67Lead relevance · High
Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Lead relevance67
- Project scale (MW)17
- Event type12
- Lifecycle stage10
- Recency6
- Operator identified10
- Multi-unit evidence6
- Size of change6
Signal materiality60
- Event type16
- Size of change22
- MW affected12
- Units affected10
Commissioning delayed by up to 350 days — 4 units / 28 MW
Pfullendorf, Baden-Württemberg · Operator: ABO Energy Windpark Pfullendorf-Denkingen GmbH & Co. KG
4 units · 28 MW
- MaStR evidence: HIGH
- Registry only · external search not performed
What changed
4 wind units registered a later planned commissioning date (+350 days).
Why this ranks high. Mid-sized 28 MW signal, 4 registrations moving together, unusually large schedule shift (350 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Project development or development-management services
- Engineering and environmental services
Verify next
- Verify whether the date change reflects real rescheduling or a registry correction
- Check permitting and construction status
- Look for recent developer updates
Change summary
- Units with a new planned date
- 4
- Planned commissioning (same for every unit)
- Sept 2026 → Aug 2027 (+350 days)
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (4)
SEE967662403658View official MaStR record ↗SEE946691682654View official MaStR record ↗SEE991405743596View official MaStR record ↗SEE981599845879View official MaStR record ↗
Grouping basis
Supporting registry evidence: Shared unit-name pattern (“wp pfullendorf…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Planung
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.
Snapshot transition
14 Sept 2026 → 16 Sept 2026