Schedule change
58Lead relevance · Moderate

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance58

  • Project scale (MW)8
  • Event type12
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Multi-unit evidence5
  • Size of change5

Signal materiality51

  • Event type16
  • Size of change21
  • MW affected6
  • Units affected8

Commissioning delayed by up to 334 days — 3 units / 5.55 MW

Niederer Fläming, Brandenburg · Operator: BEC - Energie Consult GmbH

3 units · 5.55 MW

Asset typeHorizontalläufer
Energy carrierWind
Registered operatorBEC - Energie Consult GmbH

3 wind units registered a later planned commissioning date (+275 days to +334 days).

Why this ranks here. 3 registrations moving together, unusually large schedule shift (334 days) and the registered operator is known. Small combined capacity (5.55 MW); it may still reflect a registry correction rather than a new commercial need; no external evidence yet.

A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.
Developer servicesEngineeringMarket intelligence

Investigation hypotheses only. They are not evidence that any of these needs currently exist.

Units with a new planned date
3
Planned commissioning before
31 Jan – 31 Mar 2027
Planned commissioning now
31 Dec 2027
Shift per unit
+275 to +334 days

GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Asset type (MaStR)
Horizontalläufer
Energy carrier (MaStR)
Wind
Operating status (MaStR)
In Planung

MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.

Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.

26 Oct 2026 → 27 Oct 2026