Capacity change
56Lead relevance · Moderate

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance56

  • Project scale (MW)9
  • Event type14
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Size of change5

Signal materiality45

  • Event type18
  • Size of change20
  • MW affected7

Registered wind capacity increased (+2.74 MW) — 7 MW

Hattgenstein, Rheinland-Pfalz · Operator: GERES Power III GmbH

1 unit · 7 MW

Asset typeHorizontalläufer
Energy carrierWind
Registered operatorGERES Power III GmbH

Registered capacity changed from 4.26 MW to 7 MW (+2.74 MW, +64%).

Why this ranks here. The registered operator is known. It affects only one 7 MW unit; no external evidence yet.

A larger registered capacity may indicate a changed project design, turbine or equipment choice, or grid-connection scope, and could affect engineering and equipment requirements.
Developer servicesGrid & electricalEngineering

Investigation hypotheses only. They are not evidence that any of these needs currently exist.

Registered capacity
4.26 MW → 7 MW (+2.74 MW / +64%)

GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.

Grouping basisSingle unit
A single MaStR registration.
Asset type (MaStR)
Horizontalläufer
Energy carrier (MaStR)
Wind
Operating status (MaStR)
In Planung

MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.

Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.

25 Sept 2026 → 28 Sept 2026