Schedule change
78Lead relevance · Very high

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance78

  • Project scale (MW)23
  • Event type12
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Multi-unit evidence9
  • Size of change6

Signal materiality73

  • Event type16
  • Size of change24
  • MW affected18
  • Units affected15

Commissioning delayed by up to 518 days — 13 units / 91 MW

Zerbst/Anhalt, Sachsen-Anhalt · Operator: Windpark Packendorfer Teich GmbH & Co. KG

13 units · 91 MW

Asset typeHorizontalläufer
Energy carrierWind
Registered operatorWindpark Packendorfer Teich GmbH & Co. KG

13 wind units registered a later planned commissioning date (+518 days).

Why this ranks high. Large 91 MW multi-unit signal, 13 registrations moving together, unusually large schedule shift (518 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.

A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.
Developer servicesEngineeringMarket intelligence

Investigation hypotheses only. They are not evidence that any of these needs currently exist.

Units with a new planned date
13
Planned commissioning (same for every unit)
Dec 2026 → Jun 2028 (+518 days)

GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“paken wea…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Asset type (MaStR)
Horizontalläufer
Energy carrier (MaStR)
Wind
Operating status (MaStR)
In Planung

MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.

Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.

23 Oct 2026 → 24 Oct 2026

← Back to the brief · 2026-10-24