Schedule change
70Lead relevance · High

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance70

  • Project scale (MW)20
  • Event type12
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Multi-unit evidence4
  • Size of change6

Signal materiality66

  • Event type16
  • Size of change22
  • MW affected15
  • Units affected13

Commissioning delayed by up to 405 days — 8 units / 55.4 MW

Rhede, Nordrhein-Westfalen · Operator: Bürgerwind Büngern GmbH & Co. KG

8 units · 55.4 MW

Asset typeHorizontalläufer
Energy carrierWind
Registered operatorBürgerwind Büngern GmbH & Co. KG

8 wind units registered a later planned commissioning date (+265 days to +405 days).

Why this ranks high. Large 55.4 MW multi-unit signal, unusually large schedule shift (405 days) and the registered operator is known. The grouping evidence is limited; it may still reflect a registry correction rather than a new commercial need.

A material schedule shift may indicate a change in project timing and could alter when supplier or service requirements arise. It may also reflect a registry correction.
Developer servicesEngineeringMarket intelligence

Investigation hypotheses only. They are not evidence that any of these needs currently exist.

Units with a new planned date
8
Planned commissioning before
10 Jun 2027
Planned commissioning now
01 Mar – 19 Jul 2028
Shift per unit
+265 to +405 days

GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.

Grouping basisConservative group
These registrations are grouped for presentation because they share location/operator/category characteristics. GridGraph does not assert that this grouping represents one canonical development project.
Asset type (MaStR)
Horizontalläufer
Energy carrier (MaStR)
Wind
Operating status (MaStR)
In Planung

MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.

Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.

30 Sept 2026 → 1 Oct 2026

← Back to the brief · 2026-10-01