59Lead relevance · Moderate
Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Lead relevance59
- Project scale (MW)11
- Event type12
- Lifecycle stage10
- Recency8
- Operator identified10
- Multi-unit evidence2
- Size of change6
Signal materiality53
- Event type16
- Size of change24
- MW affected8
- Units affected5
Commissioning delayed by up to 568 days — 2 units / 10.5 MW
Angermünde, Brandenburg · Operator: Windkraft Neukünkendorf GmbH & Co. KG
2 units · 10.5 MW
- MaStR evidence: HIGH
- Registry only · external search not performed
What changed
2 wind units registered a later planned commissioning date (+376 days to +568 days).
Why this ranks here. Unusually large schedule shift (568 days) and the registered operator is known. Small combined capacity (10.5 MW); the grouping evidence is limited; it may still reflect a registry correction rather than a new commercial need; no external evidence yet.
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Project development or development-management services
- Engineering and environmental services
Verify next
- Verify whether the date change reflects real rescheduling or a registry correction
- Check permitting and construction status
- Look for recent developer updates
Change summary
- Units with a new planned date
- 2
- Planned commissioning before
- 31 Aug 2026 – 11 Mar 2027
- Planned commissioning now
- 21 Mar 2028
- Shift per unit
- +376 to +568 days
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (2)
SEE986471147065View official MaStR record ↗SEE996392045579View official MaStR record ↗
Grouping basis
Supporting registry evidence: Same planned/commissioning date on every unit
These registrations are grouped for presentation because they share location/operator/category characteristics. GridGraph does not assert that this grouping represents one canonical development project.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Planung
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.
Snapshot transition
22 Sept 2026 → 23 Sept 2026