark GmbH & Co. KG (registered in MaStR; not confirmed externally)
Developer
Not identified
Project evidence
Partial
Commercial evidence
None found

No public procurement evidence was found in this verification run.

2 independent external sources.

Registry lead relevance: 66 → After external verification: 68 (+2) +2: identity or project only partially corroborated.

Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Partially corroborated — 2 independent external sources at medium confidence or better. External evidence is additional context and never replaces or downgrades the MaStR record; project corroboration is not evidence of procurement or buyer intent.
Grouping: Likely site group — Shared unit-name pattern (“drebber wea…”); Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 3 registered MaStR units
Snapshot transition: First tracked snapshot → 16 Sept 2026
MaStR unit IDs: SEE974978989820, SEE984196010558, SEE936621932539
Commercial signals (3): cmua8mg8c0esvwtucw4hx2p3c, cmua8mg8c0et8wtucjx3em9i1, cmua8mg8a0erjwtuchtma6rwn

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“drebber wea…”); Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
67Lead relevance · High

Why this ranks high. Mid-sized 28 MW signal, 4 registrations moving together, unusually large schedule shift (350 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance67

  • Project scale (MW)17
  • Event type12
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence6
  • Size of change6

Signal materiality60

  • Event type16
  • Size of change22
  • MW affected12
  • Units affected10

Commissioning delayed by up to 350 days — 4 units / 28 MW

Pfullendorf, Baden-Württemberg · Operator: ABO Energy Windpark Pfullendorf-Denkingen GmbH & Co. KG

4 units · 28 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Sept 2026 → Aug 2027 (+350 days)

4 wind units registered a later planned commissioning date (+350 days).

A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
4
Planned commissioning (same for every unit)
Sept 2026 → Aug 2027 (+350 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“wp pfullendorf…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 4 registered MaStR units
Snapshot transition: 14 Sept 2026 → 16 Sept 2026
MaStR unit IDs: SEE967662403658, SEE946691682654, SEE991405743596, SEE981599845879
Commercial signals (4): cmua8mg8b0esiwtuco1kt9hyo, cmua8mg8a0erpwtuceqqd686p, cmua8mg8d0etgwtuc1uiwqv9x, cmua8mg8c0et2wtucgdhz86gs

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“wp pfullendorf…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Capacity change
67Lead relevance · High

Why this ranks high. Mid-sized 28 MW signal, 4 registrations moving together and the registered operator is known.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance67

  • Project scale (MW)17
  • Event type14
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Multi-unit evidence6
  • Size of change3

Signal materiality50

  • Event type18
  • Size of change10
  • MW affected12
  • Units affected10

Registered wind capacity increased (+4 MW) — 4 units / 28 MW

Lengerich, Niedersachsen · Operator: Windpark Andervenne/Handrup GmbH & Co. KG

4 units · 28 MW

Wind · Wind turbine (horizontal-axis)

4 wind units registered a capacity change; combined registered capacity moved from 24 MW to 28 MW (+4 MW).

A larger registered capacity may indicate a changed project design, turbine or equipment choice, or grid-connection scope, and could affect engineering and equipment requirements.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Design / technologyGrid connectionEngineeringEquipment sizing
Design change?Permit & grid documentsDeveloper updates
Facts, hypotheses and how to verify
Per-unit change
4 units changed from 6 MW to 7 MW each
Combined registered capacity now
28 MW
Combined change
+4 MW (+17%)
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Check whether the change reflects a design or turbine-model change
  • Compare with permit and grid-connection documents
  • Look for recent developer announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 4 registered MaStR units
Snapshot transition: 17 Sept 2026 → 18 Sept 2026
MaStR unit IDs: SEE964929211100, SEE957853333543, SEE964433332780, SEE909407101382
Commercial signals (4): cmua8mg8f0euywtuc76fvhu7y, cmua8mg8f0euswtucuwnetajo, cmua8mg8f0euxwtucipjzvtr4, cmua8mg8g0evdwtucy5qivonz

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
↑ Back to top

Receive a filtered weekly brief for your market

Tell us which Bundesländer and technologies you care about and we'll follow up with a weekly brief scoped to that — not the full report.

Relevant Bundesländer (optional)
Relevant technologies (optional)

We'll only use this to follow up with a filtered weekly brief for your market. Read how your data is stored and how to withdraw at any time in our Privacy Policy.

New developments (12)

New planned asset
65Lead relevance · High

Why this ranks high. Mid-sized 14 MW signal, freshly registered planned asset and the registered operator is known. External corroboration is only partial.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance65

  • Project scale (MW)13
  • Event type20
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Multi-unit evidence3
  • External verification2

Signal materiality34

  • Event type20
  • MW affected9
  • Units affected5

New planned wind development signal — 2 units / 14 MW

Linnich, Nordrhein-Westfalen · Operator: MLK Consulting GmbH & Co. KG

2 planned units · 14 MW · First observed 18 Sept 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 31 Dec 2028

2 new planned wind units totalling 14 MW were first observed in this MaStR snapshot.

A newly registered planned asset may be an early sign of a development worth a quick look.

  • MaStR evidence: HIGH
  • Partially corroborated externally · 1 independent source

Project corroboration does not establish procurement activity.

External evidence predates registry detection; newly observed does not necessarily mean a new project.

Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
2
Total registered capacity
14 MW
Capacity per unit
7 MW each
First observed in MaStR snapshot
18 Sept 2026
Planned commissioning
31 Dec 2028
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
External evidence details

External verification: Partially corroborated

Some external sources mention a wind development in Linnich, but the match to the registered project is incomplete. Public project evidence found as early as 26 Nov 2023; GridGraph first observed the MaStR registration on 18 Sept 2026. No public procurement evidence was found in this verification run.

Project company
MLK Consulting GmbH & Co. KG (registered in MaStR; not confirmed externally)
Developer
Not identified
Project evidence
Partial
Commercial evidence
None found
  • Neue Windenergieanlagen in Richtung Lövenich (aktualisiert 01/2024) | Dorfgemeinschaft Hottorf e.V.Web page · hottorf.de · Published 26 Nov 2023 · medium confidenceSupports: project exists, company identity, location, unit count, project stageVerified from page text
  • ProjektpläneMunicipal planning document · kreis-dueren.de · Published 18 Dec 2024 · low confidenceSupports: locationVerified from PDF text · page 3“… =WFS (Stand 22.04.2022) Quellen: Bebauungsplan Nr. 6 "Windenergie Gereonsweiler-Linnich" - Ausfertigung Nr.2, Stadt Linnich (2018); M = 1:5.000 Produktfernleitung Würselen - Flugplatz Geilenkirchen, PI-KM 31,215-32,555; Fernleitungs- Betriebsgesellschaft mbH; Digitale Daten erhalten am 17.05.2023 (Az.: 7/23/B47421/23) 86 89 84 80 85 90 86 …”
  • Bekanntmachung im Amtsblatt und auf der Homepage des ...Permit document · kreis-viersen.de · Published 27 Sept 2023 · low confidenceSupports: company identity, unit countVerified from PDF text · page 1“… utzrechtlichen Genehmigungsbescheides vom 27.09.2023 für das Vorhaben der Firma MLK Consulting GmbH &Co. KG, In Tenholt 33, 41812 Erkelenz, zur Errichtung und Betrieb von zwei Windenergieanlagen in Niederkrüchten Dam Für die Stadt/ Gemeinde: Kreis Viersen Sonstiges bitte eintragen: (Verbände, Sparkassen, etc.) keine”
  • Repowering in der Vulkaneifel: MLK und Eegon nehmen Windpark Scheid mit 14 MW Leistung in BetriebNews / press report · iwr.de · Published 16 Jun 2026 · low confidenceSupports: company identity, capacityVerified from page text

No public procurement evidence was found in this verification run.

1 independent external source.

Registry lead relevance: 63 → After external verification: 65 (+2) +2: identity or project only partially corroborated.

Related registry activity
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Partially corroborated — 1 independent external source at medium confidence or better. External evidence is additional context and never replaces or downgrades the MaStR record; project corroboration is not evidence of procurement or buyer intent.
Grouping: Likely site group — Shared unit-name pattern (“windpark linnich l…”); Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: First tracked snapshot → 18 Sept 2026
MaStR unit IDs: SEE900947787715, SEE949151902903
Commercial signals (2): cmua8mg8g0evbwtuceaz7x7xg, cmua8mg8g0evvwtucodf2n0ph

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“windpark linnich l…”); Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
New planned asset
61Lead relevance · High

Why this ranks high. Mid-sized 21 MW signal, 3 registrations moving together and freshly registered planned asset. Operator identity is unresolved, which reduces immediate actionability; a targeted external search found no reliable corroborating source yet, which is not proof that the project does not exist.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance61

  • Project scale (MW)15
  • Event type20
  • Lifecycle stage10
  • Recency7
  • Operator identified4
  • Multi-unit evidence5

Signal materiality39

  • Event type20
  • MW affected11
  • Units affected8

New planned wind development signal — 3 units / 21 MW

Marsberg, Nordrhein-Westfalen · Operator: Registered operator name not resolved

3 planned units · 21 MW · First observed 18 Sept 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 17 Sept 2029

3 new planned wind units totalling 21 MW were first observed in this MaStR snapshot.

A multi-unit planned development of this scale may represent an early commercial signal worth investigating.

  • MaStR evidence: HIGH
  • Registry only · external search performed; no project corroboration
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
3
Total registered capacity
21 MW
Capacity per unit
7 MW each
First observed in MaStR snapshot
18 Sept 2026
Planned commissioning
17 Sept 2029
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
External evidence details

External verification: Searched, no reliable evidence found

A targeted search (5 queries) found no sufficiently reliable external source for this wind development in Marsberg. This does not show that the project does not exist. No public procurement evidence was found in this verification run.

Project company
Not resolved
Developer
Not identified
Project evidence
None
Commercial evidence
None found

We searched and found no reliable external evidence yet. This is not proof that the project does not exist.

  • Öffentliche Bekanntmachung gemäß § 5 Abs. 2 des ...Permit document · hochsauerlandkreis.de · Published 17 Mar 2025 · low confidenceSupports: locationVerified from PDF text · page 1“… chael Flocke auf Erteilung einer Genehmigung gem. § 16 b BImSchG im Stadtgebiet Marsberg Die Windpark Himmelreich GmbH & Co. KG, v.d. E & L Energie & Landwirtschaft Verwaltungs-GmbH, v.d. GF Michael Flocke mit Sitz in 34431 Marsberg-Meerhof, Zur Egge 17 hat beim Hochsauerlandkreis, als zuständiger Genehmigungsbehörde, am 17.03.2025 die Er …”
  • Öffentliche BekanntmachungPermit document · kreis-lippe.de · Published 10 Jul 2025 · low confidenceSupports: locationVerified from PDF text · page 1“… r Gemeinde Leopoldshöhe Der Windpark Greste GmbH & Co. KG, Zur Egge 17 in 34431 Marsberg, wurde mit Bescheid vom 30.06.2025 die Änderungsgenehmigung (Repowering) gem. § 16b Abs. 1 Bundes-Immissionsschutzgesetz (BImSchG) für die Errichtung und den Betrieb von einer Windenergieanlage des Typs Enercon E-138 EP3 E3 (Nennleistung: 4.260 kWel, …”
  • [PDF] Abwägung § 3 (2), § 4 (2) BauGB - Stadt MarsbergMunicipal planning document · marsberg.de · Published 20 Jun 2025 · low confidenceSupports: locationVerified from PDF text · page 3“Stadt Marsberg – 80. Änderung des Flächennutzungsplanes für den Windpark-Giershagen Beteiligung der Öffentlichkeit und der Behörden und sonstigen Träger öffentlicher Belange gemäß §§ 3 (1) und 4 (1) BauGB sowie der Nachbargemeinden gem. § 2 (2) BauGB Seite 3 von 35 Stand: 24.06.2025 lfd. Nr. Einwender/in; Datum der Einwendung lfd. Nr. Äuß …”

No public procurement evidence was found in this verification run.

No independent external sources.

Registry lead relevance: 61 (unchanged by external verification) Searched, but no reliable external evidence was found; registry score unchanged.

Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Searched, no reliable evidence found — a targeted search found no sufficiently reliable external source, which is not proof that the project does not exist. External evidence is additional context and never replaces or downgrades the MaStR record; project corroboration is not evidence of procurement or buyer intent.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 3 registered MaStR units
Snapshot transition: First tracked snapshot → 18 Sept 2026
MaStR unit IDs: SEE944045826150, SEE915835652594, SEE962323158182
Commercial signals (3): cmua8mg8g0evtwtuc9xgkckxu, cmua8mg8g0evgwtucyg6zs2ui, cmua8mg8f0euwwtucraxhv2kt

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
New planned asset
60Lead relevance · High

Why this ranks high. Mid-sized 20.4 MW signal and 3 registrations moving together. Operator identity is unresolved, which reduces immediate actionability.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance60

  • Project scale (MW)15
  • Event type20
  • Lifecycle stage10
  • Recency6
  • Operator identified4
  • Multi-unit evidence5

Signal materiality39

  • Event type20
  • MW affected11
  • Units affected8

New planned wind development signal — 3 units / 20.4 MW

Wielen, Niedersachsen · Operator: Registered operator name not resolved

3 planned units · 20.4 MW · First observed 17 Sept 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 30 Jun 2028

3 new planned wind units totalling 20.4 MW were first observed in this MaStR snapshot.

A multi-unit planned development of this scale may represent an early commercial signal worth investigating.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
3
Total registered capacity
20.4 MW
Capacity per unit
6.8 MW each
First observed in MaStR snapshot
17 Sept 2026
Planned commissioning
30 Jun 2028
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 3 registered MaStR units
Snapshot transition: First tracked snapshot → 17 Sept 2026
MaStR unit IDs: SEE901277924894, SEE966660872428, SEE984940260468
Commercial signals (3): cmua8mg8d0eu0wtuc5lcskgjl, cmua8mg8d0etywtucg9nekd58, cmua8mg8d0etzwtucpdt5ntpr

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
New planned asset
60Lead relevance · High

Why this ranks high. The registered operator is known. Small combined capacity (12.5 MW); the grouping evidence is limited; a targeted external search found no reliable corroborating source yet, which is not proof that the project does not exist.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance60

  • Project scale (MW)12
  • Event type20
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence2

Signal materiality34

  • Event type20
  • MW affected9
  • Units affected5

New planned wind units — 2 units / 12.5 MW

Neukirchen-Vluyn, Nordrhein-Westfalen · Operator: ENNI Energie & Umwelt Niederrhein GmbH Frau Kemper-Wibelitz

2 planned units · 12.5 MW · First observed 17 Sept 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 01 Jan 2029

2 new planned wind units totalling 12.5 MW were first observed in this MaStR snapshot.

A newly registered planned asset may be an early sign of a development worth a quick look.

  • MaStR evidence: HIGH
  • Registry only · external search performed; no project corroboration
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
2
Total registered capacity
12.5 MW
Capacity per unit
5.7–6.8 MW per unit
First observed in MaStR snapshot
17 Sept 2026
Planned commissioning
01 Jan 2029
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
External evidence details

External verification: Searched, no reliable evidence found

A targeted search (5 queries) found no sufficiently reliable external source for this wind development in Neukirchen-Vluyn. This does not show that the project does not exist. No public procurement evidence was found in this verification run.

Project company
ENNI Energie & Umwelt Niederrhein GmbH Frau Kemper-Wibelitz (registered in MaStR; not confirmed externally)
Developer
Not identified
Project evidence
None
Commercial evidence
None found

We searched and found no reliable external evidence yet. This is not proof that the project does not exist.

No public procurement evidence was found in this verification run.

No independent external sources.

Registry lead relevance: 60 (unchanged by external verification) Searched, but no reliable external evidence was found; registry score unchanged.

Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Searched, no reliable evidence found — a targeted search found no sufficiently reliable external source, which is not proof that the project does not exist. External evidence is additional context and never replaces or downgrades the MaStR record; project corroboration is not evidence of procurement or buyer intent.
Grouping: Conservative group — Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: First tracked snapshot → 17 Sept 2026
MaStR unit IDs: SEE939784415895, SEE944861792660
Commercial signals (2): cmua8mg8d0etwwtucdivi3wyp, cmua8mg8d0etxwtucue5qf4vd

Grouping basisConservative group
Supporting registry evidence: Same planned/commissioning date on every unit
These registrations are grouped for presentation because they share location/operator/category characteristics. GridGraph does not assert that this grouping represents one canonical development project.
New planned asset
60Lead relevance · High

Why this ranks high. The registered operator is known. Small combined capacity (11.12 MW); a targeted external search found no reliable corroborating source yet, which is not proof that the project does not exist.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance60

  • Project scale (MW)12
  • Event type20
  • Lifecycle stage10
  • Recency5
  • Operator identified10
  • Multi-unit evidence3

Signal materiality33

  • Event type20
  • MW affected8
  • Units affected5

New planned wind development signal — 2 units / 11.12 MW

Eydelstedt, Niedersachsen · Operator: Casa Projekt GmbH

2 planned units · 11.12 MW · First observed 14 Sept 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 31 Mar 2028

2 new planned wind units totalling 11.12 MW were first observed in this MaStR snapshot.

A newly registered planned asset may be an early sign of a development worth a quick look.

  • MaStR evidence: HIGH
  • Registry only · external search performed; no project corroboration
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
2
Total registered capacity
11.12 MW
Capacity per unit
5.56 MW each
First observed in MaStR snapshot
14 Sept 2026
Planned commissioning
31 Mar 2028
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
External evidence details

External verification: Searched, no reliable evidence found

A targeted search (5 queries) found no sufficiently reliable external source for this wind development in Eydelstedt. This does not show that the project does not exist. No public procurement evidence was found in this verification run.

Project company
Casa Projekt GmbH (registered in MaStR; not confirmed externally)
Developer
Not identified
Project evidence
None
Commercial evidence
None found

We searched and found no reliable external evidence yet. This is not proof that the project does not exist.

No public procurement evidence was found in this verification run.

No independent external sources.

Registry lead relevance: 60 (unchanged by external verification) Searched, but no reliable external evidence was found; registry score unchanged.

Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Searched, no reliable evidence found — a targeted search found no sufficiently reliable external source, which is not proof that the project does not exist. External evidence is additional context and never replaces or downgrades the MaStR record; project corroboration is not evidence of procurement or buyer intent.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: First tracked snapshot → 14 Sept 2026
MaStR unit IDs: SEE980390432899, SEE989229623668
Commercial signals (2): cmua8mg880eqewtucnp7xdr8d, cmua8mg880eqfwtucdlpwfmcz

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
New planned asset
56Lead relevance · Moderate

Why this ranks here. Freshly registered planned asset and the registered operator is known. It affects only one 6.8 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance56

  • Project scale (MW)9
  • Event type20
  • Lifecycle stage10
  • Recency7
  • Operator identified10

Signal materiality27

  • Event type20
  • MW affected7

New planned wind unit — 6.8 MW

Fluorn-Winzeln, Baden-Württemberg · Operator: KS Energiesysteme GmbH & Co. KG

1 planned unit · 6.8 MW · First observed 18 Sept 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 31 Oct 2028

A new planned wind unit of 6.8 MW was first observed in this MaStR snapshot.

A newly registered planned asset may be an early sign of a development worth a quick look.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Registered capacity
6.8 MW
First observed in MaStR snapshot
18 Sept 2026
Planned commissioning
31 Oct 2028
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: First tracked snapshot → 18 Sept 2026
MaStR unit IDs: SEE939940025395
Commercial signals (1): cmua8mg8g0evswtuchf0o1icq

Grouping basisSingle unit
A single MaStR registration.
New planned asset
55Lead relevance · Moderate

Why this ranks here. Freshly registered planned asset and the registered operator is known. Small combined capacity (3.55 MW); the grouping evidence is limited; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance55

  • Project scale (MW)6
  • Event type20
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Multi-unit evidence2

Signal materiality30

  • Event type20
  • MW affected5
  • Units affected5

New planned biomass units — 2 units / 3.55 MW

Wilsecker, Rheinland-Pfalz · Operator: Bioenergie Günter Nels

2 planned units · 3.55 MW · First observed 18 Sept 2026

Biomass · Verbrennungsmotor

Planned commissioning: 01 Nov 2026

2 new planned biomass units totalling 3.55 MW were first observed in this MaStR snapshot.

A newly registered planned asset may be an early sign of a development worth a quick look.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Developer servicesGrid connectionElectrical BOPCivil / BOPEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Planned units first observed
2
Total registered capacity
3.55 MW
Capacity per unit
1.52–2.03 MW per unit
First observed in MaStR snapshot
18 Sept 2026
Planned commissioning
01 Nov 2026
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Conservative group — Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: First tracked snapshot → 18 Sept 2026
MaStR unit IDs: SEE915904736682, SEE923306785566
Commercial signals (2): cmua8mg8g0evhwtucpb5jhf90, cmua8mg8g0evkwtuc3ljzyq1j

Grouping basisConservative group
Supporting registry evidence: Same planned/commissioning date on every unit
These registrations are grouped for presentation because they share location/operator/category characteristics. GridGraph does not assert that this grouping represents one canonical development project.
New planned asset
55Lead relevance · Moderate

Why this ranks here. The registered operator is known. It affects only one 7.2 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance55

  • Project scale (MW)9
  • Event type20
  • Lifecycle stage10
  • Recency6
  • Operator identified10

Signal materiality27

  • Event type20
  • MW affected7

New planned wind unit — 7.2 MW

Schwedt/Oder, Brandenburg · Operator: TEUT Energieprojekte GmbH

1 planned unit · 7.2 MW · First observed 16 Sept 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 01 Jul 2028

A new planned wind unit of 7.2 MW was first observed in this MaStR snapshot.

A newly registered planned asset may be an early sign of a development worth a quick look.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Registered capacity
7.2 MW
First observed in MaStR snapshot
16 Sept 2026
Planned commissioning
01 Jul 2028
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: First tracked snapshot → 16 Sept 2026
MaStR unit IDs: SEE978577149425
Commercial signals (1): cmua8mg8c0eszwtuc8xmkspza

Grouping basisSingle unit
A single MaStR registration.
New planned asset
55Lead relevance · Moderate

Why this ranks here. The registered operator is known. It affects only one 7 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance55

  • Project scale (MW)9
  • Event type20
  • Lifecycle stage10
  • Recency6
  • Operator identified10

Signal materiality27

  • Event type20
  • MW affected7

New planned wind unit — 7 MW

Buchholz in der Nordheide, Niedersachsen · Operator: Windpark Trelder Berg GmbH & Co. KG

1 planned unit · 7 MW · First observed 17 Sept 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 31 Mar 2028

A new planned wind unit of 7 MW was first observed in this MaStR snapshot.

A newly registered planned asset may be an early sign of a development worth a quick look.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Registered capacity
7 MW
First observed in MaStR snapshot
17 Sept 2026
Planned commissioning
31 Mar 2028
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: First tracked snapshot → 17 Sept 2026
MaStR unit IDs: SEE962620902549
Commercial signals (1): cmua8mg8d0etvwtuc6ny299v8

Grouping basisSingle unit
A single MaStR registration.
New planned asset
55Lead relevance · Moderate

Why this ranks here. The registered operator is known. It affects only one 7 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance55

  • Project scale (MW)9
  • Event type20
  • Lifecycle stage10
  • Recency6
  • Operator identified10

Signal materiality27

  • Event type20
  • MW affected7

New planned wind unit — 7 MW

Nuthe-Urstromtal, Brandenburg · Operator: Achtruten GmbH

1 planned unit · 7 MW · First observed 16 Sept 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 01 Nov 2029

A new planned wind unit of 7 MW was first observed in this MaStR snapshot.

A newly registered planned asset may be an early sign of a development worth a quick look.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Registered capacity
7 MW
First observed in MaStR snapshot
16 Sept 2026
Planned commissioning
01 Nov 2029
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: First tracked snapshot → 16 Sept 2026
MaStR unit IDs: SEE908196034888
Commercial signals (1): cmua8mg880eqqwtuchxj3wnyx

Grouping basisSingle unit
A single MaStR registration.
New planned asset
55Lead relevance · Moderate

Why this ranks here. The registered operator is known. It affects only one 6.8 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance55

  • Project scale (MW)9
  • Event type20
  • Lifecycle stage10
  • Recency6
  • Operator identified10

Signal materiality27

  • Event type20
  • MW affected7

New planned wind unit — 6.8 MW

Ottenstein, Niedersachsen · Operator: wpd Windpark Lichtenhagen-Ottenstein GmbH & Co. KG

1 planned unit · 6.8 MW · First observed 16 Sept 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 01 Sept 2029

A new planned wind unit of 6.8 MW was first observed in this MaStR snapshot.

A newly registered planned asset may be an early sign of a development worth a quick look.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Registered capacity
6.8 MW
First observed in MaStR snapshot
16 Sept 2026
Planned commissioning
01 Sept 2029
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: First tracked snapshot → 16 Sept 2026
MaStR unit IDs: SEE931881125646
Commercial signals (1): cmua8mg890erdwtucgpuo2upv

Grouping basisSingle unit
A single MaStR registration.
New planned asset
55Lead relevance · Moderate

Why this ranks here. Freshly registered planned asset and the registered operator is known. It affects only one 5.7 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance55

  • Project scale (MW)8
  • Event type20
  • Lifecycle stage10
  • Recency7
  • Operator identified10

Signal materiality27

  • Event type20
  • MW affected7

New planned wind unit — 5.7 MW

Wittenhagen, Mecklenburg-Vorpommern · Operator: Windpark Wittenhagen GmbH

1 planned unit · 5.7 MW · First observed 19 Sept 2026

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 08 Sept 2030

A new planned wind unit of 5.7 MW was first observed in this MaStR snapshot.

A newly registered planned asset may be an early sign of a development worth a quick look.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Turbine supplyGrid connectionElectrical BOPCivil / foundationsEngineering
PermitsDeveloper newsProcurement / tenders
Facts, hypotheses and how to verify
Registered capacity
5.7 MW
First observed in MaStR snapshot
19 Sept 2026
Planned commissioning
08 Sept 2030
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Civil works and balance-of-plant
  • Turbine-related services (supply, transport, installation, service)
  • Identify the developer or project company
  • Check planning and permitting status
  • Search municipal planning documents
  • Search recent company announcements
  • Search tenders and procurement notices
  • Verify whether construction or supplier selection has started
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: First tracked snapshot → 19 Sept 2026
MaStR unit IDs: SEE939153505967
Commercial signals (1): cmua8mg8h0ew3wtuczudhjttm

Grouping basisSingle unit
A single MaStR registration.
↑ Back to top

Major schedule changes (12)

Schedule change
67Lead relevance · High

Why this ranks high. Large 61.16 MW multi-unit signal, 11 registrations moving together and the registered operator is known.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance67

  • Project scale (MW)21
  • Event type8
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence9
  • Size of change3

Signal materiality59

  • Event type16
  • Size of change12
  • MW affected16
  • Units affected15

Commissioning delayed by up to 61 days — 11 units / 61.16 MW

Osterwieck, Sachsen-Anhalt · Operator: BürgerEnergiePark Druiberg GmbH & Co. KG

11 units · 61.16 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Aug 2026 → Oct 2026 (+61 days)

11 wind units registered a later planned commissioning date (+61 days).

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
11
Planned commissioning (same for every unit)
Aug 2026 → Oct 2026 (+61 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 11 registered MaStR units
Snapshot transition: 14 Sept 2026 → 16 Sept 2026
MaStR unit IDs: SEE923194783002, SEE965611938862, SEE921734338453, SEE942701385935, SEE904699493788, SEE961955578634, SEE928400364181, SEE908262824344, SEE971876086033, SEE972209952865, SEE914107132826
Commercial signals (11): cmua8mg890er1wtucjncyf60l, cmua8mg8b0esgwtucbkw2hcbl, cmua8mg890eqzwtuc0ujv6q53, cmua8mg8a0ermwtucdo1rxd3u, cmua8mg880eqlwtuckcptbecq, cmua8mg8b0es8wtucqfzdb41l, cmua8mg890er8wtucpobh7dtx, cmua8mg880eqrwtuc1wxr3wsd, cmua8mg8c0esowtucb2dppkgf, cmua8mg8c0esqwtuc533nopb5, cmua8mg890equwtucom7liu5u

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
67Lead relevance · High

Why this ranks high. Mid-sized 33.6 MW signal, 8 registrations moving together and the registered operator is known.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance67

  • Project scale (MW)18
  • Event type12
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence7
  • Size of change4

Signal materiality56

  • Event type16
  • Size of change14
  • MW affected13
  • Units affected13

Commissioning delayed by up to 91 days — 8 units / 33.6 MW

Vierlinden, Brandenburg · Operator: Windpark GmbH & Co. Friedersdorf KG

8 units · 33.6 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Sept 2026 → Dec 2026 (+91 days)

8 wind units registered a later planned commissioning date (+91 days).

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
8
Planned commissioning (same for every unit)
Sept 2026 → Dec 2026 (+91 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 8 registered MaStR units
Snapshot transition: 14 Sept 2026 → 16 Sept 2026
MaStR unit IDs: SEE922685481786, SEE913520124807, SEE919145966020, SEE947246001616, SEE904081043287, SEE995527757547, SEE958709807737, SEE965280610458
Commercial signals (8): cmua8mg890er0wtuc6b3gvsoc, cmua8mg890eqswtuc9olx7473, cmua8mg890eqvwtucg1mqu8km, cmua8mg8a0errwtuce69cmddv, cmua8mg880eqiwtucehsm7uro, cmua8mg8d0etlwtuc62visat5, cmua8mg8b0es5wtucy3awx2ir, cmua8mg8b0esdwtuctf0drz5m

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
66Lead relevance · High

Why this ranks high. Mid-sized 30 MW signal, 5 registrations moving together, unusually large schedule shift (254 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance66

  • Project scale (MW)17
  • Event type12
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence6
  • Size of change5

Signal materiality60

  • Event type16
  • Size of change20
  • MW affected13
  • Units affected11

Commissioning delayed by up to 254 days — 5 units / 30 MW

Andervenne, Niedersachsen · Operator: Windpark Andervenne/Handrup GmbH & Co. KG

5 units · 30 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 01 Jan 2028

5 wind units registered a later planned commissioning date (+177 days to +254 days).

A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
5
Planned commissioning before
01 Jan 2028
Planned commissioning now
26 Jun – 11 Sept 2028
Shift per unit
+177 to +254 days
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Related registry activity
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Planned/commissioning dates within 77 days of each other
Presentation group: 5 registered MaStR units
Snapshot transition: 16 Sept 2026 → 17 Sept 2026
MaStR unit IDs: SEE993980427908, SEE911227906214, SEE907764600142, SEE954827990450, SEE910487618479
Commercial signals (5): cmua8mg8e0eu2wtucatxnil2t, cmua8mg8e0eu6wtucf21vmci8, cmua8mg8e0eu5wtuczprazoq8, cmua8mg8e0eu4wtucnr2objjq, cmua8mg8e0eu3wtucbhyamtj6

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Planned/commissioning dates within 77 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
66Lead relevance · High

Why this ranks high. Mid-sized 28 MW signal, 4 registrations moving together, unusually large schedule shift (212 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance66

  • Project scale (MW)17
  • Event type12
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence6
  • Size of change5

Signal materiality57

  • Event type16
  • Size of change19
  • MW affected12
  • Units affected10

Commissioning delayed by up to 212 days — 4 units / 28 MW

Aschersleben, Sachsen-Anhalt · Operator: Windpark Aschersleben West GmbH & Co. Betriebs-KG

4 units · 28 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Sept 2026 → Apr 2027 (+212 days)

4 wind units registered a later planned commissioning date (+212 days).

A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
4
Planned commissioning (same for every unit)
Sept 2026 → Apr 2027 (+212 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 4 registered MaStR units
Snapshot transition: 16 Sept 2026 → 17 Sept 2026
MaStR unit IDs: SEE983155477517, SEE951902626280, SEE935657041444, SEE978717307883
Commercial signals (4): cmua8mg8e0eufwtucotbfurcu, cmua8mg8e0euewtucvuh5x82x, cmua8mg8e0eudwtuclhz7i2cc, cmua8mg8e0eucwtucp7t9kzot

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
66Lead relevance · High

Why this ranks high. Mid-sized 34 MW signal, 5 registrations moving together and the registered operator is known.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance66

  • Project scale (MW)18
  • Event type12
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence6
  • Size of change4

Signal materiality54

  • Event type16
  • Size of change14
  • MW affected13
  • Units affected11

Commissioning delayed by up to 91 days — 5 units / 34 MW

Westerstede, Niedersachsen · Operator: Windpark Garnholt II GmbH & Co. KG

5 units · 34 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Sept 2026 → Dec 2026 (+91 days)

5 wind units registered a later planned commissioning date (+91 days).

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
5
Planned commissioning (same for every unit)
Sept 2026 → Dec 2026 (+91 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“garnholt repowering…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 5 registered MaStR units
Snapshot transition: 14 Sept 2026 → 16 Sept 2026
MaStR unit IDs: SEE925554984784, SEE928990214590, SEE945782084636, SEE998286058351, SEE972206472441
Commercial signals (5): cmua8mg890er4wtuc3b2lqiz7, cmua8mg890er9wtucx3sj4t4i, cmua8mg8a0erowtucllhpdpt9, cmua8mg8d0etnwtucg24iuap7, cmua8mg8c0espwtucmpifwub8

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“garnholt repowering…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
63Lead relevance · High

Why this ranks high. Mid-sized 17.1 MW signal, 3 registrations moving together, unusually large schedule shift (395 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance63

  • Project scale (MW)14
  • Event type12
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence5
  • Size of change6

Signal materiality56

  • Event type16
  • Size of change22
  • MW affected10
  • Units affected8

Commissioning delayed by up to 395 days — 3 units / 17.1 MW

Riepsdorf, Schleswig-Holstein · Operator: Gosdorfer Windenergie GmbH & Co. KG

3 units · 17.1 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Sept 2026 → Oct 2027 (+395 days)

3 wind units registered a later planned commissioning date (+395 days).

A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
3
Planned commissioning (same for every unit)
Sept 2026 → Oct 2027 (+395 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 3 registered MaStR units
Snapshot transition: 16 Sept 2026 → 17 Sept 2026
MaStR unit IDs: SEE981646345239, SEE906387470156, SEE910197833025
Commercial signals (3): cmua8mg8e0eu9wtucguy674pm, cmua8mg8e0eu8wtuc6gwbel7w, cmua8mg8e0eu7wtuczo46ypak

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
60Lead relevance · High

Why this ranks high. 3 registrations moving together, unusually large schedule shift (487 days) and the registered operator is known. Small combined capacity (10.8 MW); it may still reflect a registry correction rather than a new commercial need.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance60

  • Project scale (MW)11
  • Event type12
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence5
  • Size of change6

Signal materiality55

  • Event type16
  • Size of change23
  • MW affected8
  • Units affected8

Commissioning delayed by up to 487 days — 3 units / 10.8 MW

Neu Wulmstorf, Niedersachsen · Operator: Bürgerwind Neu Wulmstorf GmbH & Co. KG

3 units · 10.8 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Aug 2026 → Dec 2027 (+487 days)

3 wind units registered a later planned commissioning date (+487 days).

A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
3
Planned commissioning (same for every unit)
Aug 2026 → Dec 2027 (+487 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“wp ardestorf e…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 3 registered MaStR units
Snapshot transition: 14 Sept 2026 → 16 Sept 2026
MaStR unit IDs: SEE998567815413, SEE952445092044, SEE919482350469
Commercial signals (3): cmua8mg8d0etowtucqet2a4qo, cmua8mg8a0erywtucdqx8ivet, cmua8mg890eqwwtucx8o8i77q

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“wp ardestorf e…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
60Lead relevance · High

Why this ranks high. Mid-sized 14.4 MW signal, unusually large schedule shift (393 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance60

  • Project scale (MW)13
  • Event type12
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence3
  • Size of change6

Signal materiality53

  • Event type16
  • Size of change22
  • MW affected10
  • Units affected5

Commissioning delayed by up to 393 days — 2 units / 14.4 MW

Ostritz, Sachsen · Operator: Windpark Leuba GmbH & Co. KG

2 units · 14.4 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Dec 2026 → Jan 2028 (+393 days)

2 wind units registered a later planned commissioning date (+393 days).

A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
2
Planned commissioning (same for every unit)
Dec 2026 → Jan 2028 (+393 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: 14 Sept 2026 → 16 Sept 2026
MaStR unit IDs: SEE994718969318, SEE944980938314
Commercial signals (2): cmua8mg8d0etkwtucgfa8aoi1, cmua8mg8a0ernwtuch6l31rba

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
59Lead relevance · Moderate

Why this ranks here. Mid-sized 24.8 MW signal, 4 registrations moving together and the registered operator is known. No external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance59

  • Project scale (MW)16
  • Event type8
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence6
  • Size of change3

Signal materiality49

  • Event type16
  • Size of change11
  • MW affected12
  • Units affected10

Commissioning delayed by up to 49 days — 4 units / 24.8 MW

Groitzsch, Sachsen · Operator: Windpark Breunsdorf I GmbH

4 units · 24.8 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 29 Aug – 19 Sept 2026

4 wind units registered a later planned commissioning date (+25 days to +49 days).

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
4
Planned commissioning before
29 Aug – 19 Sept 2026
Planned commissioning now
30 Sept – 31 Oct 2026
Shift per unit
+25 to +49 days
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“wp breunsdorf…”); Identical registered capacity; Planned/commissioning dates within 31 days of each other
Presentation group: 4 registered MaStR units
Snapshot transition: 14 Sept 2026 → 16 Sept 2026
MaStR unit IDs: SEE991782946146, SEE935658230519, SEE983618247596, SEE906379861047
Commercial signals (4): cmua8mg8d0ethwtuciro4qe2k, cmua8mg8a0ergwtucccfqeopf, cmua8mg8c0et6wtuc2g1fowvf, cmua8mg880eqowtucmh450o0m

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“wp breunsdorf…”); Identical registered capacity; Planned/commissioning dates within 31 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
58Lead relevance · Moderate

Why this ranks here. Unusually large schedule shift (242 days) and the registered operator is known. Small combined capacity (11.12 MW); it may still reflect a registry correction rather than a new commercial need; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance58

  • Project scale (MW)12
  • Event type12
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence3
  • Size of change5

Signal materiality49

  • Event type16
  • Size of change20
  • MW affected8
  • Units affected5

Commissioning delayed by up to 242 days — 2 units / 11.12 MW

Nideggen, Nordrhein-Westfalen · Operator: Energiepark Nideggen WP Wollersheim-Süd GmbH & Co. KG

2 units · 11.12 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Nov 2026 → Jul 2027 (+242 days)

2 wind units registered a later planned commissioning date (+242 days).

A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
2
Planned commissioning (same for every unit)
Nov 2026 → Jul 2027 (+242 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: 14 Sept 2026 → 16 Sept 2026
MaStR unit IDs: SEE974879084358, SEE969693002466
Commercial signals (2): cmua8mg8c0esuwtucmp258ihh, cmua8mg8b0esmwtucijusskz0

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
58Lead relevance · Moderate

Why this ranks here. Mid-sized 13.6 MW signal and the registered operator is known. No external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance58

  • Project scale (MW)13
  • Event type12
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence3
  • Size of change4

Signal materiality44

  • Event type16
  • Size of change14
  • MW affected9
  • Units affected5

Commissioning delayed by up to 91 days — 2 units / 13.6 MW

Ochtrup, Nordrhein-Westfalen · Operator: Dirkshof Verwaltungs GmbH

2 units · 13.6 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Sept 2026 → Dec 2026 (+91 days)

2 wind units registered a later planned commissioning date (+91 days).

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
2
Planned commissioning (same for every unit)
Sept 2026 → Dec 2026 (+91 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: 14 Sept 2026 → 16 Sept 2026
MaStR unit IDs: SEE926891013687, SEE929145793823
Commercial signals (2): cmua8mg890er6wtuc8pxmstam, cmua8mg890erawtuc9ggc1cax

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Schedule change
57Lead relevance · Moderate

Why this ranks here. The registered operator is known. Small combined capacity (11.12 MW); no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance57

  • Project scale (MW)12
  • Event type12
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence3
  • Size of change4

Signal materiality43

  • Event type16
  • Size of change14
  • MW affected8
  • Units affected5

Commissioning delayed by up to 92 days — 2 units / 11.12 MW

Lügde, Nordrhein-Westfalen · Operator: Westwind Projektierungs GmbH & Co. KG

2 units · 11.12 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Aug 2026 → Nov 2026 (+92 days)

2 wind units registered a later planned commissioning date (+92 days).

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Units with a new planned date
2
Planned commissioning (same for every unit)
Aug 2026 → Nov 2026 (+92 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: 14 Sept 2026 → 16 Sept 2026
MaStR unit IDs: SEE939389536018, SEE973074301017
Commercial signals (2): cmua8mg8a0erkwtucigc5q6zj, cmua8mg8c0esrwtucjcf4atwb

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
↑ Back to top

Capacity changes (6)

Multiple changes
66Lead relevance · High

Why this ranks high. Capacity and schedule changes recorded together on the same units and the registered operator is known. Small combined capacity (10.5 MW).

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance66

  • Project scale (MW)11
  • Event type14
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Multi-unit evidence3
  • Several changes together5
  • Size of change6

Signal materiality59

  • Event type18
  • Size of change22
  • MW affected8
  • Units affected5
  • Several changes together6

Multiple registry changes (capacity + schedule) — 2 units / 10.5 MW

Nordwestuckermark, Brandenburg · Operator: MLK Brandenburg Windpark Entwicklungs GmbH & Co. KG

2 units · 10.5 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Dec 2026 → Dec 2027 (+365 days)

2 wind units registered a capacity change; combined registered capacity moved from 8.4 MW to 10.5 MW (+2.1 MW). 2 wind units registered a later planned commissioning date (+365 days).

Several registry changes were recorded together on the same units. That may indicate a substantive update to the project rather than a routine correction, and is worth investigating.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Design / technologyGrid connectionEngineeringEquipment sizingProject schedulingConstruction timing
Design change?Permit & grid documentsDeveloper updatesRegistry correction?
Facts, hypotheses and how to verify
Units with a capacity change
2
Per-unit change
+0.6 MW to +1.5 MW
Combined registered capacity now
10.5 MW
Combined change
+2.1 MW (+25%) — from 8.4 MW
Units with a new planned date
2
Planned commissioning (same for every unit)
Dec 2026 → Dec 2027 (+365 days)
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Check whether the change reflects a design or turbine-model change
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Compare with permit and grid-connection documents
  • Check permitting and construction status
  • Look for recent developer announcements
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“mlk wp horst…”); Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: 17 Sept 2026 → 18 Sept 2026
MaStR unit IDs: SEE930756682567, SEE965375636790
Commercial signals (4): cmua8mg8g0evowtuckv2vymbm, cmua8mg8f0ev0wtucnpprgtdq, cmua8mg8g0evpwtucjaq51zu3, cmua8mg8f0ev1wtuchta5bupb

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“mlk wp horst…”); Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Capacity change
62Lead relevance · High

Why this ranks high. Mid-sized 17.56 MW signal, 3 registrations moving together and the registered operator is known.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance62

  • Project scale (MW)14
  • Event type14
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence5
  • Size of change3

Signal materiality48

  • Event type18
  • Size of change12
  • MW affected10
  • Units affected8

Registered wind capacity reduced (-3.44 MW) — 3 units / 17.56 MW

Rheda-Wiedenbrück, Nordrhein-Westfalen · Operator: Rheda-Wiedenbrücker Energiegenossenschaft eG

3 units · 17.56 MW

Wind · Wind turbine (horizontal-axis)

3 wind units registered a capacity change; combined registered capacity moved from 21 MW to 17.56 MW (-3.44 MW).

A smaller registered capacity may indicate a scaled-back or redesigned project, which could change the scope of engineering and equipment requirements.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Design / technologyGrid connectionEngineeringEquipment sizing
Design change?Permit & grid documentsDeveloper updates
Facts, hypotheses and how to verify
Units with a capacity change
3
Per-unit change
-1.44 MW to -1 MW
Combined registered capacity now
17.56 MW
Combined change
-3.44 MW (-16%) — from 21 MW
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Check whether the change reflects a design or turbine-model change
  • Compare with permit and grid-connection documents
  • Look for recent developer announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“rheda wiedenbrück…”); Same planned/commissioning date on every unit
Presentation group: 3 registered MaStR units
Snapshot transition: 14 Sept 2026 → 16 Sept 2026
MaStR unit IDs: SEE964610181217, SEE977030266792, SEE931714231414
Commercial signals (3): cmua8mg8b0esbwtuc06zjc02b, cmua8mg8c0esywtuckutbyxs1, cmua8mg890ercwtuct2x5lztm

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“rheda wiedenbrück…”); Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Multiple changes
60Lead relevance · High

Why this ranks high. Capacity and schedule changes recorded together on the same units and the registered operator is known. It affects only one 7 MW unit.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance60

  • Project scale (MW)9
  • Event type14
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Several changes together5
  • Size of change5

Signal materiality50

  • Event type18
  • Size of change19
  • MW affected7
  • Several changes together6

Multiple registry changes (capacity + schedule) — 7 MW

Jarmen, Mecklenburg-Vorpommern · Operator: Windkraft Plötz

1 unit · 7 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: Aug 2028 → Mar 2028 (-153 days)

Registered capacity changed from 4.6 MW to 7 MW (+2.4 MW, +52%). The registered planned commissioning date moved by -153 days (Aug 2028 → Mar 2028).

Several registry changes were recorded together on the same units. That may indicate a substantive update to the project rather than a routine correction, and is worth investigating.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Design / technologyGrid connectionEngineeringEquipment sizingProject schedulingConstruction timing
Design change?Permit & grid documentsDeveloper updatesRegistry correction?
Facts, hypotheses and how to verify
Registered capacity
4.6 MW → 7 MW (+2.4 MW / +52%)
Planned commissioning
Aug 2028 → Mar 2028 (-153 days)
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Check whether the change reflects a design or turbine-model change
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Compare with permit and grid-connection documents
  • Check permitting and construction status
  • Look for recent developer announcements
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 18 Sept 2026 → 19 Sept 2026
MaStR unit IDs: SEE904288262849
Commercial signals (2): cmua8mg8i0ewrwtucm7uxvarz, cmua8mg8i0ewqwtuco1rf195d

Grouping basisSingle unit
A single MaStR registration.
Capacity change
60Lead relevance · High

Why this ranks high. Mid-sized 14 MW signal and the registered operator is known.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance60

  • Project scale (MW)13
  • Event type14
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Multi-unit evidence3
  • Size of change3

Signal materiality42

  • Event type18
  • Size of change10
  • MW affected9
  • Units affected5

Registered wind capacity increased (+2 MW) — 2 units / 14 MW

Linnich, Nordrhein-Westfalen · Operator: MLK Consulting GmbH & Co. KG

2 units · 14 MW

Wind · Wind turbine (horizontal-axis)

2 wind units registered a capacity change; combined registered capacity moved from 12 MW to 14 MW (+2 MW).

A larger registered capacity may indicate a changed project design, turbine or equipment choice, or grid-connection scope, and could affect engineering and equipment requirements.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Design / technologyGrid connectionEngineeringEquipment sizing
Design change?Permit & grid documentsDeveloper updates
Facts, hypotheses and how to verify
Per-unit change
2 units changed from 6 MW to 7 MW each
Combined registered capacity now
14 MW
Combined change
+2 MW (+17%)
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Check whether the change reflects a design or turbine-model change
  • Compare with permit and grid-connection documents
  • Look for recent developer announcements
Related registry activity
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“windpark linnich l…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: 17 Sept 2026 → 18 Sept 2026
MaStR unit IDs: SEE989096479764, SEE967631317245
Commercial signals (2): cmua8mg8f0euqwtucpn7c3ll8, cmua8mg8f0ev4wtucmdops84s

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“windpark linnich l…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Capacity change
53Lead relevance · Moderate

Why this ranks here. The registered operator is known. It affects only one 7 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance53

  • Project scale (MW)9
  • Event type14
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Size of change3

Signal materiality35

  • Event type18
  • Size of change10
  • MW affected7

Registered wind capacity increased (+1 MW) — 7 MW

Linnich, Nordrhein-Westfalen · Operator: Ventus Bürgerstrom Kofferen Nr. 125 GmbH & Co. KG

1 unit · 7 MW

Wind · Wind turbine (horizontal-axis)

Registered capacity changed from 6 MW to 7 MW (+1 MW, +17%).

A larger registered capacity may indicate a changed project design, turbine or equipment choice, or grid-connection scope, and could affect engineering and equipment requirements.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Design / technologyGrid connectionEngineeringEquipment sizing
Design change?Permit & grid documentsDeveloper updates
Facts, hypotheses and how to verify
Registered capacity
6 MW → 7 MW (+1 MW / +17%)
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Check whether the change reflects a design or turbine-model change
  • Compare with permit and grid-connection documents
  • Look for recent developer announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 17 Sept 2026 → 18 Sept 2026
MaStR unit IDs: SEE951203193535
Commercial signals (1): cmua8mg8g0evxwtuc5se8tz0f

Grouping basisSingle unit
A single MaStR registration.
Capacity change
52Lead relevance · Moderate

Why this ranks here. The registered operator is known. It affects only one 7 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance52

  • Project scale (MW)9
  • Event type14
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Size of change3

Signal materiality35

  • Event type18
  • Size of change10
  • MW affected7

Registered wind capacity increased (+1 MW) — 7 MW

Olfen, Nordrhein-Westfalen · Operator: GENREO - Gesellschaft zur Nutzung regenerativer Energien in Olfen mbH

1 unit · 7 MW

Wind · Wind turbine (horizontal-axis)

Registered capacity changed from 6 MW to 7 MW (+1 MW, +17%).

A larger registered capacity may indicate a changed project design, turbine or equipment choice, or grid-connection scope, and could affect engineering and equipment requirements.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Design / technologyGrid connectionEngineeringEquipment sizing
Design change?Permit & grid documentsDeveloper updates
Facts, hypotheses and how to verify
Registered capacity
6 MW → 7 MW (+1 MW / +17%)
  • Project development or development-management services
  • Grid-connection / interconnection and electrical infrastructure services
  • Engineering and environmental services
  • Check whether the change reflects a design or turbine-model change
  • Compare with permit and grid-connection documents
  • Look for recent developer announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 14 Sept 2026 → 16 Sept 2026
MaStR unit IDs: SEE903356207102
Commercial signals (1): cmua8mg880eqhwtucofnx8sa4

Grouping basisSingle unit
A single MaStR registration.
↑ Back to top

Operator / company changes (5)

Operator change
61Lead relevance · High

Why this ranks high. Large 50.4 MW multi-unit signal and 7 registrations moving together. Operator identity is unresolved, which reduces immediate actionability.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance61

  • Project scale (MW)20
  • Event type13
  • Lifecycle stage10
  • Recency7
  • Operator identified4
  • Multi-unit evidence7

Signal materiality41

  • Event type14
  • MW affected15
  • Units affected12

Registered operator changed on 7 wind units — 7 units / 50.4 MW

Vogelsberg, Thüringen · Operator: 2 registered operators (names not resolved)

7 units · 50.4 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 7 wind units, now registered to 2 different operators.

Several units moving from one registered operator to different registered operators may reflect project-company restructuring, for example separate operating entities per unit. That is worth checking against company records; the change alone does not establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Units with an operator change
7
Previous registered operator
BOREAS Energie GmbH
New registered operator
2 different registered operators (names not resolved in MaStR reference data; IDs under per-unit values)
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 7 registered MaStR units
Snapshot transition: 18 Sept 2026 → 19 Sept 2026
MaStR unit IDs: SEE957987437704, SEE985898386200, SEE910040688604, SEE993415826207, SEE979955065719, SEE944599970217, SEE938421090761
Commercial signals (7): cmua8mg8h0ew7wtucmapvay4l, cmua8mg8i0ewiwtuch9c2nt60, cmua8mg8i0ewpwtuckn52ttyz, cmua8mg8i0ewkwtucy5i5w4bc, cmua8mg8i0ewewtucyruu85gt, cmua8mg8i0ewlwtuc1tok3jbh, cmua8mg8h0ew5wtucufcsvk09

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Operator change
56Lead relevance · Moderate

Why this ranks here. Mid-sized 25.2 MW signal and 4 registrations moving together. Operator identity is unresolved, which reduces immediate actionability; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance56

  • Project scale (MW)16
  • Event type13
  • Lifecycle stage10
  • Recency7
  • Operator identified4
  • Multi-unit evidence6

Signal materiality36

  • Event type14
  • MW affected12
  • Units affected10

Registered operator changed on 4 wind units — 4 units / 25.2 MW

Harsewinkel, Nordrhein-Westfalen · Operator: Registered operator name not resolved

4 units · 25.2 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 4 wind units.

A registered operator change can be a useful trigger for investigating ownership, project restructuring, or a change in the commercial entity responsible for the asset. It does not by itself establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Units with an operator change
4
Previous registered operator
Alterric Deutschland GmbH
New registered operator
Operator ID ABR940869955595 (name not resolved)
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“harsewinkel…”); Same planned/commissioning date on every unit
Presentation group: 4 registered MaStR units
Snapshot transition: 17 Sept 2026 → 18 Sept 2026
MaStR unit IDs: SEE924661158088, SEE951157580276, SEE958712750662, SEE970708821767
Commercial signals (4): cmua8mg8g0evlwtucu6sezki4, cmua8mg8g0evwwtucb9tn8moo, cmua8mg8f0eutwtucq6zgmgf1, cmua8mg8f0ev6wtuccxr5z7li

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“harsewinkel…”); Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Operator change
48Lead relevance · Moderate

Why this ranks here. The registered operator is known. It affects only one 5.6 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance48

  • Project scale (MW)8
  • Event type13
  • Lifecycle stage10
  • Recency7
  • Operator identified10

Signal materiality21

  • Event type14
  • MW affected7

Registered operator changed on a wind unit — 5.6 MW

Kuhs, Mecklenburg-Vorpommern · Operator: WEB Windpark Kuhs GmbH & Co. KG

1 unit · 5.6 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 1 wind unit.

A registered operator change can be a useful trigger for investigating ownership, project restructuring, or a change in the commercial entity responsible for the asset. It does not by itself establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Previous registered operator
WEB Windenergie Deutschland GmbH
New registered operator
WEB Windpark Kuhs GmbH & Co. KG
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 17 Sept 2026 → 18 Sept 2026
MaStR unit IDs: SEE968763951574
Commercial signals (1): cmua8mg8f0ev5wtuc96zj3cc6

Grouping basisSingle unit
A single MaStR registration.
Operator change
40Lead relevance · Low

Why this ranks here. Operator identity is unresolved, which reduces immediate actionability; it affects only one 4.26 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance40

  • Project scale (MW)7
  • Event type13
  • Lifecycle stage10
  • Recency6
  • Operator identified4

Signal materiality20

  • Event type14
  • MW affected6

Registered operator changed on a wind unit — 4.26 MW

Bell (Hunsrück), Rheinland-Pfalz · Operator: Registered operator name not resolved

1 unit · 4.26 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 1 wind unit.

A registered operator change can be a useful trigger for investigating ownership, project restructuring, or a change in the commercial entity responsible for the asset. It does not by itself establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Previous registered operator
Höhenwind-Park GmbH
New registered operator
Operator ID ABR934711067314 (name not resolved)
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 14 Sept 2026 → 16 Sept 2026
MaStR unit IDs: SEE947944821547
Commercial signals (1): cmua8mg8a0ertwtucwhwf2p1u

Grouping basisSingle unit
A single MaStR registration.
Operator change
40Lead relevance · Low

Why this ranks here. Operator identity is unresolved, which reduces immediate actionability; it affects only one 4.26 MW unit; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance40

  • Project scale (MW)7
  • Event type13
  • Lifecycle stage10
  • Recency6
  • Operator identified4

Signal materiality20

  • Event type14
  • MW affected6

Registered operator changed on a wind unit — 4.26 MW

Hasselbach, Rheinland-Pfalz · Operator: Registered operator name not resolved

1 unit · 4.26 MW

Wind · Wind turbine (horizontal-axis)

The registered operator changed on 1 wind unit.

A registered operator change can be a useful trigger for investigating ownership, project restructuring, or a change in the commercial entity responsible for the asset. It does not by itself establish an acquisition or ownership transfer.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Asset transactionsFinancingDue diligenceDeveloper intelligence
Company registerSale / restructuring newsRelated entities?
Facts, hypotheses and how to verify
Previous registered operator
Höhenwind-Park GmbH
New registered operator
Operator ID ABR934711067314 (name not resolved)
  • Project development or development-management services
  • Asset or company transaction advisory and technical due diligence
  • Financing or refinancing discussions
  • Look up the new registered operator in the commercial register (Handelsregister)
  • Check whether the previous and new operators are related entities
  • Search for announcements of a sale, financing or restructuring
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 14 Sept 2026 → 16 Sept 2026
MaStR unit IDs: SEE988245136381
Commercial signals (1): cmua8mg8d0etewtuc26aqk58j

Grouping basisSingle unit
A single MaStR registration.
↑ Back to top

Recently commissioned assets (12)

Commissioned asset
49Lead relevance · Moderate

Why this ranks here. Mid-sized 28 MW signal, 4 registrations moving together and the registered operator is known. Already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance49

  • Project scale (MW)17
  • Event type6
  • Lifecycle stage3
  • Recency7
  • Operator identified10
  • Multi-unit evidence6

Signal materiality34

  • Event type12
  • MW affected12
  • Units affected10

4 wind units commissioned — 4 units / 28 MW

Werder, Mecklenburg-Vorpommern · Operator: mea Energieagentur Mecklenburg-Vorpommern GmbH

4 units · 28 MW

Wind · Wind turbine (horizontal-axis)

4 wind units (28 MW) moved from planned to commissioned status in MaStR, with registered commissioning dates between 27 Aug – 10 Sept 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Units commissioned
4
Total registered capacity
28 MW
Commissioned between
27 Aug – 10 Sept 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“passow…”); Identical registered capacity; Planned/commissioning dates within 14 days of each other
Presentation group: 4 registered MaStR units
Snapshot transition: 17 Sept 2026 → 18 Sept 2026
MaStR unit IDs: SEE979746367374, SEE929428218029, SEE930234352135, SEE987752894869
Commercial signals (4): cmua8mg8f0ev9wtucik3ttnrd, cmua8mg8g0evmwtucjel50fm4, cmua8mg8g0evnwtucsvvqe31i, cmua8mg8f0eupwtucbzbygozn

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“passow…”); Identical registered capacity; Planned/commissioning dates within 14 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Commissioned asset
46Lead relevance · Moderate

Why this ranks here. Mid-sized 22.8 MW signal, 4 registrations moving together and the registered operator is known. Already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance46

  • Project scale (MW)15
  • Event type6
  • Lifecycle stage3
  • Recency6
  • Operator identified10
  • Multi-unit evidence6

Signal materiality34

  • Event type12
  • MW affected12
  • Units affected10

4 wind units commissioned — 4 units / 22.8 MW

Seewald, Baden-Württemberg · Operator: Windpark Seewald GmbH & Co. KG

4 units · 22.8 MW

Wind · Wind turbine (horizontal-axis)

4 wind units (22.8 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 16 Sept 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Units commissioned
4
Total registered capacity
22.8 MW
Commissioning date
16 Sept 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Same planned/commissioning date on every unit
Presentation group: 4 registered MaStR units
Snapshot transition: 16 Sept 2026 → 17 Sept 2026
MaStR unit IDs: SEE941270408496, SEE955617440902, SEE932004115964, SEE947075407313
Commercial signals (4): cmua8mg8d0etuwtucoykeodyh, cmua8mg8d0ettwtucmdiyg5ec, cmua8mg8e0euiwtuc0hpdcom6, cmua8mg8e0eumwtucqwvw893z

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Commissioned asset
42Lead relevance · Low

Why this ranks here. 3 registrations moving together and the registered operator is known. Small combined capacity (12.6 MW); already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance42

  • Project scale (MW)12
  • Event type6
  • Lifecycle stage3
  • Recency6
  • Operator identified10
  • Multi-unit evidence5

Signal materiality29

  • Event type12
  • MW affected9
  • Units affected8

3 wind units commissioned — 3 units / 12.6 MW

Hommerdingen, Rheinland-Pfalz · Operator: Vattenfall Wind Hommerdingen GmbH & Co. KG

3 units · 12.6 MW

Wind · Wind turbine (horizontal-axis)

3 wind units (12.6 MW) moved from planned to commissioned status in MaStR, with registered commissioning dates between 07 Sept – 12 Sept 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Units commissioned
3
Total registered capacity
12.6 MW
Commissioned between
07 Sept – 12 Sept 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Identical registered capacity; Planned/commissioning dates within 5 days of each other
Presentation group: 3 registered MaStR units
Snapshot transition: 14 Sept 2026 → 16 Sept 2026
MaStR unit IDs: SEE996625002355, SEE965372586708, SEE970981650610
Commercial signals (3): cmua8mg8d0etmwtucockqtpok, cmua8mg8b0esewtuc4f6riqof, cmua8mg8b0esnwtucagfrea2r

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Planned/commissioning dates within 5 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Commissioned asset
41Lead relevance · Low

Why this ranks here. The registered operator is known. Small combined capacity (12 MW); already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance41

  • Project scale (MW)12
  • Event type6
  • Lifecycle stage3
  • Recency7
  • Operator identified10
  • Multi-unit evidence3

Signal materiality26

  • Event type12
  • MW affected9
  • Units affected5

2 wind units commissioned — 2 units / 12 MW

Weddelbrook, Schleswig-Holstein · Operator: Windpark Weddelbrook GmbH & Co. KG

2 units · 12 MW

Wind · Wind turbine (horizontal-axis)

2 wind units (12 MW) moved from planned to commissioned status in MaStR, with registered commissioning dates between 07 Sept – 09 Sept 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Units commissioned
2
Total registered capacity
12 MW
Commissioned between
07 Sept – 09 Sept 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Likely site group — Shared unit-name pattern (“weddelbrook…”); Identical registered capacity; Planned/commissioning dates within 2 days of each other
Presentation group: 2 registered MaStR units
Snapshot transition: 17 Sept 2026 → 18 Sept 2026
MaStR unit IDs: SEE917202841525, SEE965908785889
Commercial signals (2): cmua8mg8g0eviwtucl3ve6lyd, cmua8mg8f0ev2wtucknw0j9d9

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“weddelbrook…”); Identical registered capacity; Planned/commissioning dates within 2 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Commissioned asset
39Lead relevance · Low

Why this ranks here. The registered operator is known. Small combined capacity (13.2 MW); the grouping evidence is limited; already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance39

  • Project scale (MW)12
  • Event type6
  • Lifecycle stage3
  • Recency6
  • Operator identified10
  • Multi-unit evidence2

Signal materiality26

  • Event type12
  • MW affected9
  • Units affected5

2 wind units commissioned — 2 units / 13.2 MW

Bartow, Mecklenburg-Vorpommern · Operator: WB Energy Bartow 4 GmbH & Co. KG

2 units · 13.2 MW

Wind · Wind turbine (horizontal-axis)

2 wind units (13.2 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 11 Sept 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Units commissioned
2
Total registered capacity
13.2 MW
Commissioning date
11 Sept 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Conservative group — Same planned/commissioning date on every unit
Presentation group: 2 registered MaStR units
Snapshot transition: 14 Sept 2026 → 16 Sept 2026
MaStR unit IDs: SEE973918533093, SEE924355310488
Commercial signals (2): cmua8mg8c0estwtucj4m4mx54, cmua8mg890er3wtuctjs8mh0r

Grouping basisConservative group
Supporting registry evidence: Same planned/commissioning date on every unit
These registrations are grouped for presentation because they share location/operator/category characteristics. GridGraph does not assert that this grouping represents one canonical development project.
Commissioned asset
39Lead relevance · Low

Why this ranks here. Mid-sized 15 MW signal and the registered operator is known. Only one registered unit; already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance39

  • Project scale (MW)13
  • Event type6
  • Lifecycle stage3
  • Recency7
  • Operator identified10

Signal materiality22

  • Event type12
  • MW affected10

Wind unit commissioned — 15 MW — MaStR SEE956282536914

Ausschließliche Wirtschaftszone · Operator: EnBW He Dreiht GmbH & Co. KG

1 unit · 15 MW

Wind · Wind turbine (horizontal-axis)

1 wind unit (15 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 08 Sept 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Registered capacity
15 MW
Commissioning date
08 Sept 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 17 Sept 2026 → 18 Sept 2026
MaStR unit IDs: SEE956282536914
Commercial signals (1): cmua8mg8h0ew0wtuc6n5if2tj

Grouping basisSingle unit
Stable MaStR location ID: SEL907851722023
A single MaStR registration.
Commissioned asset
39Lead relevance · Low

Why this ranks here. Mid-sized 15 MW signal and the registered operator is known. Only one registered unit; already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance39

  • Project scale (MW)13
  • Event type6
  • Lifecycle stage3
  • Recency7
  • Operator identified10

Signal materiality22

  • Event type12
  • MW affected10

Wind unit commissioned — 15 MW — MaStR SEE977091784846

Ausschließliche Wirtschaftszone · Operator: EnBW He Dreiht GmbH & Co. KG

1 unit · 15 MW

Wind · Wind turbine (horizontal-axis)

1 wind unit (15 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 11 Sept 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Registered capacity
15 MW
Commissioning date
11 Sept 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 17 Sept 2026 → 18 Sept 2026
MaStR unit IDs: SEE977091784846
Commercial signals (1): cmua8mg8f0ev7wtucdd3kh9iq

Grouping basisSingle unit
Stable MaStR location ID: SEL924532254390
A single MaStR registration.
Commissioned asset
39Lead relevance · Low

Why this ranks here. Mid-sized 15 MW signal and the registered operator is known. Only one registered unit; already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance39

  • Project scale (MW)13
  • Event type6
  • Lifecycle stage3
  • Recency7
  • Operator identified10

Signal materiality22

  • Event type12
  • MW affected10

Wind unit commissioned — 15 MW — MaStR SEE959171440316

Ausschließliche Wirtschaftszone · Operator: EnBW He Dreiht GmbH & Co. KG

1 unit · 15 MW

Wind · Wind turbine (horizontal-axis)

1 wind unit (15 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 01 Sept 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Registered capacity
15 MW
Commissioning date
01 Sept 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 17 Sept 2026 → 18 Sept 2026
MaStR unit IDs: SEE959171440316
Commercial signals (1): cmua8mg8f0euuwtucnmj5rifa

Grouping basisSingle unit
Stable MaStR location ID: SEL944610363684
A single MaStR registration.
Commissioned asset
39Lead relevance · Low

Why this ranks here. Mid-sized 15 MW signal and the registered operator is known. Only one registered unit; already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance39

  • Project scale (MW)13
  • Event type6
  • Lifecycle stage3
  • Recency7
  • Operator identified10

Signal materiality22

  • Event type12
  • MW affected10

Wind unit commissioned — 15 MW — MaStR SEE980292520984

Ausschließliche Wirtschaftszone · Operator: EnBW He Dreiht GmbH & Co. KG

1 unit · 15 MW

Wind · Wind turbine (horizontal-axis)

1 wind unit (15 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 28 Aug 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Registered capacity
15 MW
Commissioning date
28 Aug 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 17 Sept 2026 → 18 Sept 2026
MaStR unit IDs: SEE980292520984
Commercial signals (1): cmua8mg8f0evawtucnfrccsld

Grouping basisSingle unit
Stable MaStR location ID: SEL962226038772
A single MaStR registration.
Commissioned asset
38Lead relevance · Low

Why this ranks here. Mid-sized 15 MW signal and the registered operator is known. Only one registered unit; already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance38

  • Project scale (MW)13
  • Event type6
  • Lifecycle stage3
  • Recency6
  • Operator identified10

Signal materiality22

  • Event type12
  • MW affected10

Wind unit commissioned — 15 MW — MaStR SEE934812516407

Ausschließliche Wirtschaftszone · Operator: Nordseecluster A GmbH & Co. KG

1 unit · 15 MW

Wind · Wind turbine (horizontal-axis)

1 wind unit (15 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 15 Sept 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Registered capacity
15 MW
Commissioning date
15 Sept 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 16 Sept 2026 → 17 Sept 2026
MaStR unit IDs: SEE934812516407
Commercial signals (1): cmua8mg8e0euawtucny7x7m5z

Grouping basisSingle unit
Stable MaStR location ID: SEL978257116990
A single MaStR registration.
Commissioned asset
34Lead relevance · Low

Why this ranks here. The registered operator is known. It affects only one 7.2 MW unit; already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance34

  • Project scale (MW)9
  • Event type6
  • Lifecycle stage3
  • Recency6
  • Operator identified10

Signal materiality19

  • Event type12
  • MW affected7

Wind unit commissioned — 7.2 MW — MaStR SEE948347059193

Bartow, Mecklenburg-Vorpommern · Operator: WB Energy Bartow 3 GmbH & Co. KG

1 unit · 7.2 MW

Wind · Wind turbine (horizontal-axis)

1 wind unit (7.2 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 11 Sept 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Registered capacity
7.2 MW
Commissioning date
11 Sept 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 14 Sept 2026 → 16 Sept 2026
MaStR unit IDs: SEE948347059193
Commercial signals (1): cmua8mg8a0eruwtuc66ur8hy6

Grouping basisSingle unit
Stable MaStR location ID: SEL902120953986
A single MaStR registration.
Commissioned asset
34Lead relevance · Low

Why this ranks here. The registered operator is known. It affects only one 7.2 MW unit; already commissioned, so it is weighted below early-stage signals; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance34

  • Project scale (MW)9
  • Event type6
  • Lifecycle stage3
  • Recency6
  • Operator identified10

Signal materiality19

  • Event type12
  • MW affected7

Wind unit commissioned — 7.2 MW — MaStR SEE967676871405

Bartow, Mecklenburg-Vorpommern · Operator: WB Energy Bartow 1 GmbH & Co. KG

1 unit · 7.2 MW

Wind · Wind turbine (horizontal-axis)

1 wind unit (7.2 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 11 Sept 2026.

Newly commissioned units move from planning into operation. Relevance may shift from build-phase to operating-phase services such as O&M or asset transactions; this registry change does not itself show any service need.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
O&M
MaStR recordOperating companyCommissioning news
Facts, hypotheses and how to verify
Registered capacity
7.2 MW
Commissioning date
11 Sept 2026
Lifecycle change
Planned → commissioned
  • Operations, maintenance and technical management services
  • Asset or company transaction advisory and technical due diligence
  • Confirm operating status and commissioning date in the official MaStR record
  • Identify the operating company and public information on service arrangements
  • Check for commissioning announcements
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 14 Sept 2026 → 16 Sept 2026
MaStR unit IDs: SEE967676871405
Commercial signals (1): cmua8mg8b0esjwtucj5lcqx4i

Grouping basisSingle unit
Stable MaStR location ID: SEL950431007089
A single MaStR registration.
↑ Back to top

Other registry changes (2)

Smaller registry changes, listed for completeness.

Schedule change
42Lead relevance · Low

Why this ranks here. The registered operator is known. It affects only one 7.2 MW unit; short date shifts are common registry maintenance; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance42

  • Project scale (MW)9
  • Event type4
  • Lifecycle stage10
  • Recency7
  • Operator identified10
  • Size of change2

Signal materiality29

  • Event type16
  • Size of change6
  • MW affected7

Commissioning delayed by 20 days — 7.2 MW

Borken, Nordrhein-Westfalen · Operator: Windenergie Schlatt GmbH & Co. KG

1 unit · 7.2 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 04 Sept 2026 → 24 Sept 2026 (+20 days)

The registered planned commissioning date moved by +20 days (04 Sept 2026 → 24 Sept 2026).

A short date shift is common and may be routine registry maintenance. Worth attention mainly if it is part of a wider pattern.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Planned commissioning
04 Sept 2026 → 24 Sept 2026 (+20 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 18 Sept 2026 → 19 Sept 2026
MaStR unit IDs: SEE915492311551
Commercial signals (1): cmua8mg8i0ewowtucc4omc9yx

Grouping basisSingle unit
A single MaStR registration.
Schedule change
40Lead relevance · Low

Why this ranks here. The registered operator is known. It affects only one 5.7 MW unit; short date shifts are common registry maintenance; no external evidence yet.

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance40

  • Project scale (MW)8
  • Event type4
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Size of change2

Signal materiality31

  • Event type16
  • Size of change8
  • MW affected7

Commissioning delayed by 29 days — 5.7 MW

Elsdorf, Nordrhein-Westfalen · Operator: Energiepark Elsdorf WP Frankeshoven GmbH & Co. KG

1 unit · 5.7 MW

Wind · Wind turbine (horizontal-axis)

Planned commissioning: 01 Sept 2026 → 30 Sept 2026 (+29 days)

The registered planned commissioning date moved by +29 days (01 Sept 2026 → 30 Sept 2026).

A short date shift is common and may be routine registry maintenance. Worth attention mainly if it is part of a wider pattern.

  • MaStR evidence: HIGH
  • Registry only · external search not performed
Project schedulingEngineeringConstruction timingSupplier timing
Registry correction?Permit & construction statusDeveloper updates
Facts, hypotheses and how to verify
Planned commissioning
01 Sept 2026 → 30 Sept 2026 (+29 days)
  • Project development or development-management services
  • Engineering and environmental services
  • Verify whether the date change reflects real rescheduling or a registry correction
  • Check permitting and construction status
  • Look for recent developer updates
Evidence and source lineage

MaStR evidence confidence: HIGH — strength of the MaStR evidence for the change itself, not of any commercial opportunity.
External verification: Not checked — no sources outside MaStR have been consulted.
Grouping: Single unit
Presentation group: 1 registered MaStR unit
Snapshot transition: 14 Sept 2026 → 16 Sept 2026
MaStR unit IDs: SEE956879758149
Commercial signals (1): cmua8mg8a0es1wtucetkq3ni2

Grouping basisSingle unit
A single MaStR registration.
↑ Back to top

Receive a filtered weekly brief for your market

Tell us which Bundesländer and technologies you care about and we'll follow up with a weekly brief scoped to that — not the full report.