78Lead relevance · Very high
Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Lead relevance78
- Project scale (MW)25
- Event type12
- Lifecycle stage10
- Recency8
- Operator identified10
- Multi-unit evidence9
- Size of change4
Signal materiality65
- Event type16
- Size of change14
- MW affected20
- Units affected15
Commissioning delayed by up to 97 days — 27 units / 405 MW
Ausschließliche Wirtschaftszone · Operator: Nordseecluster A GmbH & Co. KG
27 units · 405 MW
- MaStR evidence: HIGH
- Registry only · external search not performed
What changed
27 wind units registered a later planned commissioning date (+36 days to +97 days).
Why this ranks high. Large 405 MW multi-unit signal, 27 registrations moving together and the registered operator is known.
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Project development or development-management services
- Engineering and environmental services
Verify next
- Verify whether the date change reflects real rescheduling or a registry correction
- Check permitting and construction status
- Look for recent developer updates
Change summary
- Units with a new planned date
- 27
- Planned commissioning before
- 25 Sept 2026
- Planned commissioning now
- 31 Oct – 31 Dec 2026
- Shift per unit
- +36 to +97 days
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (27)
SEE900513297235View official MaStR record ↗SEE902663504331View official MaStR record ↗SEE906006978216View official MaStR record ↗SEE909382805954View official MaStR record ↗SEE910064003308View official MaStR record ↗SEE912766297955View official MaStR record ↗SEE914229395819View official MaStR record ↗SEE920019158410View official MaStR record ↗SEE920824374135View official MaStR record ↗SEE924000723038View official MaStR record ↗SEE939755406938View official MaStR record ↗SEE949339640498View official MaStR record ↗SEE952197771259View official MaStR record ↗SEE958300498112View official MaStR record ↗SEE958327266701View official MaStR record ↗SEE961975761351View official MaStR record ↗SEE964309087554View official MaStR record ↗SEE965247303478View official MaStR record ↗SEE967113701593View official MaStR record ↗SEE971714837612View official MaStR record ↗SEE973119472863View official MaStR record ↗SEE976669730117View official MaStR record ↗SEE989188540167View official MaStR record ↗SEE993505953028View official MaStR record ↗SEE994396655169View official MaStR record ↗SEE998932559942View official MaStR record ↗SEE999304048637View official MaStR record ↗
Grouping basis
Supporting registry evidence: Identical registered capacity; Planned/commissioning dates within 61 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Planung
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.
Snapshot transition
28 Oct 2026 → 3 Nov 2026