Schedule change
61Lead relevance · High

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance61

  • Project scale (MW)16
  • Event type8
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Multi-unit evidence6
  • Size of change3

Signal materiality51

  • Event type16
  • Size of change13
  • MW affected12
  • Units affected10

Commissioning delayed by up to 70 days — 4 units / 24 MW

Wilnsdorf, Nordrhein-Westfalen · Operator: MVV Windenergie GmbH

4 units · 24 MW

Asset typeHorizontalläufer
Energy carrierWind
Registered operatorMVV Windenergie GmbH

4 wind units registered a later planned commissioning date (+36 days to +70 days).

Why this ranks high. Mid-sized 24 MW signal, 4 registrations moving together and the registered operator is known.

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.
Developer servicesEngineeringMarket intelligence

Investigation hypotheses only. They are not evidence that any of these needs currently exist.

Units with a new planned date
4
Planned commissioning before
14 Sept 2026
Planned commissioning now
20 Oct – 23 Nov 2026
Shift per unit
+36 to +70 days

GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.

Grouping basisLikely site group
Supporting registry evidence: Shared unit-name pattern (“wilnsdorf…”); Identical registered capacity; Planned/commissioning dates within 34 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Asset type (MaStR)
Horizontalläufer
Energy carrier (MaStR)
Wind
Operating status (MaStR)
In Planung

MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.

Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.

28 Sept 2026 → 29 Sept 2026

← Back to the brief · 2026-09-29