62Lead relevance · High
Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Lead relevance62
- Project scale (MW)12
- Event type20
- Lifecycle stage10
- Recency8
- Operator identified10
- Multi-unit evidence2
Signal materiality34
- Event type20
- MW affected9
- Units affected5
New planned wind units — 2 units / 13.2 MW
Greußen, Thüringen · Operator: BOREAS Energie GmbH
2 planned units · 13.2 MW · First observed 28 Sept 2026
- MaStR evidence: HIGH
- Registry only · external search not performed
What changed
2 new planned wind units totalling 13.2 MW were first observed in this MaStR snapshot.
Why this ranks high. Freshly registered planned asset and the registered operator is known. Small combined capacity (13.2 MW); the grouping evidence is limited.
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Project development or development-management services
- Grid-connection / interconnection and electrical infrastructure services
- Engineering and environmental services
- Civil works and balance-of-plant
- Turbine-related services (supply, transport, installation, service)
Verify next
- Identify the developer or project company
- Check planning and permitting status
- Search municipal planning documents
- Search recent company announcements
- Search tenders and procurement notices
- Verify whether construction or supplier selection has started
Change summary
- Planned units first observed
- 2
- Total registered capacity
- 13.2 MW
- Capacity per unit
- 6–7.2 MW per unit
- First observed in MaStR snapshot
- 28 Sept 2026
- Planned commissioning
- 31 Dec 2028
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (2)
SEE988229123277View official MaStR record ↗SEE950092867503View official MaStR record ↗
Grouping basis
Supporting registry evidence: Same planned/commissioning date on every unit
These registrations are grouped for presentation because they share location/operator/category characteristics. GridGraph does not assert that this grouping represents one canonical development project.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Planung
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.
Snapshot transition
First tracked snapshot → 28 Sept 2026