Schedule change
63Lead relevance · High

Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Lead relevance63

  • Project scale (MW)14
  • Event type12
  • Lifecycle stage10
  • Recency8
  • Operator identified10
  • Multi-unit evidence5
  • Size of change4

Signal materiality48

  • Event type16
  • Size of change14
  • MW affected10
  • Units affected8

Commissioning delayed by up to 90 days — 3 units / 17.1 MW

Warnkenhagen, Mecklenburg-Vorpommern · Operator: Windpark Dalkendorf GmbH

3 units · 17.1 MW

Asset typeHorizontalläufer
Energy carrierWind
Registered operatorWindpark Dalkendorf GmbH

3 wind units registered a later planned commissioning date (+90 days).

Why this ranks high. Mid-sized 17.1 MW signal, 3 registrations moving together and the registered operator is known.

A registered schedule move of this size may reflect ordinary rescheduling and could shift when supplier or service requirements arise.
Developer servicesEngineeringMarket intelligence

Investigation hypotheses only. They are not evidence that any of these needs currently exist.

Units with a new planned date
3
Planned commissioning (same for every unit)
Aug 2026 → Oct 2026 (+90 days)

GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.

Grouping basisLikely site group
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
Asset type (MaStR)
Horizontalläufer
Energy carrier (MaStR)
Wind
Operating status (MaStR)
In Planung

MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.

Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.

22 Oct 2026 → 23 Oct 2026

← Back to the brief · 2026-10-23