66Lead relevance · High
Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Lead relevance66
- Project scale (MW)15
- Event type12
- Lifecycle stage10
- Recency8
- Operator identified10
- Multi-unit evidence6
- Size of change5
Signal materiality56
- Event type16
- Size of change19
- MW affected11
- Units affected10
Commissioning delayed by up to 198 days — 4 units / 22.24 MW
Heringen (Werra), Hessen · Operator: Windpark GmbH & Co. Heringen-Monte Kali KG
4 units · 22.24 MW
- MaStR evidence: HIGH
- Registry only · external search not performed
What changed
4 wind units registered a later planned commissioning date (+135 days to +198 days).
Why this ranks high. Mid-sized 22.24 MW signal, 4 registrations moving together, unusually large schedule shift (198 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Project development or development-management services
- Engineering and environmental services
Verify next
- Verify whether the date change reflects real rescheduling or a registry correction
- Check permitting and construction status
- Look for recent developer updates
Change summary
- Units with a new planned date
- 4
- Planned commissioning before
- 01 Oct 2026
- Planned commissioning now
- 13 Feb – 17 Apr 2027
- Shift per unit
- +135 to +198 days
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (4)
SEE991003107165View official MaStR record ↗SEE924310371240View official MaStR record ↗SEE963024883984View official MaStR record ↗SEE968003070737View official MaStR record ↗
Grouping basis
Supporting registry evidence: Shared unit-name pattern (“wp gaishecke ii wea…”); Identical registered capacity; Planned/commissioning dates within 63 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Planung
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.
Snapshot transition
30 Sept 2026 → 1 Oct 2026