Commissioning delayed by up to 303 days — 2 units / 14.4 MW
Bad Wünnenberg, Nordrhein-Westfalen · Operator: Hirschweg GmbH & Co. KG
2 units · 14.4 MW
- MaStR evidence: HIGH
- Registry only · external search not performed
What changed
2 wind units registered a later planned commissioning date (+303 days).
Why this ranks high. Mid-sized 14.4 MW signal, unusually large schedule shift (303 days) and the registered operator is known. It may still reflect a registry correction rather than a new commercial need.
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Project development or development-management services
- Engineering and environmental services
Verify next
- Verify whether the date change reflects real rescheduling or a registry correction
- Check permitting and construction status
- Look for recent developer updates
Change summary
- Units with a new planned date
- 2
- Planned commissioning (same for every unit)
- Sept 2026 → Jul 2027 (+303 days)
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (2)
SEE937010566762View official MaStR record ↗SEE931278864707View official MaStR record ↗
Grouping basis
Supporting registry evidence: Shared unit-name pattern (“sintfeld…”); Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Planung
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.
Snapshot transition
30 Sept 2026 → 1 Oct 2026