66Lead relevance · High
Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Lead relevance66
- Project scale (MW)11
- Event type14
- Lifecycle stage10
- Recency7
- Operator identified10
- Multi-unit evidence3
- Several changes together5
- Size of change6
Signal materiality59
- Event type18
- Size of change22
- MW affected8
- Units affected5
- Several changes together6
Multiple registry changes (capacity + schedule) — 2 units / 10.5 MW
Nordwestuckermark, Brandenburg · Operator: MLK Brandenburg Windpark Entwicklungs GmbH & Co. KG
2 units · 10.5 MW
- MaStR evidence: HIGH
- Registry only · external search not performed
What changed
2 wind units registered a capacity change; combined registered capacity moved from 8.4 MW to 10.5 MW (+2.1 MW). 2 wind units registered a later planned commissioning date (+365 days).
Why this ranks high. Capacity and schedule changes recorded together on the same units and the registered operator is known. Small combined capacity (10.5 MW).
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Project development or development-management services
- Grid-connection / interconnection and electrical infrastructure services
- Engineering and environmental services
Verify next
- Check whether the change reflects a design or turbine-model change
- Verify whether the date change reflects real rescheduling or a registry correction
- Compare with permit and grid-connection documents
- Check permitting and construction status
- Look for recent developer announcements
- Look for recent developer updates
Change summary
- Units with a capacity change
- 2
- Per-unit change
- +0.6 MW to +1.5 MW
- Combined registered capacity now
- 10.5 MW
- Combined change
- +2.1 MW (+25%) — from 8.4 MW
- Units with a new planned date
- 2
- Planned commissioning (same for every unit)
- Dec 2026 → Dec 2027 (+365 days)
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (2)
SEE930756682567View official MaStR record ↗SEE965375636790View official MaStR record ↗
Grouping basis
Supporting registry evidence: Shared unit-name pattern (“mlk wp horst…”); Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Planung
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.
Snapshot transition
17 Sept 2026 → 18 Sept 2026