64Lead relevance · High
Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Lead relevance64
- Project scale (MW)12
- Event type14
- Lifecycle stage10
- Recency8
- Operator identified10
- Multi-unit evidence3
- Several changes together5
- Size of change2
Signal materiality47
- Event type18
- Size of change9
- MW affected9
- Units affected5
- Several changes together6
Multiple registry changes (capacity + operator) — 2 units / 12.4 MW
Schladen-Werla, Niedersachsen · Operator: Bürgerwindpark Beuchte Planungsgesellschaft mbH & Co. KG
2 units · 12.4 MW
- MaStR evidence: HIGH
- Registry only · external search not performed
What changed
2 wind units registered a capacity change; combined registered capacity moved from 14.4 MW to 12.4 MW (-2 MW). The registered operator changed on 1 wind unit.
Why this ranks high. Capacity and operator changes recorded together on the same units and the registered operator is known. Small combined capacity (12.4 MW).
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Project development or development-management services
- Grid-connection / interconnection and electrical infrastructure services
- Engineering and environmental services
- Asset or company transaction advisory and technical due diligence
- Financing or refinancing discussions
Verify next
- Check whether the change reflects a design or turbine-model change
- Look up the new registered operator in the commercial register (Handelsregister)
- Compare with permit and grid-connection documents
- Check whether the previous and new operators are related entities
- Look for recent developer announcements
- Search for announcements of a sale, financing or restructuring
Change summary
- Per-unit change
- 2 units changed from 7.2 MW to 6.2 MW each
- Combined registered capacity now
- 12.4 MW
- Combined change
- -2 MW (-14%)
- Previous registered operator
- Bürgerwind Beuchte WEA 11 powered by Ebert GmbH & Co. KG
- New registered operator
- Bürgerwindpark Beuchte Planungsgesellschaft mbH & Co. KG
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (2)
SEE968764666774View official MaStR record ↗SEE996187172190View official MaStR record ↗
Grouping basis
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Planned/commissioning dates within 31 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Planung
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.
Snapshot transition
5 Oct 2026 → 6 Oct 2026