61Lead relevance · High
Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Lead relevance61
- Project scale (MW)16
- Event type8
- Lifecycle stage10
- Recency8
- Operator identified10
- Multi-unit evidence6
- Size of change3
Signal materiality49
- Event type16
- Size of change11
- MW affected12
- Units affected10
Commissioning delayed by up to 52 days — 4 units / 27.2 MW
Meyenburg, Brandenburg · Operator: KWE Windpark Meyenburg Zwei GmbH & Co. KG
4 units · 27.2 MW
- MaStR evidence: HIGH
- Registry only · external search not performed
What changed
4 wind units registered a later planned commissioning date (+9 days to +52 days).
Why this ranks high. Mid-sized 27.2 MW signal, 4 registrations moving together and the registered operator is known.
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Project development or development-management services
- Engineering and environmental services
Verify next
- Verify whether the date change reflects real rescheduling or a registry correction
- Check permitting and construction status
- Look for recent developer updates
Change summary
- Units with a new planned date
- 4
- Planned commissioning before
- 24 Sept – 02 Dec 2026
- Planned commissioning now
- 15 Oct – 31 Dec 2026
- Shift per unit
- +9 to +52 days
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (4)
SEE907165464749View official MaStR record ↗SEE944425963253View official MaStR record ↗SEE993341144499View official MaStR record ↗SEE990837459846View official MaStR record ↗
Grouping basis
Supporting registry evidence: Identical registered capacity; Planned/commissioning dates within 77 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Planung
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.
Snapshot transition
6 Oct 2026 → 15 Oct 2026