65Lead relevance · High
Lead relevance estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Lead relevance65
- Project scale (MW)16
- Event type12
- Lifecycle stage10
- Recency8
- Operator identified10
- Multi-unit evidence3
- Size of change6
Signal materiality63
- Event type16
- Size of change25
- MW affected12
- Units affected10
Commissioning delayed by up to 731 days — 4 units / 26.56 MW
Steinfurt, Nordrhein-Westfalen · Operator: Bürgerwind Wilmsberg GmbH & Co.KG
4 units · 26.56 MW
- MaStR evidence: HIGH
- Registry only · external search not performed
What changed
4 wind units registered a later planned commissioning date (+304 days to +731 days).
Why this ranks high. Mid-sized 26.56 MW signal, unusually large schedule shift (731 days) and the registered operator is known. The grouping evidence is limited; it may still reflect a registry correction rather than a new commercial need.
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Project development or development-management services
- Engineering and environmental services
Verify next
- Verify whether the date change reflects real rescheduling or a registry correction
- Check permitting and construction status
- Look for recent developer updates
Change summary
- Units with a new planned date
- 4
- Planned commissioning before
- 31 Dec 2026
- Planned commissioning now
- 31 Oct 2027 – 31 Dec 2028
- Shift per unit
- +304 to +731 days
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (4)
SEE916376876135View official MaStR record ↗SEE931586687135View official MaStR record ↗SEE934161154367View official MaStR record ↗SEE971728073242View official MaStR record ↗
Grouping basis
These registrations are grouped for presentation because they share location/operator/category characteristics. GridGraph does not assert that this grouping represents one canonical development project.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Planung
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.
Snapshot transition
22 Oct 2026 → 23 Oct 2026