Capacity change
Low priority40
This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.
What this score is built from
- Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
- Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
- Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.
Registered capacity changed for Horizontalläufer in Hingstheide, Schleswig-Holstein
Hingstheide, Schleswig-Holstein
Asset typeHorizontalläufer
Energy carrierWind
Registered operatorJUWI GmbH
Commercial interpretation
A material capacity increase indicates a larger registered asset capacity than in the previous snapshot.
Change summary
- Combined registered capacity across grouped units
- 13.6 MW
- Registered units
- 2
- Asset type
- Horizontalläufer
- Energy carrier
- Wind
- Location
- Hingstheide, Schleswig-Holstein
- Registered operator
- JUWI GmbH
- Operating status
- In Planung
- Registered capacity
- 5.7 MW → 6.8 MW
- Change
- +1.1 MW
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (2)
SEE956455379027View official MaStR record ↗SEE949616875230View official MaStR record ↗
Grouping basis
Grouping basisConservative municipality/operator/category grouping
These registrations are grouped for presentation because they share location/operator/category characteristics. GridGraph does not assert that this grouping represents one canonical development project.
These registrations are grouped for presentation because they share location/operator/category characteristics. GridGraph does not assert that this grouping represents one canonical development project.
Snapshot transition
22 Sept 2026 → 23 Sept 2026