54Lead relevance · Moderate
Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Lead relevance54
- Project scale (MW)13
- Event type8
- Lifecycle stage10
- Recency8
- Operator identified10
- Multi-unit evidence3
- Size of change2
Signal materiality40
- Event type16
- Size of change9
- MW affected10
- Units affected5
Commissioning delayed by up to 35 days — 2 units / 14.4 MW
Erkelenz, Nordrhein-Westfalen · Operator: MLK Windpark Holzweiler Nr. 100 GmbH & Co. KG
2 units · 14.4 MW
- MaStR evidence: HIGH
- Registry only · external search not performed
What changed
2 wind units registered a later planned commissioning date (+23 days to +35 days).
Why this ranks here. Mid-sized 14.4 MW signal and the registered operator is known. No external evidence yet.
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Project development or development-management services
- Engineering and environmental services
Verify next
- Verify whether the date change reflects real rescheduling or a registry correction
- Check permitting and construction status
- Look for recent developer updates
Change summary
- Units with a new planned date
- 2
- Planned commissioning before
- 08 Sept 2026
- Planned commissioning now
- 01 Oct – 13 Oct 2026
- Shift per unit
- +23 to +35 days
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (2)
SEE950340927294View official MaStR record ↗SEE960303446205View official MaStR record ↗
Grouping basis
Supporting registry evidence: Identical registered capacity; Planned/commissioning dates within 12 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Planung
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.
Snapshot transition
22 Sept 2026 → 23 Sept 2026