67Lead relevance · High
Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Lead relevance67
- Project scale (MW)18
- Event type12
- Lifecycle stage10
- Recency7
- Operator identified10
- Multi-unit evidence6
- Size of change4
Signal materiality55
- Event type16
- Size of change14
- MW affected14
- Units affected11
Commissioning delayed by up to 92 days — 5 units / 36 MW
Plettenberg, Nordrhein-Westfalen · Operator: P-Wind Plettenberg GmbH
5 units · 36 MW
- MaStR evidence: HIGH
- Registry only · external search not performed
What changed
5 wind units registered a later planned commissioning date (+92 days).
Why this ranks high. Mid-sized 36 MW signal, 5 registrations moving together and the registered operator is known.
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Project development or development-management services
- Engineering and environmental services
Verify next
- Verify whether the date change reflects real rescheduling or a registry correction
- Check permitting and construction status
- Look for recent developer updates
Change summary
- Units with a new planned date
- 5
- Planned commissioning (same for every unit)
- Oct 2026 → Jan 2027 (+92 days)
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (5)
SEE992971035214View official MaStR record ↗SEE958240705868View official MaStR record ↗SEE976515000425View official MaStR record ↗SEE925886507651View official MaStR record ↗SEE976829942756View official MaStR record ↗
Grouping basis
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Planung
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.
Snapshot transition
15 Oct 2026 → 17 Oct 2026