Timing change
High priority68

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Commissioning delayed for 3 registered wind units in Riepsdorf, Schleswig-Holstein

Riepsdorf, Schleswig-Holstein

Asset typeHorizontalläufer
Energy carrierWind
Registered operatorGosdorfer Windenergie GmbH & Co. KG
A later registered planned commissioning date may indicate asset delay or rescheduling.
Registered units
3
Asset type
Horizontalläufer
Energy carrier
Wind
Location
Riepsdorf, Schleswig-Holstein
Registered operator
Gosdorfer Windenergie GmbH & Co. KG
Operating status
In Planung
Planned commissioning
Sept 2026 → Oct 2027
Change
+395 days

GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.

Grouping basisConservative municipality/operator/category grouping
These registrations are grouped for presentation because they share location/operator/category characteristics. GridGraph does not assert that this grouping represents one canonical development project.

16 Sept 2026 → 17 Sept 2026