80Lead relevance · Very high
Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Lead relevance80
- Project scale (MW)23
- Event type20
- Lifecycle stage10
- Recency8
- Operator identified10
- Multi-unit evidence9
Signal materiality53
- Event type20
- MW affected18
- Units affected15
New planned wind development signal — 15 units / 90 MW
Wedemark, Niedersachsen · Operator: enercity Erneuerbare Projekte GmbH & Co. KG
15 planned units · 90 MW · First observed 05 Oct 2026
- MaStR evidence: HIGH
- Registry only · external search not performed
What changed
15 new planned wind units totalling 90 MW were first observed in this MaStR snapshot.
Why this ranks high. Large 90 MW multi-unit signal, 15 registrations moving together, freshly registered planned asset and the registered operator is known.
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Project development or development-management services
- Grid-connection / interconnection and electrical infrastructure services
- Engineering and environmental services
- Civil works and balance-of-plant
- Turbine-related services (supply, transport, installation, service)
Verify next
- Identify the developer or project company
- Check planning and permitting status
- Search municipal planning documents
- Search recent company announcements
- Search tenders and procurement notices
- Verify whether construction or supplier selection has started
Change summary
- Planned units first observed
- 15
- Total registered capacity
- 90 MW
- Capacity per unit
- 6 MW each
- First observed in MaStR snapshot
- 05 Oct 2026
- Planned commissioning
- 31 Mar 2029
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (15)
SEE923204127666View official MaStR record ↗SEE925495710510View official MaStR record ↗SEE929685830927View official MaStR record ↗SEE933695925719View official MaStR record ↗SEE944728701927View official MaStR record ↗SEE984735409928View official MaStR record ↗SEE986137951142View official MaStR record ↗SEE990224736680View official MaStR record ↗SEE990607072633View official MaStR record ↗SEE992996000013View official MaStR record ↗SEE961214323166View official MaStR record ↗SEE967149497125View official MaStR record ↗SEE969928819470View official MaStR record ↗SEE971781082830View official MaStR record ↗SEE973642474112View official MaStR record ↗
Grouping basis
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Planung
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.
Snapshot transition
First tracked snapshot → 5 Oct 2026