Schedule change
61Lead relevance · High

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance61

  • Project scale (MW)16
  • Event type8
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Multi-unit evidence6
  • Size of change3

Signal materiality49

  • Event type16
  • Size of change11
  • MW affected12
  • Units affected10

Commissioning delayed by up to 52 days — 4 units / 27.2 MW

Meyenburg, Brandenburg · Operator: KWE Windpark Meyenburg Zwei GmbH & Co. KG

4 units · 27.2 MW

Asset typeHorizontalläufer
Energy carrierWind
Registered operatorKWE Windpark Meyenburg Zwei GmbH & Co. KG

4 wind units registered a later planned commissioning date (+9 days to +52 days).

Why this ranks high. Mid-sized 27.2 MW signal, 4 registrations moving together and the registered operator is known.

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.
Developer servicesEngineeringMarket intelligence

Investigation hypotheses only. They are not evidence that any of these needs currently exist.

Units with a new planned date
4
Planned commissioning before
24 Sept – 02 Dec 2026
Planned commissioning now
15 Oct – 31 Dec 2026
Shift per unit
+9 to +52 days

GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Planned/commissioning dates within 77 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Asset type (MaStR)
Horizontalläufer
Energy carrier (MaStR)
Wind
Operating status (MaStR)
In Planung

MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.

Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.

6 Oct 2026 → 15 Oct 2026