66Lead relevance · High
Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Lead relevance66
- Project scale (MW)17
- Event type12
- Lifecycle stage10
- Recency6
- Operator identified10
- Multi-unit evidence6
- Size of change5
Signal materiality60
- Event type16
- Size of change20
- MW affected13
- Units affected11
Commissioning delayed by up to 254 days — 5 units / 30 MW
Andervenne, Niedersachsen · Operator: Windpark Andervenne/Handrup GmbH & Co. KG
5 units · 30 MW
- MaStR evidence: HIGH
- Registry only · external search not performed
What changed
5 wind units registered a later planned commissioning date (+177 days to +254 days).
Why this ranks high. Mid-sized 30 MW signal, 5 registrations moving together, unusually large schedule shift (254 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Project development or development-management services
- Engineering and environmental services
Verify next
- Verify whether the date change reflects real rescheduling or a registry correction
- Check permitting and construction status
- Look for recent developer updates
Change summary
- Units with a new planned date
- 5
- Planned commissioning before
- 01 Jan 2028
- Planned commissioning now
- 26 Jun – 11 Sept 2028
- Shift per unit
- +177 to +254 days
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (5)
SEE993980427908View official MaStR record ↗SEE911227906214View official MaStR record ↗SEE907764600142View official MaStR record ↗SEE954827990450View official MaStR record ↗SEE910487618479View official MaStR record ↗
Grouping basis
Supporting registry evidence: Identical registered capacity; Planned/commissioning dates within 77 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Planung
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.
Snapshot transition
16 Sept 2026 → 17 Sept 2026