66Lead relevance · High
Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Lead relevance66
- Project scale (MW)16
- Event type14
- Lifecycle stage10
- Recency7
- Operator identified10
- Multi-unit evidence6
- Size of change3
Signal materiality52
- Event type18
- Size of change12
- MW affected12
- Units affected10
Registered wind capacity increased (+4.8 MW) — 4 units / 27.2 MW
Obere Warnow, Mecklenburg-Vorpommern · Operator: KWE Windpark Herzberg Eins GmbH & Co. KG
4 units · 27.2 MW
- MaStR evidence: HIGH
- Registry only · external search not performed
What changed
4 wind units registered a capacity change; combined registered capacity moved from 22.4 MW to 27.2 MW (+4.8 MW).
Why this ranks high. Mid-sized 27.2 MW signal, 4 registrations moving together and the registered operator is known.
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Project development or development-management services
- Grid-connection / interconnection and electrical infrastructure services
- Engineering and environmental services
Verify next
- Check whether the change reflects a design or turbine-model change
- Compare with permit and grid-connection documents
- Look for recent developer announcements
Change summary
- Per-unit change
- 4 units changed from 5.6 MW to 6.8 MW each
- Combined registered capacity now
- 27.2 MW
- Combined change
- +4.8 MW (+21%)
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (4)
SEE914139723900View official MaStR record ↗SEE917552817324View official MaStR record ↗SEE923296331118View official MaStR record ↗SEE928352009284View official MaStR record ↗
Grouping basis
Supporting registry evidence: Shared unit-name pattern (“herzberg…”); Identical registered capacity; Identical registered change on every unit; Planned/commissioning dates within 72 days of each other
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Planung
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.
Snapshot transition
21 Oct 2026 → 22 Oct 2026