Multiple registry changes (schedule + operator) — 4 units / 22.24 MW
Sömmerda, Thüringen · Operator: Operator ID ABR905693656667 (name not resolved)
4 units · 22.24 MW
- MaStR evidence: HIGH
- Registry only · external search not performed
What changed
4 wind units registered a later planned commissioning date (+238 days to +320 days). The registered operator changed on 4 wind units.
Why this ranks high. Mid-sized 22.24 MW signal, 4 registrations moving together, schedule and operator changes recorded together on the same units and unusually large schedule shift (320 days). Operator identity is unresolved, which reduces immediate actionability; it may still reflect a registry correction rather than a new commercial need.
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Project development or development-management services
- Engineering and environmental services
- Asset or company transaction advisory and technical due diligence
- Financing or refinancing discussions
Verify next
- Verify whether the date change reflects real rescheduling or a registry correction
- Look up the new registered operator in the commercial register (Handelsregister)
- Check permitting and construction status
- Check whether the previous and new operators are related entities
- Look for recent developer updates
- Search for announcements of a sale, financing or restructuring
Change summary
- Units with a new planned date
- 4
- Planned commissioning before
- 01 Apr 2026
- Planned commissioning now
- 25 Nov 2026 – 15 Feb 2027
- Shift per unit
- +238 to +320 days
- Units with an operator change
- 4
- Previous registered operator
- Energiequelle GmbH
- New registered operator
- Operator ID ABR905693656667 (name not resolved)
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (4)
SEE924401845049View official MaStR record ↗SEE964769476066View official MaStR record ↗SEE926090628903View official MaStR record ↗SEE953783680832View official MaStR record ↗
Grouping basis
Supporting registry evidence: Shared unit-name pattern (“wp sömmerda…”); Identical registered capacity; Planned/commissioning dates within 82 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Planung
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.
Snapshot transition
30 Sept 2026 → 1 Oct 2026