Commissioning delayed by up to 228 days — 3 units / 21 MW
Sien, Rheinland-Pfalz · Operator: Windpark Sien II GmbH & Co. KG
3 units · 21 MW
- MaStR evidence: HIGH
- Registry only · external search not performed
What changed
3 wind units registered a later planned commissioning date (+228 days).
Why this ranks high. Mid-sized 21 MW signal, 3 registrations moving together, unusually large schedule shift (228 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Project development or development-management services
- Engineering and environmental services
Verify next
- Verify whether the date change reflects real rescheduling or a registry correction
- Check permitting and construction status
- Look for recent developer updates
Change summary
- Units with a new planned date
- 3
- Planned commissioning (same for every unit)
- Oct 2027 → Jun 2028 (+228 days)
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (3)
SEE967686694414View official MaStR record ↗SEE936438285750View official MaStR record ↗SEE911740317993View official MaStR record ↗
Grouping basis
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Planung
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.