Schedule change
65Lead relevance · High

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance65

  • Project scale (MW)18
  • Event type12
  • Lifecycle stage10
  • Recency6
  • Operator identified10
  • Multi-unit evidence4
  • Size of change5

Signal materiality60

  • Event type16
  • Size of change18
  • MW affected14
  • Units affected12

Commissioning rescheduled — 6 units / 36 MW

Brakel, Nordrhein-Westfalen · Operator: Windpark Brakel Modexen GmbH & Co. KG

6 units · 36 MW

Asset typeHorizontalläufer
Energy carrierWind
Registered operatorWindpark Brakel Modexen GmbH & Co. KG

6 wind units registered a changed planned commissioning date (-106 days to +184 days).

Why this ranks high. Mid-sized 36 MW signal, unusually large schedule shift (184 days) and the registered operator is known. The grouping evidence is limited; it may still reflect a registry correction rather than a new commercial need.

A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.
Developer servicesEngineeringMarket intelligence

Investigation hypotheses only. They are not evidence that any of these needs currently exist.

Units with a new planned date
6
Planned commissioning before
30 Jun 2026 – 02 Oct 2028
Planned commissioning now
31 Dec 2026 – 18 Jun 2028
Shift per unit
-106 to +184 days
Direction
1 later, 5 earlier

GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.

Grouping basisConservative group
Supporting registry evidence: Identical registered capacity
These registrations are grouped for presentation because they share location/operator/category characteristics. GridGraph does not assert that this grouping represents one canonical development project.
Asset type (MaStR)
Horizontalläufer
Energy carrier (MaStR)
Wind
Operating status (MaStR)
In Planung

MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.

Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.

6 Oct 2026 → 15 Oct 2026