78Lead relevance · Very high
Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Lead relevance78
- Project scale (MW)23
- Event type12
- Lifecycle stage10
- Recency8
- Operator identified10
- Multi-unit evidence9
- Size of change6
Signal materiality73
- Event type16
- Size of change24
- MW affected18
- Units affected15
Commissioning delayed by up to 518 days — 13 units / 91 MW
Zerbst/Anhalt, Sachsen-Anhalt · Operator: Windpark Packendorfer Teich GmbH & Co. KG
13 units · 91 MW
- MaStR evidence: HIGH
- Registry only · external search not performed
What changed
13 wind units registered a later planned commissioning date (+518 days).
Why this ranks high. Large 91 MW multi-unit signal, 13 registrations moving together, unusually large schedule shift (518 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Project development or development-management services
- Engineering and environmental services
Verify next
- Verify whether the date change reflects real rescheduling or a registry correction
- Check permitting and construction status
- Look for recent developer updates
Change summary
- Units with a new planned date
- 13
- Planned commissioning (same for every unit)
- Dec 2026 → Jun 2028 (+518 days)
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (13)
SEE909646504302View official MaStR record ↗SEE927898740927View official MaStR record ↗SEE928440590182View official MaStR record ↗SEE931230328049View official MaStR record ↗SEE931320565200View official MaStR record ↗SEE955774817371View official MaStR record ↗SEE968796931451View official MaStR record ↗SEE969527234735View official MaStR record ↗SEE970308949052View official MaStR record ↗SEE974463276114View official MaStR record ↗SEE978092683718View official MaStR record ↗SEE985046872029View official MaStR record ↗SEE987879268604View official MaStR record ↗
Grouping basis
Supporting registry evidence: Shared unit-name pattern (“paken wea…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Planung
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.
Snapshot transition
23 Oct 2026 → 24 Oct 2026