Schedule change
53Lead relevance · Moderate

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance53

  • Project scale (MW)6
  • Event type12
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Size of change7

Signal materiality49

  • Event type16
  • Size of change27
  • MW affected6

Commissioning delayed by 1676 days — 4.2 MW

Ahrensfelde, Brandenburg · Operator: VS Ventor WEA3 Energiegenossenschaft eG

1 unit · 4.2 MW

Asset typeHorizontalläufer
Energy carrierWind
Registered operatorVS Ventor WEA3 Energiegenossenschaft eG

The registered planned commissioning date moved by +1676 days (Mar 2023 → Nov 2027).

Why this ranks here. Unusually large schedule shift (1676 days) and the registered operator is known. It affects only one 4.2 MW unit; it may still reflect a registry correction rather than a new commercial need; no external evidence yet.

A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.
Developer servicesEngineeringMarket intelligence

Investigation hypotheses only. They are not evidence that any of these needs currently exist.

Planned commissioning
Mar 2023 → Nov 2027 (+1676 days)

GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.

Grouping basisSingle unit
A single MaStR registration.
Asset type (MaStR)
Horizontalläufer
Energy carrier (MaStR)
Wind
Operating status (MaStR)
In Planung

MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.

Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.

22 Sept 2026 → 23 Sept 2026

← Back to the brief · 2026-09-23